OFFICE MEMORANDUM

No.DGW/CON/237 A
ISSUED BY AUTHORITY OF DIRECTOR GENERAL OF WORKS
NIRMAN BHAWAN, NEW DELHI DATED: 31.12.2008

Subject: Amendment of Clause 10C, 10CA and 10CC of General Conditions


of Contracts 2008.

The modifications done vide O.M No DGW/CON/237 dt.14.10.2008 to clause


10C, 10CA & 10CC are hereby withdrawn with immediate effect. The remodified
provisions of these clauses shall be as under which shall be applicable only in
respect of the new contracts and shall not be applicable to contracts already drawn
or where tenders have already been received and not finalized.

Existing provision Modified provision


Page 26 of GCC 2008/O.M. No. Page 26 of GCC 2008
CON/236 dt. 31.7.08
Clause 10C – Payment on account of Clause 10C – Payment on account of
increase in prices/wages due to increase in prices/wages due to statutory
statutory order (s) order (s)
If after submission of the tender, the If after submission of the tender, the price
price of any material incorporated in of any material incorporated in the works
the works (not being a material (excluding the materials covered under
supplied from the Engineer-in-Charge’s Clause 10CA and not being a material
stores in accordance with Clause 10 supplied from the Engineer-in-Charge’s
thereof) and/or wages of labour stores in accordance with Clause 10
increases as a direct result of the thereof) and/or wages of labour increases
coming into force of any fresh law, or as a direct result of the coming into force
statutory rule or order (but not due to of any fresh law, or statutory rule or order
any changes in sales tax/VAT) and (but not due to any changes in sales
such increase in the price and/or tax/VAT) beyond the prices/wages
wages prevailing at the time of the prevailing at the time of the last
last stipulated date for receipt of the stipulated date of receipt of tenders
tenders including extensions if any including extensions, if any, for the

CON237A
Page 1
for the work, and the contractor work during contract period including
thereupon necessarily and properly the justified period extended under the
pays in respect of that material provisions of clause 5 of the contract
(incorporated in the works) such without any action under clause 2, then
increased price and/or in respect of the amount of the contract shall
labour engaged on the execution of accordingly be varied and provided
the work such increased wages, then further that any such increase shall be
the amount of the contract shall limited to the price/wages prevailing at
accordingly be varied and provided the time of stipulated date of
further that any such increase shall not completion or as prevailing for the
be payable if such increase has period under consideration, whichever
become operative after the stipulated is less.
date of completion of the work in
question.
If after submission of the tender, the If after submission of the tender, the price
price of any material incorporated in of any material incorporated in the works
the works (not being a material (excluding the materials covered under
supplied from the Engineer-in-Charge’s Clause 10CA and not being a material
stores in accordance with Clause 10 supplied from the Engineer-in-Charge’s
thereof) and/or wages of labour is stores in accordance with Clause 10
decreased as a direct result of the thereof) and/or wages of labour as
coming into force of any fresh law or prevailing at the time of last stipulated
statutory rules or order (but not due to date of receipt of tender including
any changes in sales tax/VAT) and extensions, if any, is decreased as a
such decrease in the prices and/or direct result of the coming into force of
wages prevailing at the time of any fresh law or statutory rules or order
receipt of the tender for the work. (but not due to any changes in sales
Government shall in respect of tax/VAT) , Government shall in respect
materials incorporated in the works (not of materials incorporated in the works
being material supplied from the (excluding the materials covered under
Engineer-in-Charge’s stores in Clause 10CA and not being material
accordance with Clause 10 hereof) supplied from the Engineer-in-Charge’s
and/or labour engaged on the execution stores in accordance with Clause 10
of the work after the date of coming hereof) and/or labour engaged on the
into force of such law statutory rule or execution of the work after the date of
order be entitled to deduct from the coming into force of such law statutory
dues of the contractor, such amount as rule or order be entitled to deduct from
shall be equivalent to the difference the dues of the contractor, such amount as
between the prices of the materials shall be equivalent to the difference
and/or wages as prevailed at the time of between the prices of the materials and/or
CON237A
Page 2
the last stipulated date for receipt of wages as prevailed at the time of the last
tenders including extensions if any for stipulated date for receipt of tenders
the work and the prices of materials including extensions if any for the work
and/or wages of labour on the coming and the prices of materials and/or wages
into force of such law, statutory rule or of labour on the coming into force of such
order. law, statutory rule or order. This will be
applicable for the contract period
including the justified period extended
under the provisions of clause 5 of the
contract without any action under
clause 2
The contractor shall, for the purpose Engineer-in-Charge may call books of
of this condition, keep such books of account and other relevant documents
account and other documents as are from the contractor to satisfy himself
necessary to show the amount of any about reasonability of increase in
increase claimed or reduction prices of materials and wages.
available and shall allow inspection
of the same by a duly authorized
representative of the Government
and further shall, at the request of
the Engineer-in-Charge may require
any documents so kept and such
other information as the Engineer-in-
Charge may require.
The contractor shall, within a The contractor shall, within a reasonable
reasonable time of his becoming aware time of his becoming aware of any
of any alteration in the price of any alteration in the price of any such
such materials and/or wages of labour, materials and/or wages of labour, give
give notice thereof to the Engineer-in- notice thereof to the Engineer-in-Charge
Charge stating that the same is given stating that the same is given pursuant to
pursuant to this condition together with this condition together with all
all information relating thereto which information relating thereto which he may
he may be in position to supply. be in position to supply.
For this purpose, the labour component For this purpose, the labour component of
of the work executed during any the work executed during period under
period shall be the percentage as consideration shall be the percentage as
specified in Schedule F, of the value of specified in Schedule F, of the value of
work done during that period. work done during that period and the
increase/decrease in labour shall be
considered on the minimum daily
CON237A
Page 3
wages in rupees of any unskilled adult
male mazdoor, fixed under any law,
statutory rule or order.

Page 26 of GCC 2008 Page 26 of GCC 2008


Clause 10 CA Clause 10 CA
Payment due to variation in prices of Payment due to variation in prices
materials after receipt of tender of materials after receipt of tender
If after submission of the tender, the price If after submission of the tender, the
of materials specified in Schedule F price of materials specified in
increases/decreases beyond the price(s) Schedule F increases/decreases
prevailing at the time of the last stipulated beyond the price(s) prevailing at the
date for receipt of tenders (including time of the last stipulated date for
extensions, if any) for the work, then the receipt of tenders (including
amount of the contract shall accordingly extensions, if any) for the work, then
be varied and provided further that any the amount of the contract shall
such variations shall be effected for accordingly be varied and provided
stipulated period of contract including the further that any such variations shall
justified period extended under the be effected for stipulated period of
provisions of Clause 5 of the contract contract including the justified period
without any action under Clause 2. extended under the provisions of
Clause 5 of the contract without any
action under Clause 2.
However for work done/during the However for work done during the
justified period extended as above, it will justified period extended as above, it
be limited to indices prevailing at the time will be limited to indices prevailing at
of stipulated date of completion or as the time of stipulated date of
prevailing for the period under completion or as prevailing for the
consideration, whichever is less. period under consideration,
whichever is less.
The increase/decrease in prices shall be The increase/decrease in prices of
determined by the All India Wholesale cement, steel reinforcement and
Price Indices of materials as published by structural steel shall be
Economic Advisor to Government of determined by the Price indices
India, Ministry of Commerce and Industry issued by the Director General
and base price for materials as issued (Works), CPWD. For other items

CON237A
Page 4
under the authority of Director General provided in the Schedule ‘F’, this
(Works), CPWD as valid on the last shall be determined by the All India
stipulated date of receipt of tender, Wholesale Price Indices of materials
including extension if any and for the as published by Economic Advisor to
period under consideration. In case, Government of India, Ministry of
price index of particular material is not Commerce and Industry and base
issued by Ministry of Commerce and price for cement, steel
Industry, then the price index of nearest reinforcement and structural steel
similar material as indicated in Schedule as issued under the authority of
‘F’ shall be followed. Director General (Works) CPWD
applicable for Delhi including
Noida, Gurgaon, Faridabad &
Ghaziabad and for other places as
issued under the authority of
Zonal Chief Engineer, CPWD and
base price of other materials
issued by concerned Zonal Chief
Engineer as indicated in Schedule
‘F’ as valid on the last stipulated
date of receipt of tender, including
extension if any and for the period
under consideration. In case, price
index of a particular material is not
issued by Ministry of Commerce and
Industry, then the price index of
nearest similar material as indicated
in Schedule ‘F’ shall be followed.
The amount of the contract shall The amount of the contract shall
accordingly be varied for all such accordingly be varied for all such
materials and will be worked out as per materials and will be worked out as
the formula given below for individual per the formula given below for
material:- individual material:-

V = P x Q x CI-CIo V = P x Q x CI-CIo
CIo CIo
Where, where,
V = Variation in material cost i.e. V = Variation in material cost i.e.
increase or decrease in the amount in increase or decrease in the amount
rupees to be paid or recovered. in rupees to be paid or recovered.
P = Base Price of material as issued P = Base Price of material as issued
CON237A
Page 5
under authority of DG(W) CPWD valid at under the authority of DG(W),CPWD
the time of the last stipulated date of or concerned Zonal Chief
receipt of tender including extensions, if Engineer as indicated in Schedule
any, ‘F’ valid at the time of the last
stipulated date of receipt of tender
including extensions, if any,
Q = Quantity of material used in the Q = Quantity of material brought at
works since previous bill. site for bonafide use in the works
since previous bill.
CIo = All India Wholesale Price Index for CIo = Price index for cement, steel
the material as published by the reinforcement bars and structural
Economic Advisor to Government of steel as issued by the DG(W),
India, Ministry of Industry and Commerce CPWD as valid on the last
as valid on the last stipulated date of stipulated date of receipt of
receipt of tenders including extensions, if tenders including extensions, if
any. any. For other items, if any,
provided in Schedule ‘F’, All India
Wholesale Price Index for the
material as published by the
Economic Advisor to Government of
India, Ministry of Industry and
Commerce as valid on the last
stipulated date of receipt of tenders
including extensions, if any.

CI = All India Wholesale Price Index for CI = Price index for cement, steel
the material for period under reinforcement bars and structural
consideration as published by Economic steel as issued under the authority
Advisor to Government of India, Ministry of DG(W), CPWD for period under
of Industry and Commerce consideration. For other items, if
any, provided in Schedule ‘F’, All
India Wholesale Price Index for the
material for period under
consideration as published by
Economic Advisor to Government of
India, Ministry of Industry and
Commerce.
Note -
(In respect of the justified period (i) In respect of the justified period
extended under the provisions of clause 5 extended under the provisions
CON237A
Page 6
of the contract without any action under of clause 5 of the contract
clause 2, the index prevailing at the time without any action under clause
of stipulated date of completion or the 2, the index prevailing at the
prevailing index of the period under time of stipulated date of
consideration, whichever is less, shall be completion or the prevailing
considered). index of the period under
Provided always that provisions of the consideration, whichever is less,
preceding Clause 10C shall not be shall be considered.
applicable in respect of Materials covered Provided always that provisions
in this Clause. of the preceding Clause 10C
shall not be applicable in
respect of Materials covered in
this Clause.
(ii) If during progress of work or
at the time of completion of
work, it is noticed that any
material brought at site is in
excess of requirement, then
amount of escalation if paid
earlier on such excess
quantity of material shall be
recovered on the basis of
cost indices as applied at the
time of payment of escalation
or as prevailing at the time of
effecting recovery, whichever
is higher.

Page 27 of GCC 2008 Page 27 of GCC 2008


Clause 10 CC Clause 10 CC
Payment due to increase/decrease in Payment due to increase/decrease
Prices/Wages after Receipt of Tender in Prices/Wages (Excluding
for Works materials covered under clause 10
If the prices of materials (not being CA) after Receipt of Tender for
materials supplied or services rendered Works
at fixed prices by the department in If the prices of materials (not being
accordance with clause 10 & 34 thereof) materials supplied or services
and/or wages of labour required for rendered at fixed prices by the
execution of the work increase, the department in accordance with
contractor shall be compensated for such clause 10 & 34 thereof) and/or
CON237A
Page 7
increase as per provisions detailed below wages of labour required for
and the amount of the contract shall execution of the work increase, the
accordingly be varied, subject to the contractor shall be compensated for
condition that such compensation for such increase as per provisions
escalation in prices and wages shall be detailed below and the amount of the
available only for the work done during contract shall accordingly be varied,
the stipulated period of the contract subject to the condition that such
including the justified period extended compensation for escalation in prices
under the provisions of clause 5 of the and wages shall be available only for
contract without any action under clause the work done during the stipulated
2. However, for the work done during the period of the contract including the
justified period extended as above, the justified period extended under the
compensation as detailed below will be provisions of clause 5 of the contract
limited to prices/wages prevailing at the without any action under clause 2.
time of stipulated date of completion or as However, for the work done during
prevailing for the period under the justified period extended as
consideration, whichever is less. No above, the compensation as detailed
such compensation shall be payable for a below will be limited to prices/wages
work for which the stipulated period of prevailing at the time of stipulated
completion is equal to or less than the date of completion or as prevailing
time as specified in Schedule F. Such for the period under consideration,
compensation for escalation in the prices whichever is less. No such
of materials and labour, when due, shall compensation shall be payable for a
be worked out based on the following work for which the stipulated period
provisions:- of completion is equal to or less than
the time as specified in Schedule F.
Such compensation for escalation in
the prices of materials and labour,
when due, shall be worked out based
on the following provisions:-

i) The base date for working out such i) The base date for working out
escalation shall be the last stipulated date such escalation shall be the last
of receipt of tenders including extension, stipulated date of receipt of
if any tenders including extension, if any

ii) The cost of work on which ii) The cost of work on which
escalation will be payable shall be escalation will be payable shall
reckoned as below :- be reckoned as below :-
a) Gross value of work done up to this a) Gross value of work done up to
CON237A
Page 8
quarter : (A) this quarter : (A)
b) Gross value of work done up to the b) Gross value of work done up to
last quarter : (B) the last quarter : (B)
c) Gross value of work done since c) Gross value of work done since
previous quarter(A-B) : (C) previous quarter(A-B) : (C)
d) Full assessed value of Secured d) Full assessed value of Secured
Advance fresh paid in this quarter : Advance(excluding materials
(D) covered under clause 10 CA)
fresh paid in this quarter : (D)
e) Full assessed value of Secured e) Full assessed value of Secured
Advance recovered in this quarter: (E) Advance(excluding materials
covered under clause 10 CA)
recovered in this quarter: (E)
f) Full assessed value of Secured f) Full assessed value of Secured
Advance for which escalation is Advance for which escalation is
payable in this quarter (D-E) : (F) payable in this quarter (D-E):
(F)
g) Advance payment made during this g) Advance payment made during
quarter : (G) this quarter : (G)
h) Advance payment recovered during h) Advance payment recovered
this quarter : (H) during this quarter : (H)
i) Advance payment for which escalation i) Advance payment for which
is payable in this quarter (G-H) : (I) escalation is payable in this
quarter (G-H) : (I)
j) Extra items paid as per Clause 12 j) Extra items paid as per Clause 12
based on prevailing market rates based on prevailing market rates
during this quarter : (J) during this quarter : (J)
Then , M=C+ F+ I – J Then , M=C+ F+ I – J
N = 0.85 M N = 0.85 M
k) Less cost of material supplied by the k) Less cost of material supplied by
department as per Clause 10 and the department as per Clause 10
recovered during the quarter : (K) and recovered during the quarter
: (K)
l) Less cost of service rendered at fixed l) Less cost of service rendered at
charges as per Clause 34 and fixed charges as per Clause 34
recovered during the quarter : (L) and recovered during the quarter:
(L)

Cost of work for which escalation is Cost of work for which escalation is
applicable : applicable :
CON237A
Page 9
W = N-(K+L) W = N-(K+L)

iii) Components for cement, steel iii) Components for materials


materials, Labour, P.O.L. etc.. shall (except cement, reinforcement
be pre-determined for every work bars, structural steel or others
and incorporated in the conditions of materials covered under
contract attached to the tender Clause 10 CA) , Labour, P.O.L.
papers included in Schedule ‘E’. etc.. shall be pre-determined for
The decision of the Engineer- in- every work and incorporated in
Charge in working out such the conditions of contract
percentage shall be binding on the attached to the tender papers
contractors included in Schedule ‘E’. The
decision of the Engineer-in-
Charge in working out such
percentage shall be binding on
the contractors.
iv) The compensation for escalation for iv) The compensation for escalation
cement, steel and P.O.L. shall be for other materials (excluding
worked as per the formula given cement, reinforcement bars ,
below structural steel or other
materials covered under clause
10 CA) and P.O.L. shall be
worked as per the formula given
below:-

a) Adjustment for component of ‘cement’ (a) DELETED

Vc = W x Xc x CI – CIo
CIo
………………………………………………
…………………………………..
b) Adjustment for component of ‘steel’ (b) DELETED
Vs = W x Xs x SI-SIo
100 SIo
.. ……………………………………………
…………………………………..

c) Adjustment for civil component c) Adjustment for civil component


(except cement and steel)/ electrical (except cement, Structural
CON237A
Page 10
component of construction ‘Materials’ steel, reinforcement bars and
other materials covered under
clause 10CA) / electrical
component of construction
‘Materials’
Vm= W x Xm x MI-MIo Vm= W x Xm x MI-MIo
100 MIo 100 MIo
Vm = Variation in material cost i.e. Vm = Variation in material cost i.e.
increase or decrease in the increase or decrease in the
amount in rupees to be paid or amount in rupees to be paid or
recovered. recovered.
W = Cost of work done worked out W = Cost of work done worked out
as indicated in sub –para (ii) of as indicated in sub–para (ii) of
Clause 10CC. Clause 10CC.
Xm = Component of ‘materials’ Xm = Component of ‘materials’
expressed as percent of the total (except cement, Structural
value of work. steel, reinforcement bars
and other materials covered
under clause 10CA)
expressed as percent of the
total value of work.
MI = All India Wholesale Price Index for MI = All India Wholesale Price Index
civil component/electrical component* of for civil component/electrical
construction material as worked out on component* of construction material
the basis of All India Wholesale Price as worked out on the basis of All
Index for individual Commodities/Group India Wholesale Price Index for
items for the period under consideration individual Commodities/Group items
as published by Economic Advisor to for the period under consideration as
Govt. of India, Ministry of Industry & published by Economic Advisor to
Commerce and applying weightages to Govt. of India, Ministry of Industry &
the individual Commodities/ Group Items. Commerce and applying weightages
( In respect of the justified period to the individual Commodities/ Group
extended under the provisions of clause 5 Items. ( In respect of the justified
of the contract without any action under period extended under the provisions
clause 2, the index prevailing at the time of clause 5 of the contract without
of stipulated date of completion or the any action under clause 2, the index
prevailing index of the period under prevailing at the time of stipulated
consideration, which ever is less shall be date of completion or the prevailing
considered). index of the period under
consideration, which ever is less
CON237A
Page 11
shall be considered).
MIo = All India Wholesale Price Index MIo = All India Wholesale Price
for civil component/electrical component * Index for civil component/electrical
of construction material as worked out on component * of construction material
the basis of All India Wholesale Price as worked out on the basis of All
Index for individual Commodities/Group India Wholesale Price Index for
items valid on the last stipulated date of individual Commodities/Group items
receipt of tender, including extension, if valid on the last stipulated date of
any, as published by the Economic receipt of tender, including extension,
Advisor to Govt. of India, Ministry of if any, as published by the Economic
Industry & Commerce and applying Advisor to Govt. of India, Ministry of
weightages to the individual Industry & Commerce and applying
Commodities/Group items. weightages to the individual
Commodities/Group items.

*Note : relevant component only will be *Note : relevant component only will
applicable. be applicable.

(d) Adjustment for component of (d) Adjustment for component of


‘POL’…………………..tender including ‘POL’…………………..tender
extension, if any. including extension, if any.
(v) The following principles………… (v) The following principles…………
…….. falling within that period. …….. falling within that period.
(vi) The component for escalation (vi) The component for escalation
…………………..receipt of tender …………………..receipt of tender
including extension, if any. including extension, if any.
(vii) The following principles…………….. (vii) The following principles………
………….. on the labour component. ……………on the labour component.

(viii) In the event of the price…………….. (viii) In the event of the


……………………………..binding on the price……………..
contractor. …………………………..binding on
the contractor.

ix) Provided always that the provision ix) Provided always that-:
of the preceding clause 10C and (a) Where provisions of clause
10CA shall not be applicable for 10CC are applicable,
contracts where provisions of this provisions of clause 10C will
clause are applicable but in cases not be applicable but
where provisions of this clause are provisions of clause 10CA
CON237A
Page 12
not applicable, the provisions of will be applicable.
Clause 10 C and 10 CA will become (b) Where provisions of clause
applicable. 10CC are not applicable,
provisions of clause 10C
and 10CA will become
applicable.

Page 92 of Proforma of Schedules Page 92 of Proforma of Schedules


(Schedule A to F) (Schedule A to F)
Schedule ‘E’ Schedule ‘E’
Schedule of component of Cement, Schedule of component of other
Steel, other materials, Labour etc., for materials, Labour, POL etc., for price
price escalation escalation

Clause 10 CC
Component of cement – Xc
expressed as percent of
total value of work …………% DELETED

Component of Steel – Xs
expressed as percent of
total value of work …………% DELETED

Component of civil - Xm Component of civil - Xm


(Except cement & steel) (Except materials
/ Electrical construction covered under
materials expressed as clause 10CA) /
percent of total value Electrical construction
of work …………% materials expressed
as percent of total
value of work ..……%

Component of Labour Component of Labour


expressed as percent of expressed as percent of
total value of work Y……….% total value of work Y……….%

Component of POL Component of POL


CON237A
Page 13
expressed as percent of expressed as percent of
total value of work Z……….% total value of work Z……….%

Existing Provision

Page 94 of GCC 2008


Schedule ‘F’
Clause 10CA
Materials Covered under this clause Nearest Materials for which All
India Wholesale Price Index is to be
followed.
1 ……………………………………… ………………………………………
2 ……………………………………… ………………………………………
3 ……………………………………… ……………………………………….

Modified Provision

Clause 10CA Nearest Materials (other than Base Price of all


Materials Covered cement, reinforcement bars the materials
under this clause : and structural steel)for which covered under
All India Wholesale Price Index
clause 10 CA *
to be followed:

1 ………………………... 1 ………………………... 1 …………………...


2 ………………………... 2 ………………………... 2 …………………...
3 ………………………... 3 ………………………... 3 …………………...
4 ……………………
4 ………………………...

* Base price of all the materials covered under clause 10 CA is to be


mentioned at the time of approval of NIT.

CON237A
Page 14
Superintending Engineer (C&M)

Issued from file No. CSQ/CM/C/37(6)/2008