Sei sulla pagina 1di 14

1

Bogibeel Rail-cum-Road Bridge

With a width ranging from 1.2 km to 18 km, the Brahmaputra river has been
bridged four times in the past. HCC holds a distinction of building two of
these bridges and has recently completed construction of the 5th bridge at
Bogibeel, near Dibrugarh in Assam.

The Mighty Brahmaputra

There are a lot of legends and prophesies floating with the current of the mighty
Brahmaputra River as it tracks its course from Tibet to Bangladesh, roaring down
through narrow chasms and gobbling up land in its pursuit to reach the sea. A
river as wide as an ocean, blood red with stories of sacrifice and patricide,
unusually for a river it is male in its aspect, and unusually for India, it is not a holy
river but often referred to as the Old Man River.
2

The Brahmaputra is not a river that can be tamed easily; it is a river that
demands respect and submission. Indeed, rare to find a reference to this river
without the adjective "mighty' attached to it. In Tibet, where the river leaps to
freedom from the great glacier mass of the northern-most chain of the
Himalayas, it is known as Tsangpo, meaning 'purifier'. Sweeping and leaping
through chasms, plunging through narrow valleys and collecting various
tributaries along the way, the river twists and turns and executes hairpin bends
before it spills into the North Eastern states of India. Here, the river collects the
Dhanasri River and becomes the Brahmaputra, son of Brahma. Rolling into the
alluvial plains of Bengal, the Brahmaputra rushes to meet the River Goddess
Ganga. United, they dissolve into each other and spread fingers into the Bay of
Bengal, feeding and destroying the fragile river islands that exist in the area
known as the Sunderbans.

Bridging History

Bridging the Brahmaputra has always been a daunting task. The river has been
traditionally considered extremely difficult for bridging due to various reasons
including its ferocious and unpredictable behaviour, high currents and turbulent
waters, widespread erosion of the banks, very short working period, and high
seismicity and remoteness of the area.

With a width ranging from 1.2 km to 18 km, the Brahmaputra river has been
bridged four times in the past. HCC holds a distinction of building two of these
bridges and has recently completed construction of the 5th bridge at Bogibeel,
near Dibrugarh.
3

Saraighat Bridge in Guwahati was the first rail-cum-road bridge over the mighty
Brahmaputra river in Assam. Although the first railway line in Assam came up in
1881, yet Brahmaputra was not bridged by the British. It was bridged by HCC by
building the 1.3 km long bridge at Saraighat near Guwahati. This bridge was
opened to traffic in April 1962 by Prime Minister Jawaharlal Nehru. In 2017, a
new 1.49 km long road bridge was constructed at Saraighat.

Kolia Bhomora Setu at Tezpur was the second bridge constructed by HCC. This
pre-stressed concrete road bridge connects Sonitpuron in the north bank, with
Nagaon district in the south bank. The length of this bridge is 3015 m, and its
construction went on from 1981 to 1987.

Naranarayan Setu is the third bridge constructed over the Brahmaputra river.
This double-deck bridge has a railway track on the lower deck and a road on the
upper deck. It has a length of 2.284 km and connects Jogighopa, a town in
Bongaigaon District in the north with Pancharatna, a town of Goalpara District in
the south. This bridge was inaugurated on April 15, 1998, by Prime Minister Atal
Bihari Vajpayee.

Built in 2017, Dhola–Sadiya Bridge, also referred to as the Bhupen Hazarika


Setu, is the fourth bridge built over the Brahmaputra river, connecting the north-
east states of Assam and Arunachal Pradesh. The bridge spans the Lohit River,
a major tributary of the Brahmaputra River, from the village of Dhola in the south
to Sadiya to the north. At 9.15 kms, it has the honour of being the longest bridge
in India.

Bogibeel Bridge

Bogibeel Bridge is a combined road and rail bridge in the Dibrugarh district of the
north eastern state of Assam. The 4940.5 m long bridge is the longest bridge of
its kind in India. The bridge provides connectivity to nearly five million people
residing in Upper Assam and Arunachal Pradesh. It also gives easy and direct
access to the upper Assam from the rest of the country through the North bank,
in contrast to the current route through Guwahati in the South bank, which is long
and tortuous.

HCC in a joint venture with DSD Brouckenbau GmbH, Germany, and VNR
Infrastructures Ltd, received a ₹987 crore order from the Northeast Frontier
Railway to construct the superstructure of Bogibeel Rail-cum-road Bridge in
November 2011. HCC's share in this order is 51%, DSD Brouckenbau GmbH is
20%, and VNR Infrastructures' is 29%. Bogibeel Rail-cum-road Bridge is a
double decked bridge with two railway tracks on the lower deck and a 3-lane
road on the upper deck, flanked by footpaths on each side. Highway alignment
4

will meet the top level of road deck of the bridge suitably beyond the abutments
while the rail alignment will continue in the same line and level.

Location

The Bogibeel Bridge, situated 17 km downstream of Dibrugarh and Dhemaji,


spans the Brahmaputra river and connects the town of Dibrugarh in the south to
Dhemaji to the river's north. The bridge is located just over 20 km away from the
Assam-Arunachal Pradesh border and is thus expected to act as an alternative to
the Kolia Bhomora Setu, Tezpur, in providing connectivity to nearly five million
people residing in Upper Assam and Arunachal Pradesh

Bogibeel is the fifth rail-road bridge on the Brahmaputra river in Assam. Due to its
location, the bridge is of strategic importance to India as it significantly enhances
India's ability to transport troops and supplies to its borders in Tibet Arunachal
Pradesh. Being in an area of intense rainfall, construction has been significantly
challenging.

Rail Connectivity

Bogibeel bridge provides a connection between the Rangia-Murkongselek


section of the North East Frontier Railway on the north bank of Brahmaputra and
5

Lumding–Dibrugarh section that lies to the south of the Brahmaputra. A new


Dibrugarh Railway Station, expected to be the largest in the region, has been
proposed and is to be linked to the Rangia-Murkongselek line via Chaulkhowa
and Moranhat. The Railways have initiated the gauge conversion of the
Dhamalgaon to Sisiborgaon rail line to the north of the bridge and commissioned
the 44 km Chalkhowa-Moranhat line to the south.

Project History

The project obtained approval of the federal Cabinet Committee on Economic


Affairs (CCEA) in September 1997 and construction began in April 2002. For
building the bridge, the Indian Railways had to construct the expanse of the
Brahmaputra river from 10 km to 5 km; this involved construction of 'guide
bunds'. The project required about 505 hectares of land, which was acquired
across 19 villages. Major earthworks and strengthening of the north and south
dykes were completed by June 2011.

Contractors involved in the Bogibeel rail-road bridge:

 The state-owned consultancy and project management enterprise Rites


(Rail India Technical and Engineering Services) undertook the pre-
construction studies, geo-technical investigations and detailed design of
the rail-road bridge.
 Bhartia Infra constructed the guide bunds and approach embankments on
the south bank of the bridge.
 Contract for construction of foundations and substructure of the bridge was
awarded to Gammon India in April 2008.
6

 A joint venture of Hindustan Construction Company (HCC), Germany-


based DSD Brouckenbau and VNR Infrastructures was awarded the
contract to construct superstructure of the bridge in November 2011.

Advantages of Welded Bridge

Bogibeel is India's first and only fully welded bridge construction. It is also for the
first time that European codes and welding standards were adhered to in the
construction of a bridge in India.

Normally, in a steel bridge construction, bolts and rivets are used, which need
periodic replacement due to shear failure over traffic loads. Construction of
trusses using welding makes the connection between the components a
permanent one, thereby eliminating the above failures. A welded bridge not only
reduces maintenance cost but also adds to the longevity of the superstructure. It
is estimated that Bogibeel Bridge is durable and serviceable for 120 years.

Construction Methodology

For the construction of this mammoth bridge, HCC has set-up huge facilities on
the left bank of the river, and had three sequences of Fabrication, Assembly and
Launching.

Fabrication: The Fabrication Shops of 2000 MT per month capacity were set-up
with two parallel Bays. The team had assembled customized platforms in-house
to fabricate and fit various joints employing Gas Metal Arc Welding (GMAW). To
ensure an error-free welding - Magnetic Particle Testing, Dry Penetration Testing
and Ultra Sonic Testing were deployed. A specialized Beam making CMM
Machine from Italy was used for the first time in India for fabrication of Box and I-
7

Sections using Submerged Arc Welding (SAW) procedure. A blasting gun was
used to achieve the surface roughness of SA 2½ before applying paint. The
intermediate and final spray coatings are performed in a highly controlled climatic
chamber with spray guns.

Assembly: Thereafter, these fabricated sections are moved to the assembly


shop where they are installed on their designated beds. They are guided to their
correct positions through jacking and welded by GMAW process. These
segments are arranged in a sequence and sent for the vertical assembly using
horizontal lifters. After installation of the top and bottom girders, the final Truss
Bridge Dimension Design Chambers are examined thoroughly and approved to
complete the fit-out. A Nose is fabricated and fitted on the first truss before
launching it on the piers.

Launch: While determining the methodology of erecting the steel trusses on


pillars, engineers had two choices — lift the spans with floating cranes or erect
them with a launching truss. And they have to decide based on which option
would be more practical and economical. After weighing the pros and cons, the
HCC team came-up with a solution of pulling the steel trusses with a set of jacks
and winches on the pillars. This eliminated the need to enter the river, which was
often turbulent during monsoons. Besides, it also ensured safer working
conditions, precluded the mobilisation of giant set-ups on either side of the 4.8
km wide river, and accelerated the pace of the project.

The strategy is a testimony of the company's value engineering, an important


feature of the globally-practiced 'Lean Construction' that is changing the way
projects are executed from design to construction.

1000-ton hydraulic jacks and strand jacks linked with the substructures were
8

used for moving the steel truss over the pillars. Two sets of steel cable strands
were anchored to the end cross beams of the Truss and hauled by hydraulic
jacks. The Truss slides over the Launching Bearing with the help of Sliding
Plates, which were inserted at one end and taken out at the other, thereby
moving the Truss towards its desired position. In order to limit the required
launching forces, the superstructure was pulled in 4 launching segments of 10
spans each. Thus, the superstructure was pulled over the pillars just like a train
of ten spans. With each span weighing 1700 MT, the pulling force required was
equivalent to pulling 26 Airbus A380 with maximum take-off weight over 650
tons, put together without any wheels.

Finally, the launching bearings were replaced by final bearings. The tracks were
laid, and the road was constructed adapting RCC construction. After fulfilling the
electrical and other ancillary requirements, the assignment was completed.

Supply-Chain Management

Construction supply chain is a network of suppliers, manufacturers, assemblers,


sub-contractors, retailers, customers and other stakeholders. The main objective
of effective supply chain management is to reduce the handling costs and on-site
storage. Enterprise Resource Planning (ERP) solutions such as System
Applications & Products (SAP), implemented at all HCC project sites offer
flexibility in material planning as per the construction sequence and help
overcome challenges during execution. This, in turn, minimises the idling time of
equipment and material inventories and enhances the efficiency of operations.

HCC follows the Just-In-Time (JIT) inventory system, where it produces or


9

acquires materials and products as per demand. This is a key component of its
supply chain.

One of the major challenges at most construction sites is logistics management,


which depends on the availability of various transporters and modern tracking
systems. It allows a project manager to select the right transport mix to bring
heavy equipment or material to the project site and improve delivery time. At the
Bogibeel Bridge project, the team used a combination of rail and road transport
to deliver 80,000 tons of steel plates from various parts of the country to the
remote project site in Assam. The orders for extra wide plates were placed in
advance as per the design of the superstructure. In this way, the team avoided
any possible mismatch of material and ensured qualitative and timely execution
of the job.

Steel plates and sections were procured mainly from three sources i.e. JSPL,
Essar and SAIL. Of these 80,000 MT, approximately 20,000 MT (25% scope)
was categorized as ODC (Over Dimension Cargo) and attracted special
measures for transport to the project site from the sources in Hazira and Angul,
which were more than 3200 km and 1800 km away, respectively. The average
lead time of procuring these materials is 4 months. Procurement plan was made
according to minimum order quantity required thickness-wise, also estimating
future market price trends as the order lot sizes ranges from 3500 MT to 10000
MT.

Spherical bearings were inspected at Germany, shipped to China for load testing,
and then shipped to Bhopal for the refitting of tested bearings, and then finally
shipped to project site. The lead time of such consignments is 6 months. Average
daily consumption of welding wire was 2000 kg per day; grinding wheels around
5000 per day; Argon + Co2 shielding gas more than 200 cylinders per day; O2
10

cylinders around 500 per day; and around 50 BMCG cylinders per day. Besides
4,50,000 Shear studs were imported from Nelson, USA, (lead time of 3 months),
High Strength Friction Grip bolts of around 7,00,000 quantity were manufactured
at different sources in India, and Diamant MM1018FL gap compensation were
imported from Germany (lead time of 3 months). The team achieved perfect
synergy between each of these project elements' procurement and uninterrupted
construction flow.

Arjun Dhawan, Director & Group CEO

HCC has time and again undertaken complex infrastructure projects that are
benchmarks in India’s infrastructure journey. Bogibeel Bridge is an engineering
masterpiece which has many technical firsts to its name. It is India’s first fully
welded Warren truss girder type steel bridge. Not only has an incremental
launching technique for superstructure erection been used for the first time in
India, it is also the world’s longest incrementally launched steel bridge. HCC is
proud to create such marvels for the nation.

The HCC team through its sheer determination and grit completed this project, as
bridging the mighty Brahmaputra has always been a daunting task. The river is
extremely difficult to bridge due to various reasons including its ferocious and
unpredictable behaviour, high currents and turbulent waters, widespread erosion
of the banks, short working period, high seismicity and the sheer remoteness of
the area.

Most 2D Software

The fabrication of various components, using reinforcement bars and plates, has
become an integral part of infrastructure projects. Advanced software is used to
determine the optimum sizes of bars and plates before procurement, thereby
reducing wastage and volume.

At the Bogibeel project, the HCC team used 'Most 2D' automatic nesting software
to generate efficient two-dimensional cutting plans for fabricating the steel
superstructure for the bridge. The nesting technology was based on advanced
cutting algorithms specifically designed to optimise the cutting layouts in
shearing. The software generates high-utilisation layouts, significantly reducing
waste, and maximizes productivity.

Spherical Bearings

Railways have traditionally used steel rocker-roller bearings for bridges with
11

larger spans. For the Bogibeel Bridge, the initial plan was to use Pot-PTFE
bearing with metallic pins and guide bearings. However, it was found that the
size of bearing required for taking the anticipated load cannot be accommodated
in the pier cap, hence, Spherical Bearings were used.

Spherical Bearings are designed to carry combinations of vertical loads,


horizontal loads, longitudinal and transversal movements and rotations. They are
used in steel and concrete road and railway bridges. The bearings are made of
steel elements coupled with a PTFE surface to allow movement and rotations.
One side of the internal median plate is machined as a spherical surface to allow
tilting movement (rotation) whilst on the other side, a flat sliding surface is
obtained to allow displacements.

Spherical Bearings with 4 support system as per European bearing standard EN-
1337 have been used in the Bogibeel Bridge. A total of 164 bearings have been
used to construct the bridge. Each span is supported by 4 Spherical Bearings.
These bearings had been manufactured by Maurer AG, Germany, in accordance
with the design finalized and approved by Ramboll / RITES.

Corrosion Protection Measures

The superstructure of Bogibeel Bridge has been constructed using a special


grade copper-bearing steel plates to reduce corrosion. The average annual
12

relative humidity in Bogibeel is 90% which goes up to 96 - 97%. To further


reduce corrosion due to the excessive humidity, a complex Corrosion Protection
System specific to different components of the bridge has been implemented
during construction.

 Metal Spraying – Aluminum: Thermal Spray, basically known as


Metallizing; is a process in which metal is melted and directly sprayed onto
the surface of another metal to protect against corrosion, heat, traction,
etc. Aluminum (Al) provides excellent corrosion resistance properties. TSA
coating provides enhanced shelf life, maximum corrosion protection and
very less curing time compared to painting. This method was used for the
Gusset Plates and Brackets.
 For the exterior of Bottom Chord, Bottom Joint & Bottom Cross Girder, Hot
Zinc spray has been carried out as a primer then epoxy with MIO & TIO2
coating on it and Aliphatic Polyurethane coating has been carried out on
the top of it.
 For surfaces in contact with concrete that is the Top Chord and Top Joint,
Metal Spray Zinc Coating of 80uM has been carried out.
 For exterior of Top Chord, Top Joint, Top Cross Girders and Diagonals, a
primer of Inorganic Zinc Silicate having an intermediate coat of Epoxy with
MIO and a top coat of Aliphatic Polyurethane has been carried out.
 For interior of Bottom Chord, Bottom Joint, Top Chord, Top Joint, Top
Cross Girder and Diagonals, a primer of zinc-rich epoxy having an
intermediate coat of PVC with MIO and a top coat of water-based
Polyurethane was applied.
 And for surface with concrete that is Top Cross Girder, a final coat of Metal
Spray Aluminum Coating was done again to ensure complete corrosion
protection.
 Hot Dip Galvanizing is the process of coating iron and steel with zinc,
which alloys with the surface of the base metal. It is done by immersing the
metal in molten zinc at a temperature of around 840°F (449°C). Here, a
coating of 250 uM was applied to the Stringers & Bracings of the bridge.
 Also, all enclosed spaces were sealed by welding and were vacuum tested
so that no air can go inside and initiate corrosion.

Seismic Restrainers

Location of Bogibeel Bridge falls in Seismic Zone-V, which in Indian history, has
been most vulnerable to earthquakes with magnitudes in excess of 7.0. In order
to offer good stability to the heavy spans (1700 MT), they are provided with
seismic restrainers.

This arrangement works like male & female connection with female pockets
13

embedded onto piers and male parts arrangement on the span. For precise
lowering of the span such that male joint fits into the female connections before
the final lowering of the span on the permanent bearings, HCC team devised a
unique circular slider frame made of stainless steel with jacks arrangement.

With this, the exact movement to fit the Seismic restrainers and final lowering of
the heavy spans on permanent bearings were achieved.

Bogibeel Bridge: Asia's Longest & Most Famous

 The project boasts of benefits such as strategic and speedier access for
defence forces to the Indo-China border, which means faster movement of
troops and heavy weaponry.
 Provides better connectivity to nearly five million people inhabiting the
upper Assam region and Arunachal Pradesh. Saves travel-time between
Tinsukia in Assam to Naharlagun of Arunachal Pradesh by more than 10
hours, thereby saving fuel and travel cost. The 4.94 km bridge now
connects the south bank of Brahmaputra river in Assam's Dibrugarh district
with Silapathar in Dhemaji district close to Arunachal Pradesh, and cuts
down the distance between the two by about 400 km.
 Its biggest benefit is the travel time that it will save: as of now, a train
journey from Arunachal Pradesh to Assam's Dibrugarh requires a 500 km
detour via Guwahati. Now, the journey is reduced to less than 100 km.
Also, the train journey between Delhi and Dibrugarh has reduced by 3
hours.
 Tourist places of Arunachal Pradesh will become more accessible and give
a fillip to the tourism industry. The bridge also cuts down the distance to
the border with China by 10 hours.
 The bridge benefits the intra/inter-state transportation of medical patients
seeking treatment in Dibrugarh district, which houses the prestigious
Assam Medical College. Currently, if any emergency of super speciality
kind arises along the northern bank, patients have to rely on the
cumbersome boat ferries.
 The bridge is part of the infrastructure projects conceived by the
government of India to improve logistics along the border in Arunachal
Pradesh. By connecting two very important highways of Assam - NH37
and NH52, the bridge enhances the intra-state trade ecosystem. At
present, cargo takes 10 to 12 hours to reach its destination. The Bogibeel
Rail-Road link reduces trans-shipment time and takes maximum 2 hours,
thus saving cost of transportation, fuel, and the time taken.
 At 32 meters above water level of the mighty Brahmaputra river, it is hailed
as an engineering marvel of the country as construction of such a mega-
bridge in a seismically sensitive zone was a herculean task for the
14

engineers. About 30 lakh bags of cement, 19,250 mt reinforcement steel,


and 2,800 mt structural steel were used.
 Has earned the distinction of being Asia's second largest bridge with three-
lane roads on top and a double rail line underneath. Constructed at a cost
of ₹5,920 crores, it assures a serviceable period of around 120 years.

Potrebbero piacerti anche