The team should allow only senior managers to sign off deliverables
The team should get acceptance of project deliverables from the appropriate stakeholders at
The team should get acceptance of project deliverables from the users during a UAT phase at
Acceptance of any particular deliverable on the project is gained from all stakeholders at the
same time
B) Document guidelines
B,C
AC
The most complex tasks should be allocated by the Team Leader (ScrumMaster)
Q:4-Which of the following are roles in the Scrum framework?
Scrum Master
Product Owner
Team
Q:5-Which one of the following is a key feature that you would expect to find in an Agile
project?
System documentation created at the end of each increment, at the start of the deployment
User Stories held in a spreadsheet or specialist database, where full details of user
conversations are recorded for future purposes, like handover to maintenance or support
User Story cards containing only enough detail for planning and development, which will need
Product backlog
Product specification
Effort chart
Team backlog
Should allocate tasks to the team members each day at the stand-up meeting
Q:9-A major theme in Scrum is "inspect and adapt." What does it mean?
Scrum insists on auditors who frequently inspect the work of the team and suggest ways to
Scrum recommends that upper management inspect the Burndown charts and notes from the
daily scrums to find ways in which the team should adapt their practices to be more productive.
Scrum emphasizes taking a short step of development, inspecting both the resulting product
and the efficacy of current practices, and then adapting the product goals and process practices
Inspect and adapt refers to the ScrumMasters role in inspecting the work and writing stories
Q:10-Which one of the following statements is correct regarding quality of deliverables from
a Scrum Project?
The products produced by a scrum project should be cheaper than those produced by any
The products will be more expensive than by any other approach but will be top quality
The products will be fit for purpose, but may not do what the customer wanted
The products will be of appropriate quality, as the guidanceof the product owneris involved