Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Foundation
Works and
Soil
Improvement
TSP-308 MPK Ferdinand Fassa
What do we want from foundation?
• Settlement
• Slope stability
• Liquefaction
(after earthquake)
• Sinkhole
• scouring / abrasion
Differential
No Settlement Total Settlement Settlement
effect of liquefaction
landslide (slope Stability)
sinkhole
scouring
scouring / abrasion (?)
Shallow Foundation
Spread footings
• Wall footings
• Mat foundations / Raft foundations
Blinding
(sand, granular, lean concrete)
Construction sequences of shallow foundations
crosslot bracing
rakers
tiebacks
construction of diaphragm
Construction of slurry walls
INSERTING PORUING
REINFORCING CONCRETE
STEEL CAGE INTO INTO TRENCH
TRENCH
SLURRY
PUMPED COMPATED
IN REINFORCED
CONCRETE PANEL
EXCAVATING SOIL
SLURRY
PUMPED
OUT
Add bentonite
while retracting
steel casing /
pouring concrete
Bored Pile – cutting excess pile
Pile Foundation & Pile Driving Equipment
Test Pile
Test type
• Load Test w/ Reaction Piles
– To determine load capacity with respect to pile
penetration (settlement)
• Standard Penetration Test
– To determine the load applied for hammering
Pile loading test
Kenteledge
Secondary beam of cast-iron
block of
concrete
Main beam
Timber crib
Load cell
REACTION BEAMS
HYDRAULIC JACK
DIAL GAUGE
FIXED PLATFORM
29
installation of bulb piles (franki piles)
drive steel casing into final depth
Vertical
Aft batter
Forward batter
Operating Mechanism of Diesel Hammer
Pile Driving Calculation
• Drop Hammer 2W H
R
S 0.1
2W H
h • Single-Acting Hammer R
S 0.1
2E
R • Double-Acting Hammer R
S 0.1
R = safe load on pile (lbs)
s W = weight of falling mass (lbs)
Wh Rs H = height of free falling mass (ft)
E = total energy of Ram at the bottom of its down-
strokes (ft-lbs)
S = average penetration per blow for last 6 blows (in)
Pile Load Capacity
2E Wr K .Wp
R x
S 0.1 Wr Wp
R = safe load (lbs)
S = average penetration per blow, last 6 blows (in.)
E = energy of hammer (ft-lbs)
Wr = weight of hammer ram (lbs)
Wp = weight of pile, incl. driving apparatus (lbs)
K = coefficient of restitution
K = 0.2 for piles weighting 50 lbs or less
K = 0.4 for piles weighting 50 lbs to 100 lbs
K = 0.6 for piles weighting more than 100 lbs
Recommended Hammer Sizes
B = 32 / 4 = 8 blows/cu.ft
2
4 18 8 24 3
R
15
Bored pile construction
• Excavate soil using
Concrete auger/drilling bucket
pump
• Install (steel) casing
install • Inject bentonite mix to
reinforcement stabilize
• Insert reinforcement (as
required)
excavation and
pour • Insert tremie pipe
steel casing
concrete
• Place concrete while
add
pumping out bentonite
bentonite
underpinning
The installation of temporary or permanent support to an existing foundation to
provide either additional depth or an increase in bearing capacity
Performance of foundation is influenced by:
– Movement during construction
– Movement after construction
– Response to ground movement
underpinning
underpinning
Jacking up
Improving non-cohesive soil
42
Ground Improvement Method
vibrator
casing
sand
driven point
(closed) driven point
(open)
Quarry run/
Seabed kerikil/sand bags Seabed
Cerucuk Bamboo
Spasi = 1 m, L = 6 m