• The Contractor shall prepare an integrated plan showing the arrangements to be made for accommodating road and
pedestrian traffic, at individual construction sites and continuously along the alignment, including arrangements being
implemented by other Contractors, to smooth traffic operations and for the safety of both construction workers and
road users
The Plan shall consider different measures such as:
• The use of suitable construction sequences and methods at station sites to reduce the period of disruption to road
users
• proper phasing and timing of traffic signals
• modifications to intersection geometry
• changes in lane usage
• parking prohibitions
• re-location of bus stops
• maintenance of existing roads within the vicinity of the Works areas
• reducing width of footpaths and median
• right-turn prohibition
• work site access management
• minimising the duration of any road closure
• reversible lane operations
• modification of roadway alignment affected by the construction, which shall be in conformance with the requirements
and regulations defined by the relevant authorities; other engineering traffic measures as may be applicable.
MITIGATION OF TRAFFIC DISTURBANCES
• The Contractor shall manage the vehicular and pedestrian right of way. To maintain essential traffic requirements, as these may
influence the construction process.
• The Contractor shall include local traffic diversion routes and assess traffic impacts . Signage layout shall be included for traffic
diversions.
• Traffic diversion schemes to adjacent roadways shall be developed with quantitative justifications.
Other considerations include:
• The minimum lane widths for fast traffic and mixed traffic shall follow the regulations of authorities.
• Any roads or intersections that have no alternative access shall not be fully closed for construction
• Emergency access to all properties shall be maintained at all times.
• Access to business premises and property shall be maintained to the extent that normal activities are not seriously disrupted.
• Where existing footbridges and underpasses are demolished or closed, provisions shall be made for pedestrian crossing to minimise
the conflicts between a traffic lane.
• Construction traffic shall be separated from other traffic wherever possible
• Any traffic related facilities (bus stops, parking, etc.) which are affected by the construction works shall be maintained or relocated to
appropriate locations.
• Motorists, pedestrians, workmen, plant and equipment shall be protected from accident at all times.
• The Contractor’s temporary traffic management plan shall be coordinated with the Works and traffic arrangements of other Contractors
where these interface with this Contract.
• Roadway designs, traffic management schemes, and installation of traffic control devices shall be in conformance with the
requirements and regulations defined by the relevant authorities
• Where applicable, utility diversions shall be incorporated in the traffic management plan
.
BROAD METHODOLOGY FOR TRAFFIC MANAGEMENT
• Gabion Wall shall be constructed on the edge of Nallah to support 2 Lane road on west. 1st 100 m shall be
SECON commissioned in 1st phase to allow construction of North Head Wall Piles in phased manner. In second Phase
D entire 2 lane traffic shall be diverted over Road over Gabion Wall.
STAGE
THIRD • Simultaneously decking is provided towards Building side for 2 lane width as shown in fig.
STAGE
FIFTH • Traffic marshals and proper traffic signage’s are deployed to implement the diversion as shown in fig.
STAGE
SIXTH • Remaining half traffic from Mahim-Sion link road is diverted on decking provided in one go.
STAGE
SEVEN • Finally full station is taken up for excavation and other activities
TH
STAGE
BKC STATION
Traffic diversion in 4 phases as per details appended in Stage 1:
the following sketches shall done which are self- i) 2 Lane Road flexible pavement is developed between
explanatory. Impact of upcoming Mumbai Metro Capping Beam & Millenium building along grid 18-24.
Line-2B has not been considered, as there is no ii) Sant Dyaneshwar Road is diverted over this newly
official intimation & instruction till data date. constructed road.
Stage 3:
Stage 2: i) Divert East Bound 3 Lane traffic on South side 3 Lane decking.
i) Construct 3 Lane Road near Grid 15 along East West 6 lane corridor. ii) 3 Lane Road along grid 17-18 is occupied & Barricaded.
ii) West Bound 3 Lane Traffic is diverted over newly constructed Road. iii) Complete 3 Lane Decking with Utility Bridge Installation @ Grid 18.
iii) 3 Lane road is along grid 15-16 is occupied for decking Works iv) Divert Utility over Utility Bridge ( 1200mm dia Storm Water Line, 450mm
iv) Completion of 3 lane Decking & associated works. sewer line, 300mm MGL Line & OFC cables).
v) Divert All 6 Lane Traffic on 6 Lane Decking.
vi) Pedestrian Shall move along 1m walkway along decking.
vii) Excavation beneath decking shall be taken after 6 lane diversion
VIDYANAGRI STATION
Traffic diversion in 1 phase as per details appended in the
following sketches shall done which are selfexplanatory.
Details are appended in the sketch shown below
Phase1:
• Secant pile shall be completed before
diverting Road over station Grid 19-20.
• Barricading shall be done on both
sides of pavement.
• Trial run shall be tested before
diverting Sharda Devi Road along Mithi
River Nallah.
• Deploy traffic marshals and divert the
traffic on parallel road towards nallah
side.
Phase -2:
After TBM works completion from North
Shaft of Vidya Nagari 2 lanes of road shall
be diverted along North Shaft. 1 Lane
shall ply over decking on North Shaft
SANTACRUZ STATION
1. Barricade on both sides of 2 lane carriageway provided beneath the flyover.
2. Demolish the footpath and provide 1 lane carriageway for heavy vehicles.
3. Bus stops to be relocated as shown in above figure.
4. Deploy traffic marshals & divert the 2 lane traffic on carriageway provided below
Flyover.
5. 4 Lane shall be provided towards hutment side.
6. Take up the full station for further activities.
ensure the safety
of road users in
the impacted area
construction of the
stations have to be done facilitate access to
in phases to ensure that the construction site,
the traffic management and to maintain
plan provides the reasonable
minimum number of two construction
traffic lanes in each progress
direction