Sei sulla pagina 1di 6

Recent Developments in Steel/Concrete Composite Slabs

Composite floor slabs are of interest to conceptual designers, The series will be presented in two parts: three articles in this
architects, engineers and contractors. They combine a variety issue of Structural Engineering International, and a second
of structural and economic advantages with the very real group in SEI 2/96. Authors for this series come from univer-
benefit of providing a stable, secure working platform dur- sities and the steel industry, primarily in Europe, where much
ing construction. The JABSE Publications Committee has work is currently underway to prepare European-wide
assembled a series of articles to give readers an in-depth recommendations for composite slab design and construc-
state-of-the-art insight into recent developments in the field. tion, but also from other regions of the world.

Composite Floor Slab Design and Construction


%Iichel Crisinel, Civil Eng.
Swiss Federal Institute of Technology, Lausanne. Switzerland
David O'Leary, Civil Eng.
University of Salford. Salford. UK

The Development made using corrugated sheets support- ity. coupled with a search by manufac-
of Composite Slabs ed by fabricated steel beams and cov- turers to use composite slabs with oth-
ered with a thin concrete slab contain- er framing materials, marked a new
ing a wire mesh (Fig. 1). The connec- period of expansion for the technique.
Composite slab systems were first de- tion between the sheet and the con- Steel decking is now used in conjunc-
veloped in the late 1930s for use in tall crete was provided by pure bond, tion with steel frames, but also is used
buildings. At that time, this technique except in cases of significantly high in concrete, prestressed concrete and
brought a considerable dead-load re- load conditions, where the mesh wires timber structures.
duction, and was essentially seen as a were welded to the top of the sheet The initial use of composite decks was
substitute for traditional reinforced corrugations.
concrete slabs. Because of their effi-
as a substitute for traditional rein-
ciency and advantages, composite
In the middle of the 1960s. the first forced concrete slabs. A composite
dovetailed profiled sheeting, originally floor is essentially an overlay of one-
slabs were soon applied to a wide designed for composite slabs, was in- wav structural elements: the primary
range of construction projects invari-
troduced from the USA to the Euro- beams, the secondary beams and the
ably based on structural steel framing
pean market, especially in Switzer- composite slab (Fig. 2). The slab spans
(highrise, lowrise and industrial build-
land [2]. During the late 1980s, the in- between the secondary beams. which
ings).
troduction of fast-track construction span transversely onto the primary
In Europe. the first composite slabs methods brought a new interest in beams: the latter in turn span to col-
appeared at the end of the 1950s [1]. steel design and consequently in com- umns spaced in the range of 6 to 9 m.
At that time, the construction was posite flooring. This change in mental- This set of load paths lends itself to

/r ituconcrcte
structural concrete

mesh reinforcement
// corrugated steel sheet

fusion welds

steel beam

Fig. 1: Earh' composite slab Fig. 2: Composite floor

Structural Engineering International 1/96 Reports 41


4 x 150 = 600 rectangular grids, and it is feasible to either the flanges and/or in parts of the
increase the span in at least one direc- webs. Shear essentially occurs near the
tion to 12, 15 or even 20 m and more. supports. The thin component plate
I I
elements which make up the decking
The overall depth of composite slabs
4 x 150 = 600 may buckle prior to yield under these
generally varies between SO and 250
compressive and shear stresses. there-
miii, with a bare metal thickness of by reducing the deckings load carry-
steel sheet between 0.7 and 1.5 mm. ing capacity and stiffness.
The robustness of composite floors
55 ÷ 4 x 150 + 95 = 750 identifies them for the construction of The current design procedures rely on
thin slabs (80 mm to 120 mm) with the concept of effective width to pro-
moderate loading or medium span vide a method for the calculation of
requirements. Thicker types of slabs this type of thin-walled member.
4 x 183 = 732 (130 mm to 250 mm) correspond to Clearly, the effective width of the com-
high loading or long span require- pression flange depends upon the
ments. maximum stress imposed on the
flange, which in turn depends on the
Purpose-designed decking to be used

iruLnr%
5 x 176 = 880 location of the neutral axis of the cross
in combination with concrete for com-
section. As the ineffective area of the
posite slabs is available and recom-
flange increases under increasing
mended (Fig. 3). It is not advisable to
use cladding or roofing profiles as bending moment, the neutral axis of
4 x 183 = 732 the profile is lowered and the extreme
-
composite slab decking.
fibre stresses will change accordingly.
A thin layer of galvanising is the nor- Iterative design becomes necessary for
mal protection against corrosion of strength and serviceability calcula-
decking. This is generally sufficient for tions. It is also possible to determine
4 x 200 = 800
A
the most common applications of com- design characteristics and methods by
posite floor slabs: in a dry interior at- tests.
mosphere. For more severe environ-
ments, other types of protection are
4 x 150 = 600 Permanent Stage
available and must be provided.
The behaviour of composite slabs dif-
fers from that of other similar forms of
Structural Behaviour composite construction, such as rein-
3 x 190 = 570
forced concrete and composite beams
Construction Stage of steel and concrete. In reinforced
concrete, composite action is achieved
At the construction stage, when the
concrete is wet, the decking alone re- by the adhesion capacity of the rein-
3 x 104 = 312 forcement due to the special profile of
sists the external loads. Its behaviour is
the bars used. This adhesion capacity,
then comparable to the behaviour of
verified by tests. is the same as the ulti-
the profiles for roofing.
mate resistance of the reinforcement
The decking is subjected mainly to and corresponds to the resistance in
Fig. 3: Examples of decking used in com- bending and shear. Compression due tension, assuming that the slab can al-
posite slabs to bending of the profile may arise in ways develop full resistance to bend-
ing. In composite beams, composite ac-
tion is achieved by connectors fixed to
the top flange of the steel beam. The
design of such connectors is based on
the assumption that the beam attains
ultimate bending resistance (full con-
nection). If there are fewer connectors
than required for full connection, then
the connection is partial. In this case,
the ultimate resistance to bending
essentially depends on the number of
connectors. the span of the beam and
the method of construction.
The behaviour of composite slabs with
decking has elements in common with
both reinforcement and beam systems:
decking with embossments or anchor-
ages (Fig. 4 compares to reinforce-
ment, whereas the decking itself is an
element with bending rigidity similar
Fig. 4: Tvpicalforn of connection in composite slabs to steel beams. The difference results
42 Reports Structural Engineering International 1/96
from the fact that decking, and similar-
ly the embossments. can be deformed.
Also. unlike reinforcement, decking
does not benefit from being totally em-
bedded in concrete. The deformation
depends on numerous parameters.
which makes the analysis of the actual
behaviour of composite slabs more
complicated.
In normal loading conditions. a com-
posite slab usually behaves as a deflection [mm]
cracked structure bending in the longi-
tudinal direction of the sheet:
— When loads are small, the slab
might be uncracked. The composite Fig. 5: Two typical behaviour modes of composite slabs
action between the parts is full, and
the stresses of the sheet and con-
crete are linearly dependent on the
strains. deflection. Concrete will creep over a Mode 2: Ductile Behaviour
— With an increase in load, the con-
period of several years. which gradual-
crete cracks in tension, which re- ly increases the deflections of the slab. The mechanical connection is capable
duces the stiffness of the structure. The way in which a composite slab be- of transferring the shear force until
This results in greater deflections of failure occurs. Failure is produced
haves during a loading test provides
the slab compared to the uncracked the basis for a design method for a par- either by bending. corresponding to
state. The adhesion between the ticular type of the sheet. As a conse- total connection, or by longitudinal
sheet and the concrete is capable of quence of the great variety of the sheet shear, corresponding to partial con-
transferring the shear force between nection.
types and of the lack of common ana-
the cracks. It is possible that adhe- lytical formulae, all sheet types must The behaviour may be classified as
sion will fail at the ends of the slab. be studied experimentally. Two modes ductile if the failure load exceeds the
— When a composite slab is experi- of behaviour can be described using load causing the first recorded end slip
mentally or accidentally subjected Fig. 5, based on a loading test where by more than 10%. If the maximum
to loads higher than the design the load was gradually increased by load is reached at a midspan deflection
loads, its behaviour greatly depends displacement-controlled jacks. Initially exceeding L150. the failure load shall
on the type of the steel sheet. In all the load-deflection curve is linear for be taken as the load at the midspan
composite slabs some relative slip all types of slabs which correspond deflection of L/50.
takes place between the steel and to the behaviour of a homogeneous
material bonded together by surface Otherwise, the behaviour is classified
concrete because the shear stresses as brittle (or non-ductile). The ductile
effects. namely, chemical adhesion and
between them exceed the strength or non-ductile behaviour of a compos-
friction.
of the connection or adhesion. ite slab max' be taken into account by
— Composite slabs have different fail-
After this initial load, the behaviour means of different partial safety fac-
of the slab is characterised by the two tors applied to the failure load or to
ure modes depending not only on
following modes: the load at a deflection of L150.
the sheet type but also on the geom-
etry of the structure. There are Mode 1: Brittle Behaviour
sheet types which fail quickly if the
load increases beyond the first slip The load suddenly decreases at the Design Considerations
load (brittle or non-ductile behav- point where the bond is broken and
iour). Some types of sheet can expe-
slip occurs. All the shear force must Decking and composite slabs predomi-
rience large deflections before fail- now be taken up by friction and em- nantly carry imposed vertical loads in
ure as the loads are gradually in- bossments. The drop-off of load de- bending and shear. Because both the
creased, although the relative slip pends on the efficiency of the mechan- decking and the composite slab do not
increases at the same time (ductile ical embossments. With further de- have the same geometry in each direc-
behaviour). The failure of a com- formation of the slab, the load again tion (non-isotropic) a two-way design
posite slab can occur at the interface increases slightly, without ever reach- is complicated. To simplify this situa-
between the steel sheet and the con- ing the level of the initial phase. The tion, design procedures consider only
crete as a shear bond failure or as mechanical connection between the the bending and shear resistances
material failure in one section. elements is incapable of achieving a along the longitudinal axis (in the di-
composite effect superior to that of rection of the ribs). This results in con-
When the slab has been supported by simple surface adhesion. It should be servative estimates of actual load car-
props during construction, it will im- noted that the decrease of the load is rying capacity. Most decking manufac-
mediately deflect on the removal of not due to the sudden opening of ten- turers have produced table or charts
the props. This initial loading can sion cracks in the concrete — because with all the necessary cross-sectional
cause cracking in the concrete. Moving this is prevented by the decking — but properties. This simplifies the design-
permanent and transient loads on the by the relative slip between the con- ers task as decking geometries can be
slab again causes an instant increase in crete and the decking. quite complicated.

Structural Engineering International 1/96 Reports 43


Composite slab design is normally rel- — self-weight of the slab's profiled Cracking of concrete can be taken into
atively simple and straight forward. sheeting and concrete (when prop- account in several ways:
Minimum slab thicknesses have been ping is used)
— The slab can be considered as a
established to ensure that significant — weight of floor finishes
beam with variable inertia, depend-
two-way load distribution can occur. — live loads.
ing on the reinforcement.
Non-standard bay geometries and For the serviceability limit state, long
large openings, however, require spe- — The moment at the supports can be
duration values of the loads should be
cial consideration, as do concentrated arbitrarily reduced (maximum re-
considered for the calculation of de-
heavy loads, cyclical and dynamic duction 30%, for example) and the
formations, taking into account creep span moments consequently in-
loads.
and shrinkage of the concrete.
creased.
Loads and Actions — The reinforcement over the sup-
When a profiled sheet acts as form-
Analysis ports can be totally neglected and
the slab considered as a series of
work, the following loads should be Analysis of a composite slab may be simply supported beams. Minimum
considered in the calculations, taking made according to one of the following reinforcement must always be
into account any support: placed over intermediate supports
methods:
— self-weight of the steel decking for serviceability reasons.
— linear elastic
— weight of the wet concrete
— linear elastic with moment redistri- The analysis will use one of the above
— ponding" effect. i.e., increased bution statical systems in conjunction with the
depth of concrete due to deflection — plastic, based on kinematic behav- design loads.
of the sheeting
iour (plastic hinges)
— construction loads
— higher order analysis which takes
— temporary storage loads, if applica- Serviceability Limit States
into account nonlinear material be-
ble.
haviour and the slippage between An analysis of the composite slab for
Self-weight of the profiled sheeting, the profiled sheeting and concrete calculating deflection may take advan-
weight of the wet concrete and the slab. tage of the following approximations:
ponding effect are considered as per- — The slab is comparable to a continu-
manent loads. The construction loads
Ultimate Limit States ous beam of constant inertia, equal
represent the weight of personnel and
in value to the average inertia of the
the concreting plant and take into ac- In most cases, analysis of composite
cracked and uncracked sections.
count any impact or vibration which slabs that are continuous over several
may occur during construction. spans is performed according to the — Long-term loading effects on the
When the steel and the concrete act elastic method for a slab of unit width concrete are taken into account
(1 m) comparable to a beam of con- using the variation of the modular
compositely, the following loads act on
stant inertia (Fig. 6). ratio EalEc.
the slab:

Verification
A distinctive characteristic of compos-
Loading(q) I I I I I I1 4 4 4 4 4 4 1 4 1 1 1 1 ite slabs is that two structural states are
considered: the temporary construc-
Statical _.A.
system
tion stage, when only the decking re-
£ .1
sists the applied loads, and the perma-
I nent stage. when the concrete is bond-
ed to the steel allowing composite
concrete cracking action. It is necessary to verify that
Deflected neither the ultimate nor the service-
ability limit states are exceeded in both
structural states.

Profiled sheeting as shuttering: Verifi-


cation at the ultimate and the service-
ability limit states is required for the
safety and serviceability of the profiled
Bending sheeting acting as formwork for the
wet concrete. The effects of props must
be taken into account in this design
situation.

Composite slabs: Verification at the ul-


timate and serviceability limit states is
required for the safety and the service-
Fig. 6: Analysis of a tst'o-span conposire slab ability of the composite slab after com-

44 Reports Structural Engineering International 1/%


posite behaviour has commenced and III I V II;ffl
any props have been removed.
I I

Ultimate Limit States


IV
The resistance of the decking, in tern-
porarv stage of construction, or the
composite slab, permanent stage, must
be sufficient to resist external actions.
Each section or member must be capa- Fig. 7: Critical sections
ble of resisting the internal forces de-
termined by the analysis of the struc-
ture.
taken to see that props do not produce Aid to Construction
When considering a limit state of an' marks on the sheet. The following
rupture or excessive deformation, it verifications should be made: Before concreting. the decking pro-
should be verified that: vides a safe working platform which
— deflection is within the admissible
limit speeds the construction process for
Sd R11 other trades. The steel deck combines
— marks on the sheet due to the props high rigidity and low weight, proper-
Design value Sd for the effects of ac- should be avoided, if aesthetically ties which considerably ease the trans-
tions should be determined for each necessary. portation and storage of the materials
load case from combination rules in- on site. Often one lorry is capable of
volving design values of actions. The When the steel and the concrete act
compositely, the behaviour of the com- carrying up to 1500 m2 of flooring.
most unfavourable combinations are A team of four workers can set up to
considered at each critical section of posite slab under permanent loads
and variable service loads must be 400 m2 of decking per day. Panels are
the structure (Fig. 7). light, prefabricated elements that are
checked. The following verifications
should be made: easily transported and set in place by
Design resistances Rd of a composite two or three workers.
slab may be calculated according to — Mid-span deflections occurring in
any appropriate method: sagging moment regions must not The fastening of the steel deck to the
exceed the limiting values. structure prior to concreting provides
— Flexure: If the slab is continuous, it a stiff and reliable floor bracing. Di-
may be considered for calculation — End-slip can occur on exterior spans aphragm action, which is produced by
purposes as a series of single spans which do not have end-anchorages. the capacity of the steel deck to resist
or as continuous spans. Bending re- End slip does not occur in internal distortion in its own plan readily obvi-
sistance may be calculated accord- spans because of the blocking effect ates the need for temporary horizontal
ing to plastic theory. Several restric- of the adjacent spans. The effect of bracing during construction.
tions to the use of plastic theory are end-slip at service load levels is to
given. Negative moment bending increase mid-span deflections. De- The steel deck, extending from beam
resistance is calculated according to termining whether slip is permissi- to beam, is permanent formwork to
the location of the neutral axis, ei- ble at service load levels should be the concrete; often there is no need for
ther above the decking or within the based on full-scale test results. temporary props. The soffit remains
rib height. clean after concreting. and the use of
— Concrete cracking: Given that there
— Vertical shear: Vertical shear resis- is a profiled sheet on the lower sur- colour-coated steel sheets can result in
tance — due to a line load or a sup- face of the slab, only concrete crack- an attractive finish to the ceiling. In ad-
port reaction — and the punching ing at the supports must be verified. dition, composite slabs act as a good
shear resistance due to a point load Minimum reinforcement is re- vapour barrier and generally have
must be calculated. quired. good fire resistance and acoustic prop-
erties.
— Longitudinal shear: Two design — Vibrations may be induced by heavy
methods may be used to calculate machinery or by the movements of The steel reinforcement provided by
the longitudinal shear capacity be- people and must be within accept- the cross section of the deck is usually
tween the concrete slab and deck- able limits. sufficient to resist positive moments.
ing. These are referred to as the Fabric reinforcement may be provided
shear-bond design method [3] and in the slab to resist shrinkage or tem-
the partial connection design meth- Advantages perature movements, or to provide
od[4]. continuity over intermediate supports
Steel deck profiles are manufactured (hogging moments). Composite action
under controlled, factory conditions. is obtained by the profile shape or by
Serviceability Limit States mechanical means provided by inden-
This allows the establishment of strict
When the profiled sheeting acts as quality procedures that lead to more tation or embossment of the steel pro-
formwork, the behaviour under its file.
precision on the construction site.
self-weight and the weight of the wet Lightweight composite floors are now The hollow shape of the profile steel
concrete must be checked. Deflection the preferred for a wide range of struc- decking produces a saving of concrete
should be within acceptable limits. For tures, offering the designer and the which is variable with the deck type
aesthetic reasons, care should also be client the following advantages: (up to 40 litres/rn2). This lowering of
Structural Engineering International 1/96 Reports 45
the slab self-weight produces a signifi- lution provides a flat appearance. a crete. The composite interaction be-
cant reduction of the dead load (up to minimum floor depth and built-in fire tween steel and concrete has become
1.0 kNIm2) carried by the structure protection for the floor beams. more efficient through the develop-
and the foundations. Composite slabs ment of new profiles with improved
An alternative form of slimfloor incor-
are usually thinner than conventional embossments and other methods of
porates light gauge steel decking as connection. There has been an in-
reinforced concrete slabs because the part of a composite system (Fig. 8). It
relatively high steel area in the deck crease in the spans which can be
retains the same benefits as standard achieved with little or no propping.
(between 1000 to 1500 mm2/m width)
slimfloor construction. with the ad- which can lead to the omission of sec-
works at lower stresses.
ditional advantages of lighter slab
ondary beams.
weight and greater ease of erection.
Service and Building Flexibility These advantages have resulted from
theoretical and experimental work
Composite floors are adaptable. The'
which has led to a good understanding
may readily be modified during the life in-Situ concrete of behaviour of the composite slabs up
of the building. This is especially true to failure. This information has been
when the slab is used with framed made available to profile manufactur-
structures. It is then always possible. ers and structural engineers have been
for example. to create a new staircase provided with simple and reliable de-
between two floors by simply adding sign methods.
the necessary trimmer beams.
In conclusion the best guarantee of
Many modern profiles have re-entrant quality is the external appearance of
features which allow the simple con- the product. This can be achieved with
nection of hanging devices. It is there- conscientious construction: From the
fore possible to suspend new cable net-
engineer who chooses the profile di-
works and piping without undertaking mensions and the lay-out to the profile
costly and noisy drilling during the Fig. 8: Shallow floor arrangement with coin- manufacturer and the contractor who
building's service life. posite slab (slimfloor)
places and fixes the sheeting and final-
Recent developments in communica- ly to the concrete contractor who fol-
tions and information technology have lows correct procedures during the
shown the importance of being able to Slimfloors made of composite slabs pouring and finishing of the slab.
quickly modify the services arrange- usually span between 5 to 9 m, the to- When the whole team follows the
ment in a building. The rapid pace of tal thickness of the slab usually set be- straight forward rules. composite
change in these areas makes it impossi- tween 180 and 350 mm. The use of floors will justly continue to be appre-
ble to predict precisely the future de- deep steel decking (Fig. 8) is therefore ciated by the architect and the client.
mands on a building, so flexibility is a an efficient solution, because the deck
significant asset of the composite floor rests directly on a place welded to the
slab system. bottom flange of the beam. The deck
openings are closed b stop-end acces-
Modern building usage demands that
sories which prevent concrete leakage.
it be possible to modify services in one
The top flange of the beam is covered
part of a building without disrupting by a concrete topping (70 to 100 mm)
the activities of other occupants. New
which houses the steel fabric for hog- References
services are generally accommodated
ging moments and the shear connec-
in the ceiling, under a false floor or in a [1] Le nouveau hdtirneni administratif de Ia
coffer box running along the walls. The
tors when the beam is designed for Société Nestlé a Vevev (Suisse). Acier-
composite action. This topping consti- Stahl-Steel. vol. 25. no. 12.
two latter solutions are limited to spe- pp. S13—519,
tutes the compression part of the slab Bruxelles, 1960.
cific services, and result in a loss of within the current span. The fire stabil-
space or in poor appearance. Compos-
ity of the beam is up to 1 hour and the [2] BRYL. S. Effet de liaison entre les to/es
ite floors are rarely used without a use of lightweight concrete allows d'acier et le béton dans It's planchers me-
false ceiling beneath the beams usually talliques nzixtes. Acier-Stahl-Steel. vol. 32.
spans of up to 6 m without props.
for aesthetic reasons. The gap between no. 10, pp. 453—49. Bruxelles. 1967.
the soffit and the bottom flange consti-
tutes an ideal zone in which new ser- [3] SCHUSTER. R. M. Composite Steel-
vices may be hidden.
Conclusions Deck-Reinforced Concrete Systems Failing
in Shear-Bond. 9th IABSE Congress
Composite floors using profiled steel Amsterdam, pp. 185—191. IABSE Congress
sheeting are a modern and efficient Report. Zurich. 1972.
Slimfloors form of construction. The technique
has been used for a number of years in [4] BODE. H.: MINAS. E: SAUER-
The slimfloor has been developed in Europe and the United States. There is BORN, I. Partial Connection Design of
the 1980s [5]. In this approach, the slab now increased interest in many other Composite Slabs. Structural Engineering
International. SE! 1/1996, IABSE. Zurich.
is contained within the beam depth. countries. This is principally due to the
1996. p. XX.
The original idea was to replace the cost advantages of the system. There is
secondary beams by precast hollow a reduction in overall structural weight [5] LAWSON, R. M.: LESKELA. M. Slim-
concrete elements spanning between because of the ribs in the profile that floor Construction. To be published in
primary beams without props. This so- eliminates significant volumes of con- SEI 2/1996.

46 Reports Structural Engineering International 1/96

Potrebbero piacerti anche