Sei sulla pagina 1di 1

SRR Projects Pvt Limited

HYDERABAD

JOB SAFETY ANALYSIS


DUCTING
Project Name: Date :
Location: Revision No:
Work area:
Job Description:
Personal Protective Equipments (PPE) : Hard Hat, Safety Shoes, Safety Goggles, Hand Gloves

SEQUENCE OF Yes
POTENTIAL HAZARDS PRECAUTION
BASIC JOB STEPS / NA
S
× Non-compliance of PTW  Get the appropriate permits
Pre - work Procedures  Disseminate Tool box Talks to the crew

× Fall of material  Proper material handling techniques to be followed while handling


Shifting of material
× Sharp Edges  Use of leather hand gloves

× Fall of material  Material must not be stacked more than 1.5mtr height

 Use wooden hammer to fabricate the duct


× Noise
 Use ear plugs / ear muffs

× Trip  Proper housekeeping to be done regularly

Fabrication × Entanglement & Crushing  Avoid loose clothing & make sure body is away from the nip points

 Ensure scissors with long and proper grip are being used
× Mishandling of tools
 Riveting ply must be handled firmly while using
 Tools used must be inspected regularly & ensure Inspected
× Improper tools tools are being used
× Improper handling of portable  Standard drilling bits to be used and drilling shall be carried
tools out tangentially to the surface
 Work piece must be secured in vice while drilling

× Pinch point  Use hand leather gloves while fitting screws


Duct joining × Silicon  Use nose mask and PVC gloves while applying silicon gel
× Sharp edges  Packing required for sharp edges

× Fall of fabricated duct  Proper material handling techniques to be followed and


Erecting Duct × Failure of tackles heavier ducts shall be lifted with team of crew members as
required
 Duct must be secured to anchored to tie rods
Job Specific Hazards
& Precaution’s (Other
than indicated above)

Date Revision Prepared by Checked By Reviewed By Approved by


00

Job Safety Analysis For DUCTING Page 1

Potrebbero piacerti anche