Sei sulla pagina 1di 9

Further revisions were made to the standard in 1975.

Additional sizes and


thicknesses
of steel pipe that had been added to API specifications were added to Table 2.
Table 3,
Dimensions and Weights of Welded Wrought Iron Pipe, was deleted in its entirety,
since
wrought iron pipe is no longer produced. These changes in the standard were
approved
and it was designated an American National Standard on June 5 , 1975.
The standard was revised in 1978 to include SI metric dimensions. The outside
diameter
and wall thicknesses were converted to millimeters by multiplying the inch
dimensions by
25.4. Outside diameters larger than 16 in. were rounded to the nearest millimeter,
and
outside diameters 16 in. and smaller were rounded to the nearest 0.1 mm. Wall
thicknesses
were rounded to the nearest 0.01 mm. These converted and rounded SI metric
dimensions
were added to Table 2. A formula to calculate the SI metric plain end mass, in
kilograms
per meter, using SI metric diameters and thicknesses was added to section 5. The SI
metric
plain end mass was calculated and was added to Table 2. These changes in the
standard
were approved and it was designated an American National Standard on July 18, 1979.
Further revisions were made in 1984. The ANSI designations, which are no longer in
use, were deleted from Table 1, and the list of specifications was revised to agree
with
current ASTM and API specifications. Additional sizes and thicknesses which had
been
added to API specifications were added to Table 2. That edition was approved as an
American National Standard on August 19, 1985.
The next edition included additional wall thicknesses and was approved by the
American
National Standards Institute on August 24, 1995.
The 1996 edition contained revisions to Table 2, adding pipe sizes, changing some
plain
end weights and masses, identifying metric pipe by the dimensionless designator DN,
and
eliminating the API Specification column. The 1996 edition was approved as an
American
National Standard on September 23, 1996.
The current edition contains revisions to Table 2 to include the revised density
for steel
incorporated into Section 5 previously. Table 1 was deleted and other editorial
changes to
Sections 1, 2, 3, 5, 8, and 9 were made. This edition was approved as an American
National
Standard on December I , 2000.

7. MANUFACTURING
7.1. Mother Pipe
Mother pipe shall be manufactured as within the requirements as stated in the DEP
31.40.20.37 Ref. [8] and line pipe specifications report. The carbon steel shall be
ISO 3183 Ref [22] PSL 2.
Company shall be notified if there is intent to upgrade or modify the strength of
either the mother pipe or induction bend after the bending process.
7.2. Qualification Test Bend
The test bends shall be manufactured with approved MPS as stated in the DEP
31.40.20.33 Gen. Ref. [6]
7.3. Production Bending
Induction bending shall be carried out in accordance with the qualified MPS.
Interruption of the induction bending operation shall result in rejection of the
bend.
7.4. Post-Bending Heat Treatment
Except acceptable properties can be demonstrated after bending for any L450 X65
line, the
Contractor shall provide a quench and temper heat treatment of the entire joint.
The temperature of each furnace-load of bends shall be monitored by thermocouples
connected directly to selected bends and shall be recorded. The type and location
of the thermocouples shall be as specified in the MPS.
7.5. Strip/Plate End Welds
Induction bends shall not contain coil-strip end welds or plate end welds.
7.6. Forming and Sizing after Bending
This shall be done according to ISO 15590-1 Ref [20] as amended by DEP 31.40.20.33-
Gen. Ref. [6]
7.7. Jointers and Girth Welds
Induction bends ordinarily should not contain girth welds. The DEP 31.40.20.33-Gen
Ref. [6] permits jointers during manufacture of bends on the condition that on
completion of the bend, the joiner shall be removed such that no effect from the
joiner shall remain including the heat affected zone.
7.8. End Preparation
Bends shall be square except otherwise specified by company. The cutting method
shall not affect the properties of the bend when compared to the mother pipe.

Tension
Tension on the pull section results from three primary sources: (1) frictional
drag between the pipe and the wall of the hole, (2) fl uidic drag from
viscous drilling fl uid surrounding the pipe, and (3) the effective (submerged)
weight of the pipe as it is pulled through the hole. In addition
to these forces that act within the drilled hole, frictional drag from the
portion of the pull section remaining on the surface (typically supported
on rollers) also contributes to the tensile load on the pipe.
Additional loads that the horizontal drilling rig must overcome during
pull back result from the length of the drill string in the hole and the
reaming assembly that precedes the pull section. These loads don ’ t act on
the pull section and therefore have no effect on pipe stresses. Nonetheless,
if a direct correlation with the overall rig force is desired, loads resulting
from the reaming assembly and drill string must be estimated and added
to the tensile force acting on the pull section.
Calculation of the tensile load required to install a pipeline by HDD
is complicated due to the fact that the geometry of the drilled path must
be considered along with properties of the pipe being installed, subsurface
materials, and drilling fl uid. Assumptions and simplifi cations
are typically required. A theoretical pulling load may be calculated by
hand or with the aid of one of several commercially available software
packages.
Regardless of the method used to calculate an HDD pulling load, the
design engineer should be aware that numerous variables affect pulling
loads, many of which depend upon site-specifi c conditions and individual
contractor practices. These include prereaming diameter, hole stability,
removal of cuttings, soil and rock properties, drilling fl uid properties,
drilled path geometry, and the effectiveness of buoyancy control measures.
Such variables cannot easily be accounted for in a theoretical
calculation method designed for use over a broad range of applications.
For this reason, theoretical calculations are of limited benefi t unless
combined with engineering judgment derived from experience in HDD
construction.
The fi rst step in calculating a pulling load is to analyze the drilled path.
This analysis can be based on the designed drilled path, a “worst-case”
drilled path, or “as-built” pilot-hole data, if available. Bearing in mind
that most pilot holes are drilled longer, deeper, and to tighter radii than
designed, a conservative approach in the absence of as-built pilot-hole
data is to evaluate a worst-case drilled path that accounts for potential
deviations from the design. This worst-case path should be determined
based on allowable tolerances for pilot-hole length, elevation, and curve
radius as defi ned in the contract documents. The design engineer should
be aware that deviations in these parameters are typical and are often due

At least one (1) reading per drill rod is required during the drilling of the pilot
hole, registering inclination, heading, length, depth and the orientation of the
bent sub. This information shall be recorded on the steering log and be available
for inspection of the superintendent as and when required.
7.7.2.3 The Contractor shall ensure proper calibration of all equipment before
commencing directional drilling operation and provide proof of calibration
documentation to the Superintendent’s Representative
For steel piping operating above –20F, alloy steel studs ASTM
A193 Grade B7, with ASTM A194 Class 2H semi-finished heavy
hex nuts shall be used except for sulphide stress cracking service
where stud bolts shall be ASTM A193 Grade B7M. For steel piping
operating below –20F, ie: blowdown service, ASTM A320, Gr L7
studs, with ASTM A194, Gr 7 semi-finished hex nuts shall be used,
except for sulfide stress cracking services where stud bolts shall be
ASTM A320, Gr L7M.
(2) Bolting threads and lengths shall conform to the dimensions listed
in the appropriate national or industry flange standard. Headed
bolts (rather than stud bolts) shall not be used without prior PTT
approval.
For steel piping operating above –20F, alloy steel studs ASTM
A193 Grade B7, with ASTM A194 Class 2H semi-finished heavy
hex nuts shall be used except for sulphide stress cracking service
where stud bolts shall be ASTM A193 Grade B7M. For steel piping
operating below –20F, ie: blowdown service, ASTM A320, Gr L7
studs, with ASTM A194, Gr 7 semi-finished hex nuts shall be used,
except for sulfide stress cracking services where stud bolts shall be
ASTM A320, Gr L7M.
(2) Bolting threads and lengths shall conform to the dimensions listed
in the appropriate national or industry flange standard. Headed
bolts (rather than stud bolts) shall not be used without prior PTT
approval.
(3) All bolts and nuts shall be coated with PTFE, or equivalent
material.
(4) For Austenitic bolting materials shall be in accordance with piping
material classification data sheets.
1.4.6 Proprietary Connectors
Proprietary connectors shall be used as required by project Specifications.
1.5 Design Considerations for Particular Piping Systems
1.5.1 General
This
(3) All bolts and nuts shall be coated with PTFE, or equivalent
material.
(4) For Austenitic bolting materials shall be in accordance with piping
material classification data sheets.
1.4.6 Proprietary Connectors
Proprietary connectors shall be used as required by project Specifications.
1.5 Design Considerations for Particular Piping Systems
1.5.1 General
This

Hole Conditioning
7.6.11.1 Conditioning of the borehole will be conducted when the reaming has been
completed. This operation is to remove any excess cuttings still left within the
hole and to improve the condition and stability of the borehole and the borehole
walls.
7.6.11.2 Conditioning reaming tools are to be in good working order and appropriate
to the ground conditions indicated.
7.6.12 Pipe Pullback

The finish required by B16.5 for steel raised-face flanges is also to


be used for non-steel metallic flanges, for steel male and female
flanges, that is 125 to 250 micro inches. For steel tongue and
grove flanges gasket face finish shall be 32-63 micro inches.
(5) For NPS 26” and larger, ASME B16.47 SERIES A flanges shall be
used. Use SERIES B flanges only when needed to mate with
equipment flanges. When attached to pipe with a yield strength
greater than 248.4 MPa (36000 psi), the hub thickness requires
prior PTT approval.
(6) Except for galvanized piping threaded flanges shall not be used
without prior PTT approval and then only in steel NPS 2 and
smaller.
(7) The bore of weld neck flanges to be used in severe cyclic
conditions, ie: reciprocating pumps and compressors, or in services
with high corrosion rates shall have the same ID as the attached
piping. If the ID is not the same, the flange shall be taper bored
conditions may bear on the abandonment decision-making process.
The development and implementation of an abandonment plan consists of at least the
following seven steps:
(1) review prevailing regulatory requirements applicable to the abandonment
project; (2) compile all relevant information on the pipeline system, including
easement agreements; (3) analyze by segment taking into account the factors
addressed in Section 3 of this paper, including present and future land use; (4)
develop the abandonment plan in consultation with stakeholders (such as landowners,
government authorities, and other directly affected parties), incorporating the
information compiled in the above steps; (5) secure regulatory and landowner
approvals as required for the pipeline abandonment and site reclamation; (6)
implement the abandonment plan, the scope of which should include post-abandonment
responsibilities (addressed in Section 4); and (7) secure final regulatory release.

A proponent undertaking an abandonment plan should follow these six steps,


recognizing that site-specific conditions may require additional steps in the
development of the plan.
Please refer to the next page for a flowchart of the abandonment planning process
and to Appendix B for a detailed abandonment checklist.
Page
the removal of equipment or buildings or other structures or appurtenances; # the
conducting of investigations to determine the presence of substances; # the
decontamination of buildings or other structures or other appurtenances, or land or
water; # the stabilization, contouring, maintenance conditioning, or
reconstruction of the land surface; or # any other procedure, operation, or
requirement specified in the regulations
(as defined in the Alberta Environmental Protection and Enhancement Act)
Removal The pipeline is completely removed from the rightof-way.
Roach Excess soil placed over the ditch line to compensate for soil settlement.
Road or Railway Crossing
The crossing by a pipeline of a highway, road, street, or railway.
Sight Block
A mechanism to restrict the visual impact of a pipeline right-of-way.
Soil The naturally occurring, unconsolidated mineral or organic material at least
10 centimetres thick that occurs at the earth's surface and is capable of
supporting plants. It includes disturbance of the surface by human activities such
as cultivation and logging but not displaced materials such as mine spoils.
Spoil Soil materials other than topsoil excavated from the trench. In most cases,
the excavated soil is suitable for return to the pipeline trench, and allows for
recontouring of the right-of-way.
Subsoil Although a common term it cannot be defined accurately. It may be the B
horizon of a soil with a distinct profile. It can also be defined as the zone below
the plowed soil in which roots normally grow.
Surface Water
Water in a watercourse and water at a depth of not more than 15 metres beneath the
surface of the ground.
Suspension The cessation of normal operation of a pipeline pursuant to its licensed
use. The pipeline need not be rendered permanently incapable of its licensed use,
but must be left in a safe and stable state during this period of suspension, as
prescribed by the applicable regulations and guidelines. See also "deactivation".

The SDV valve will be provided at the station inlet and outlet. In case of an
emergency event the SDV valves will cut off the gas supply from the suppliers and
to the pipelines.
The compressor station will be designed for locally manned, fully automatic,
permanent operation from Station Control Room with remote monitoring of the station
from the Central Control Room.
9.2 Pig Receiver
Pig Receivers will be provided at all pipelines entering the compressor station.
The pig receiver is described in section 10.8.
9.3 Filter Separator Skid
The filter separators, as described in section 10.1, shall be provided at Obigbo
Compressor Station at each gas supply source.
The filter separator design and operating conditions are: Parameter Value QIT
Source Obigbo Node Source Cawthorne and Alakiri Source Okono/Okpoho
Design Pressure
98.0 barg
98.0 barg
98.0 barg
Abrasive Blast Cleaning shall be in accordance with DEP 31.40.30.37-Gen, Section
9.2.1 through 9.2.6.
4.3. Blast Profile
The blast cleaned profile shall be sharp and angular. Angular profile value shall
be determined by heat
shrink sleeve manufacturer in accordance with ISO 8503-5 requirements and
acceptance criteria.
4.4. Surface Cleaning
After blast cleaning to the specified quality, surfaces shall be brushed, vacuumed
or blown clean with
dry, oil-free compressed air to remove all dust and blast cleaning abrasive from
the surface and in
particular from pockets and corners. The pipe surface shall be cleaned of mill
scale, rust and other
foreign matter to achieve a minimum surface cleanliness of Sa 2½ in accordance with
the DEP
31.40.30.37-Gen, Section 9.2.6.
4.5. Mechanical Cleaning
Where, with the agreement of COMPANY, it is recognized that abrasive blast cleaning
cannot be
carried out; the area to be coated shall be cleaned by power wire brushing in
accordance Swedish
Standard SIS 055900 Standard ST3.
The prepared joint area shall be freed of all slag, weld spatter, mill scale, dirt
or other foreign matter, as
in abrasive blast cleaning.

Coating system identification


 system designation or trade name;
 name of coating Manufacturer/Supplier (s);
 generic type of system;
 coating application process;

Abrasive Blast Cleaning shall be in accordance with DEP 31.40.30.37-Gen, Section


9.2.1 through 9.2.6.
4.3. Blast Profile
The blast cleaned profile shall be sharp and angular. Angular profile value shall
be determined by heat
shrink sleeve manufacturer in accordance with ISO 8503-5 requirements and
acceptance criteria.
4.4. Surface Cleaning
After blast cleaning to the specified quality, surfaces shall be brushed, vacuumed
or blown clean with
dry, oil-free compressed air to remove all dust and blast cleaning abrasive from
the surface and in
particular from pockets and corners. The pipe surface shall be cleaned of mill
scale, rust and other
foreign matter to achieve a minimum surface cleanliness of Sa 2½ in accordance with
the DEP
31.40.30.37-Gen, Section 9.2.6.
4.5. Mechanical Cleaning
Where, with the agreement of COMPANY, it is recognized that abrasive blast cleaning
cannot be
carried out; the area to be coated shall be cleaned by power wire brushing in
accordance Swedish
Standard SIS 055900 Standard ST3.
The prepared joint area shall be freed of all slag, weld spatter, mill scale, dirt
or other foreign matter, as
in abrasive blast cleaning.
 system structure (e.g., 2-layer or 3-layer);
 structure components (primer, adhesive, outer layer) ;
 service temperature range;
 total nominal coating thickness;
 compatibility to line pipe coating system;
 suitability for immersed services;
 relevant international/national coating standard approvals
All bolts and nuts shall be coated with PTFE, or equivalent
material.
(4) For Austenitic bolting materials shall be in accordance with piping
material classification data sheets.
1.4.6 Proprietary Connectors
Proprietary connectors shall be used as required by project Specifications.
1.5 Design Considerations for Particular Piping Systems
1.5.1 General
This
Hole Conditioning
7.6.11.1 Conditioning of the borehole will be conducted when the reaming has been
completed. This operation is to remove any excess cuttings still left within the
hole and to improve the condition and stability of the borehole and the borehole
walls.
7.6.11.2 Conditioning reaming tools are to be in good working order and appropriate
to the ground conditions indicated.
7.6.12 Pipe Pullback

The finish required by B16.5 for steel raised-face flanges is also to


be used for non-steel metallic flanges, for steel male and female
flanges, that is 125 to 250 micro inches. For steel tongue and
grove flanges gasket face finish shall be 32-63 micro inches.
(5) For NPS 26” and larger, ASME B16.47 SERIES A flanges shall be
used. Use SERIES B flanges only when needed to mate with
equipment flanges. When attached to pipe with a yield strength
greater than 248.4 MPa (36000 psi), the hub thickness requires
prior PTT approval.
(6) Except for galvanized piping threaded flanges shall not be used
without prior PTT approval and then only in steel NPS 2 and
smaller.
(7) The bore of weld neck flanges to be used in severe cyclic
conditions, ie: reciprocating pumps and compressors, or in services
with high corrosion rates shall have the same ID as the attached
piping. If the ID is not the same, the flange shall be taper bored
conditions may bear on the abandonment decision-making process.
The development and implementation of an abandonment plan consists of at least the
following seven steps:
(1) review prevailing regulatory requirements applicable to the abandonment
project; (2) compile all relevant information on the pipeline system, including
easement agreements; (3) analyze by segment taking into account the factors
addressed in Section 3 of this paper, including present and future land use; (4)
develop the abandonment plan in consultation with stakeholders (such as landowners,
government authorities, and other directly affected parties), incorporating the
information compiled in the above steps; (5) secure regulatory and landowner
approvals as required for the pipeline abandonment and site reclamation; (6)
implement the abandonment plan, the scope of which should include post-abandonment
responsibilities (addressed in Section 4); and (7) secure final regulatory release.

A proponent undertaking an abandonment plan should follow these six steps,


recognizing that site-specific conditions may require additional steps in the
development of the plan.
Please refer to the next page for a flowchart of the abandonment planning process
and to Appendix B for a detailed abandonment checklist.
Page
the removal of equipment or buildings or other structures or appurtenances; # the
conducting of investigations to determine the presence of substances; # the
decontamination of buildings or other structures or other appurtenances, or land or
water; # the stabilization, contouring, maintenance conditioning, or
reconstruction of the land surface; or # any other procedure, operation, or
requirement specified in the regulations
(as defined in the Alberta Environmental Protection and Enhancement Act)
Removal The pipeline is completely removed from the rightof-way.
Roach Excess soil placed over the ditch line to compensate for soil settlement.
Road or Railway Crossing
The crossing by a pipeline of a highway, road, street, or railway.
Sight Block
A mechanism to restrict the visual impact of a pipeline right-of-way.
Soil The naturally occurring, unconsolidated mineral or organic material at least
10 centimetres thick that occurs at the earth's surface and is capable of
supporting plants. It includes disturbance of the surface by human activities such
as cultivation and logging but not displaced materials such as mine spoils.
Spoil Soil materials other than topsoil excavated from the trench. In most cases,
the excavated soil is suitable for return to the pipeline trench, and allows for
recontouring of the right-of-way.
Subsoil Although a common term it cannot be defined accurately. It may be the B
horizon of a soil with a distinct profile. It can also be defined as the zone below
the plowed soil in which roots normally grow.
Surface Water
Water in a watercourse and water at a depth of not more than 15 metres beneath the
surface of the ground.
Suspension The cessation of normal operation of a pipeline pursuant to its licensed
use. The pipeline need not be rendered permanently incapable of its licensed use,
but must be left in a safe and stable state during this period of suspension, as
prescribed by the applicable regulations and guidelines. See also "deactivation".

The SDV valve will be provided at the station inlet and outlet. In case of an
emergency event the SDV valves will cut off the gas supply from the suppliers and
to the pipelines.
The compressor station will be designed for locally manned, fully automatic,
permanent operation from Station Control Room with remote monitoring of the station
from the Central Control Room.
9.2 Pig Receiver
Pig Receivers will be provided at all pipelines entering the compressor station.
The pig receiver is described in section 10.8.
9.3 Filter Separator Skid
The filter separators, as described in section 10.1, shall be provided at Obigbo
Compressor Station at each gas supply source.
The filter separator design and operating conditions are: Parameter Value QIT
Source Obigbo Node Source Cawthorne and Alakiri Source Okono/Okpoho
Design Pressure
98.0 barg
98.0 barg
98.0 barg
98.0 barg
Design Temperature
7.6.12.1 At the completion of the hole opening and the hole conditioning, the
Contractor will commence the casing/carrier pipe pullback. The pipe pullback is a
critical operation and the following must be controlled by the Contractor:
involve a combination of pipe removal and abandonment-in-place along the length of
the pipeline. A key factor influencing the choice between the two options is
present and future land use.
It is further noted that the abandonment techniques presented are confined to those
possible using currently available technology. While developments in pipeline
removal and abandonment technologies were evaluated, no major improvements to the
methods currently in use were discovered. However, as pipeline abandonments become
more prevalent, improved abandonment methods will likely be developed.
1.5 Objective
The objective of this discussion paper is to assist the user in the development of
a pipeline abandonment plan, a framework for which is provided in Section 2 of this
paper. More particularly, the paper is meant to assist parties in making an
informed decision between abandoning in place or through removal. Section 3
outlines the general technical and environmental issues that should be considered
when abandoning a pipeline, while Section 4 elaborates on post-abandonment
responsibilities. Site-specific issues should be addressed on a case-by-case basis.

The objective of creating an abandonment plan is to ensure that identified issues


have been addressed and that the pipeline is abandoned in a way that provides a
forum for meaningful stakeholder input and ensures that public safety and
environmental stability are maintained.
1.6 Regulatory Requirements
The NEB is responsible for regulating interprovincial and international pipeline
systems in Canada, while the individual provinces are responsible for regulating
intraprovincial pipeline systems. Within each province, gathering, transmission,
and distribution pipelines may be regulated by different agencies. For example, in
Alberta the EUB regulates gathering and transmission lines as well as higher-
pressure distribution lines (greater than 700 kPa), while lower-pressure
distribution lines are regulated by Alberta Transportation and Utilities. AEP,
through the Environmental Protection and Enhancement Act (EPEA), regulates
conservation and reclamation activities for all three categories of pipelines.
In addition to the primary regulators, there may be other governmental agencies
within each of the respective jurisdictions that may have an interest in the
abandonment and reclamation of a pipeline. These other agencies may include local
governments, especially in populated areas where pipeline abandonment may impact
upon land uses.
In Alberta, the EUB sets the requirements for the abandonment of gathering and
transmission lines. In addition to meeting the EUB's abandonment requirements, the
pipeline right-of-way must be reclaimed to AEP standards. Reclamation certificates
are issued by inspectors designated under EPEA. For removal projects that are
classified as Class I projects,1 the operator is required to obtain an approval
under EPEA from AEP to ensure that proper conservation and reclamation occurs. For
smaller projects, AEP's Environmental Protection Guidelines for Pipelines are to be
followed during construction.
____________________ 1 A Class I pipeline is defined by the Activities Designation
Regulation (AR 110/93)

Dennis Bratton Adolf Bruneski Paul Vasseur Jim Anderson Fred Kuipers

Potrebbero piacerti anche