Sei sulla pagina 1di 4

CALENDARIO MODIFICADO VALORIZADO DE EJECUCION DE OBRA

"RENOVACION DE ABASTECIMIENTO DE AGUA; EN EL (LA) REHABILITACION DEL SANEAMIENTO BASICO EN LA LOCALIDAD YURACCANCHA, DISTRITO DE HUAC-HUAS, PROVINCIA LUCANAS,
PROYECTO
DEPARTAMENTO AYACUCHO"
VALOR REFER. DE OBRA S/.115,283.63
UBICACION YURACCANCHA - HUAC HUAS - LUCANAS - AYACUCHO
FECHA
OCTUBRE DEL 2019
120 DIAS CALENDARIOS
TOTAL
Item Descripción Und Metrado Precio Parcial MES 01 MES 02 MES 03
Metrado Costo Metrado Costo Metrado Costo Metrado Costo
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 3.60 X 2.40 M und 1.00 S. 882.67 S. 882.67 1.00 S/ 882.67 0.00 S/ - 0.00 S/ - 1.00 S. 882.67
01.02 CASETA DE GUARDIANIA Y/O ALMACEN glb 1.00 S. 1,500.00 S. 1,500.00 1.00 S/ 1,500.00 0.00 S/ - 0.00 S/ - 1.00 S. 1,500.00
01.03 CAMPAMENTO PROVISIONAL DE OBRA m2 16.00 S. 136.35 S. 2,181.60 16.00 S/ 2,181.60 0.00 S/ - 0.00 S/ - 16.00 S. 2,181.60
02 CAPTACION TIPO C-1 S. -
02.01 OBRAS PRELIMINARES S. -
02.01.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 1.29 S. 110.93 S. 143.10 0.00 S/ - 1.29 S/ 143.10 0.00 S/ - 1.29 S. 143.10
02.01.02 LIMPIEZA DEL TERRENO MANUAL m2 8.85 S. 2.56 S. 22.66 8.85 S/ 22.66 0.00 S/ - 0.00 S/ - 8.85 S. 22.66
02.01.03 TRAZO Y REPLANTEO PRELIMINAR m2 3.90 S. 2.80 S. 10.92 3.90 S/ 10.92 0.00 S/ - 0.00 S/ - 3.90 S. 10.92
02.02 MOVIMIENTO DE TIERRAS S. -
02.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 3.57 S. 42.16 S. 150.51 3.57 S/ 150.51 0.00 S/ - 0.00 S/ - 3.57 S. 150.51
02.03 OBRAS DE CONCRETO S. -
02.03.01 SOLADO 2" MEZCLA C:H 1:12 m2 2.93 S. 36.02 S. 105.54 0.00 S/ - 2.93 S/ 105.54 0.00 S/ - 2.93 S. 105.54
02.03.02 CONCRETO f'c=140 kg/cm2 m3 1.21 S. 499.52 S. 604.42 0.00 S/ - 1.21 S/ 604.42 0.00 S/ - 1.21 S. 604.42
02.03.03 CONCRETO MUROS F'C=175KG/CM2 m3 0.71 S. 522.34 S. 370.86 0.00 S/ - 0.71 S/ 370.86 0.00 S/ - 0.71 S. 370.86
02.03.04 CONCRETO LOSA f'c= 175 kg/cm2 m3 0.13 S. 497.09 S. 64.62 0.00 S/ - 0.13 S/ 64.62 0.00 S/ - 0.13 S. 64.62
02.03.05 ENCOFRADO Y DESENCOFRADO MUROS m2 10.08 S. 73.86 S. 744.51 0.00 S/ - 10.08 S/ 744.51 0.00 S/ - 10.08 S. 744.51
02.03.06 ENCOFRADO Y DESENCOFRADO LOSA m2 2.23 S. 71.63 S. 159.73 0.00 S/ - 2.23 S/ 159.73 0.00 S/ - 2.23 S. 159.73
02.03.07 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 40.54 S. 5.33 S. 216.08 0.00 S/ - 40.54 S/ 216.08 0.00 S/ - 40.54 S. 216.08
02.04 REVOQUES Y ENLUCIDOS S. -
02.04.01 TARRAJEO EXTERIOR (MORTERO 1:5 C:A) m2 5.48 S. 26.02 S. 142.59 0.00 S/ - 5.48 S/ 142.59 0.00 S/ - 5.48 S. 142.59
02.04.02 TARRAJEO INTERIOR CON IMPERMEABILIZANTE m2 5.29 S. 39.77 S. 210.38 0.00 S/ - 5.29 S/ 210.38 0.00 S/ - 5.29 S. 210.38
02.05 VALVULAS Y ACCESORIOS S. -
02.05.01 ACCESORIOS Y VALVULAS DE CAPTACION C-1 (Ø=1") und 1.00 S. 176.27 S. 176.27 0.00 S/ - 1.00 S/ 176.27 0.00 S/ - 1.00 S. 176.27
02.06 OTROS S. -
02.06.01 PINTURA ESMALTE EN MURO EXTERIOR m2 5.48 S. 14.25 S. 78.09 0.00 S/ - 5.48 S/ 78.09 0.00 S/ - 5.48 S. 78.09
02.06.02 FILTRO DE ARENA Y GRAVA m3 1.71 S. 198.92 S. 340.15 0.00 S/ - 1.71 S/ 340.15 0.00 S/ - 1.71 S. 340.15
03 CERCO PERIMETRICO CAPTACION S. -
03.01 OBRAS PRELIMINARES S. -
03.01.01 TRAZO, NIVELACION Y REPLANTEO m2 30.25 S. 2.88 S. 87.12 0.00 S/ - 30.25 S/ 87.12 0.00 S/ - 30.25 S. 87.12
03.02 MOVIMIENTO DE TIERRAS S. -
03.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 1.44 S. 42.16 S. 60.71 0.00 S/ - 1.44 S/ 60.71 0.00 S/ - 1.44 S. 60.71
03.03 OBRAS CONCRETO SIMPLE S. -
03.03.01 CONCRETO CIMIENTO f'c=175 kg/cm2 m3 1.44 S. 484.15 S. 697.18 0.00 S/ - 1.44 S/ 697.18 0.00 S/ - 1.44 S. 697.18
03.04 CARPINTERIA METALICA S. -
03.04.01 CERCO DE PROTECCION CON TUBO F°N° DE 2" Y ALAMBRE DE PUAS N°16 m 20.00 S. 123.84 S. 2,476.80 0.00 S/ - 20.00 S/ 2,476.80 0.00 S/ - 20.00 S. 2,476.80
03.04.02 PUERTA 1.00X2.50 m und 1.00 S. 164.68 S. 164.68 0.00 S/ - 1.00 S/ 164.68 0.00 S/ - 1.00 S. 164.68
04 LINEA DE CONDUCCION S. -
04.01 OBRAS PRELIMINARES S. -
04.01.01 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS m 1,660.00 S. 1.01 S. 1,676.60 0.00 S/ - 1,660.00 S/ 1,676.60 0.00 S/ - 1,660.00 S. 1,676.60
04.02 MOVIMIENTO DE TIERRAS S. -
04.02.01 EXCAVACION EN ROCA FIJA m3 5.69 S. 65.88 S. 374.86 0.00 S/ - 5.69 S/ 374.86 0.00 S/ - 5.69 S. 374.86
04.02.02 RELLENO MANUAL CON MATERIAL DE PRESTAMO m3 11.27 S. 98.84 S. 1,113.93 0.00 S/ - 0.00 S/ - 11.27 S/ 1,113.93 11.27 S. 1,113.93
04.02.03 PROTECCION PARCIAL DE LA TUBERIA HDPE DE 1" m3 16.60 S. 189.54 S. 3,146.36 0.00 S/ - 13.28 S/ 2,517.09 3.32 S/ 629.27 16.60 S. 3,146.36
04.03 INSTALACION DE TUBERIAS
04.03.01 SUMINISTRO E INSTALACION TUBERIA FLEXIBLE HDPE EXPUESTO 1" BAR 10 m 1,660.00 S. 5.68
S. 9,428.80 1,660.00 S. 9,428.80
0.00 S/ - 1,328.00 S/ 7,543.04 332.00 S/ 1,885.76
04.03.02 SUMINISTRO E INSTALACION TUBERIA FLEXIBLE HDPE EXPUESTO EN m 16.00 S. 7.56
CRUCE AEREO 1" BAR 10 S. 120.96 16.00 S. 120.96
0.00 S/ - 16.00 S/ 120.96 0.00 S/ -
04.03.03 SUMINISTRO E INSTALACION TUBERIA FLEXIBLE HDPE EXPUESTO EN m 24.00 S. 11.16
CRUCE AEREO 1 1/2" BAR 10 S. 267.84 24.00 S. 267.84
0.00 S/ - 24.00 S/ 267.84 0.00 S/ -
04.03.04 PRUEBA HIDRAULICA EN REDES DE TUBERIA m 1,700.00 S. 1.73 S. 2,941.00 0.00 S/ - 0.00 S/ - 1,700.00 S/ 2,941.00 1,700.00 S. 2,941.00
´05 CRUCE AEREO L=16 M S. -
´05.01 OBRAS PRELIMINARES S. -
05.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 52.58 S. 2.80 S. 147.22 0.00 S/ - 52.58 S/ 147.22 0.00 S/ - 52.58 S. 147.22
05.02 MOVIMIENTO DE TIERRAS S. -
05.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 6.66 S. 42.16 S. 280.79 6.66 S/ 280.79 0.00 S/ - 0.00 S/ - 6.66 S. 280.79
05.03 OBRAS CONCRETO SIMPLE S. -
05.03.01 SOLADO E=3" MEZCLA CEMENTO-HORMIGON 1:12 m2 2.42 S. 35.38 S. 85.62 0.00 S/ - 2.42 S/ 85.62 0.00 S/ - 2.42 S. 85.62
05.03.02 CONCRETO f'c=140 kg/cm2 + 30% P.M. m3 2.99 S. 454.78 S. 1,359.79 0.00 S/ - 2.99 S/ 1,359.79 0.00 S/ - 2.99 S. 1,359.79
05.04 OBRAS CONCRETO ARMADO S. -
05.04.01 CONCRETO f'c=175 kg/cm2 m3 0.35 S. 522.34 S. 182.82 0.00 S/ - 0.35 S/ 182.82 0.00 S/ - 0.35 S. 182.82
05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.76 S. 40.40 S. 475.10 0.00 S/ - 11.76 S/ 475.10 0.00 S/ - 11.76 S. 475.10
05.04.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 56.55 S. 5.33 S. 301.41 0.00 S/ - 56.55 S/ 301.41 0.00 S/ - 56.55 S. 301.41
05.05 CABLES Y ACCESORIOS S. -
05.05.01 CABLE DE ACERO TIPO BOA DE Ø=3/8" m 25.85 S. 18.80 S. 485.98 0.00 S/ - 25.85 S/ 485.98 0.00 S/ - 25.85 S. 485.98
05.05.02 PENDOLAS DE F°G° DE Ø=1/4" m 7.52 S. 22.82 S. 171.61 0.00 S/ - 7.52 S/ 171.61 0.00 S/ - 7.52 S. 171.61
05.05.03 ACCESORIOS CRUCE AEREO L=16 M glb 1.00 S. 837.76 S. 837.76 0.00 S/ - 1.00 S/ 837.76 0.00 S/ - 1.00 S. 837.76
05.06 REVOQUES Y ENLUCIDOS S. -
05.06.01 TARRAJEO EXTERIOR (MORTERO 1:5 C:A) m2 5.60 S. 26.02 S. 145.71 0.00 S/ - 5.60 S/ 145.71 0.00 S/ - 5.60 S. 145.71
06 CRUCE AEREO L=12 M S. -
06.01 OBRAS PRELIMINARES S. -
06.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 79.88 S. 2.80 S. 223.66 0.00 S/ - 79.88 S/ 223.66 0.00 S/ - 79.88 S. 223.66
06.02 MOVIMIENTO DE TIERRAS S. -
06.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 10.03 S. 42.16 S. 422.86 0.00 S/ - 10.03 S/ 422.86 0.00 S/ - 10.03 S. 422.86
06.03 OBRAS CONCRETO SIMPLE S. -
06.03.01 SOLADO E=3" MEZCLA CEMENTO-HORMIGON 1:12 m2 4.00 S. 35.38 S. 141.52 0.00 S/ - 4.00 S/ 141.52 0.00 S/ - 4.00 S. 141.52
06.03.02 CONCRETO f'c=140 kg/cm2 + 30% P.M. m3 4.04 S. 454.78 S. 1,837.31 0.00 S/ - 4.04 S/ 1,837.31 0.00 S/ - 4.04 S. 1,837.31
06.04 OBRAS CONCRETO ARMADO S. -
06.04.01 CONCRETO f'c=175 kg/cm2 m3 0.55 S. 522.34 S. 287.29 0.00 S/ - 0.55 S/ 287.29 0.00 S/ - 0.55 S. 287.29
06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.56 S. 40.40 S. 790.22 0.00 S/ - 19.56 S/ 790.22 0.00 S/ - 19.56 S. 790.22
06.04.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 98.59 S. 5.33 S. 525.48 0.00 S/ - 98.59 S/ 525.48 0.00 S/ - 98.59 S. 525.48
06.05 CABLES Y ACCESORIOS S. -
06.05.01 CABLE DE ACERO TIPO BOA DE Ø=3/8" m 38.06 S. 18.80 S. 715.53 0.00 S/ - 38.06 S/ 715.53 0.00 S/ - 38.06 S. 715.53
06.05.02 PENDOLAS DE F°G° DE Ø=1/4" m 8.28 S. 22.82 S. 188.95 0.00 S/ - 8.28 S/ 188.95 0.00 S/ - 8.28 S. 188.95
06.05.03 ACCESORIOS CRUCE AEREO L=12 M glb 2.00 S. 772.56 S. 1,545.12 0.00 S/ - 2.00 S/ 1,545.12 0.00 S/ - 2.00 S. 1,545.12
06.06 REVOQUES Y ENLUCIDOS S. -
06.06.01 TARRAJEO EXTERIOR (MORTERO 1:5 C:A) m2 8.80 S. 26.02 S. 228.98 0.00 S/ - 8.80 S/ 228.98 0.00 S/ - 8.80 S. 228.98
07 RESERVORIO YURACCANCHA
07.01 OBRAS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO MANUAL m2 14.44 S. 2.56 S. 36.97 14.44 S/ 36.97 0.00 S/ - 0.00 S/ - 14.44 S. 36.97
07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 7.84 S. 2.80 S. 21.95 7.84 S/ 21.95 0.00 S/ - 0.00 S/ - 7.84 S. 21.95
07.02 MOVIMIENTO DE TIERRAS S. -
07.02.01 EXCAVACION MANUAL m3 2.91 S. 36.68 S. 106.74 2.91 S/ 106.74 0.00 S/ - 0.00 S/ - 2.91 S. 106.74
07.02.02 REFINE, NIVELACION Y COMPACTACION m2 7.84 S. 4.02 S. 31.52 7.84 S/ 31.52 0.00 S/ - 0.00 S/ - 7.84 S. 31.52
07.03 OBRAS CONCRETO SIMPLE S. -
07.03.01 SOLADO 2" MEZCLA C:H 1:12 m2 4.60 S. 36.02 S. 165.69 4.60 S/ 165.69 0.00 S/ - 0.00 S/ - 4.60 S. 165.69
07.04 OBRAS CONCRETO ARMADO S. -
07.04.01 CONCRETO LOSA MACIZA f'c= 210 kg/cm2 m3 0.92 S. 571.04 S. 525.36 0.92 S/ 525.36 0.00 S/ - 0.00 S/ - 0.92 S. 525.36
07.04.02 CONCRETO MUROS F'C=210KG/CM2 m3 2.40 S. 653.73 S. 1,568.95 2.40 S/ 1,568.95 0.00 S/ - 0.00 S/ - 2.40 S. 1,568.95
07.04.03 CONCRETO LOSA DE FONDO f'c= 210 kg/cm2 m3 2.76 S. 521.52 S. 1,439.40 2.76 S/ 1,439.40 0.00 S/ - 0.00 S/ - 2.76 S. 1,439.40
07.04.04 ENCOFRADO Y DESENCOFRADO MUROS m2 31.96 S. 73.86 S. 2,360.57 31.96 S/ 2,360.57 0.00 S/ - 0.00 S/ - 31.96 S. 2,360.57
07.04.05 ENCOFRADO Y DESENCOFRADO LOSA m2 8.26 S. 71.63 S. 591.66 8.26 S/ 591.66 0.00 S/ - 0.00 S/ - 8.26 S. 591.66
07.04.06 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 281.60 S. 5.33 S. 1,500.93 281.60 S/ 1,500.93 0.00 S/ - 0.00 S/ - 281.60 S. 1,500.93
07.05 REVOQUES Y ENLUCIDOS S. -
07.05.01 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:1 E= 1.5 CM m2 19.44 S. 34.09 S. 662.71 0.00 S/ - 19.44 S/ 662.71 0.00 S/ - 19.44 S. 662.71
07.05.02 TARRAJEO EXTERIOR (MORTERO 1:5 C:A) m2 19.93 S. 26.02 S. 518.58 0.00 S/ - 19.93 S/ 518.58 0.00 S/ - 19.93 S. 518.58
07.05.03 MORTERO 1:5, PENDIENTE DE FONDO m2 4.84 S. 29.95 S. 144.96 0.00 S/ - 4.84 S/ 144.96 0.00 S/ - 4.84 S. 144.96
07.06 OTROS S. -
07.06.01 TAPA METALICA SANITARIA 0.60 X 0.60 m und 1.00 S. 247.69 S. 247.69 0.00 S/ - 1.00 S/ 247.69 0.00 S/ - 1.00 S. 247.69
08 CASETA DE VALVULAS S. -
08.01 OBRAS PRELIMINARES S. -
08.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 1.28 S. 2.80 S. 3.58 1.28 S/ 3.58 0.00 S/ - 0.00 S/ - 1.28 S. 3.58
08.02 MOVIMIENTO DE TIERRAS S. -
08.02.01 EXCAVACION MANUAL m3 0.23 S. 36.68 S. 8.44 0.23 S/ 8.44 0.00 S/ - 0.00 S/ - 0.23 S. 8.44
08.02.02 REFINE, NIVELACION Y COMPACTACION m2 1.28 S. 4.02 S. 5.15 1.28 S/ 5.15 0.00 S/ - 0.00 S/ - 1.28 S. 5.15
08.03 OBRAS CONCRETO ARMADO S. -
08.03.01 CONCRETO MUROS F'C=175KG/CM2 m3 0.42 S. 522.34 S. 219.38 0.00 S/ - 0.42 S/ 219.38 0.00 S/ - 0.42 S. 219.38
08.03.02 CONCRETO LOSA DE FONDO f'c= 175 kg/cm2 m3 0.13 S. 497.09 S. 64.62 0.00 S/ - 0.13 S/ 64.62 0.00 S/ - 0.13 S. 64.62
08.03.03 ENCOFRADO Y DESENCOFRADO MUROS m2 5.71 S. 73.86 S. 421.74 0.00 S/ - 5.71 S/ 421.74 0.00 S/ - 5.71 S. 421.74
08.03.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15.76 S. 5.33 S. 84.00 0.00 S/ - 15.76 S/ 84.00 0.00 S/ - 15.76 S. 84.00
08.04 REVOQUES Y ENLUCIDOS S. -
08.04.01 TARRAJEO INTERIOR Y EXTERIOR MORTERO 1:5 m2 6.11 S. 26.02 S. 158.98 0.00 S/ - 6.11 S/ 158.98 0.00 S/ - 6.11 S. 158.98
08.05 VALVULAS Y ACCESORIOS S. -
08.05.01 VALVULA COMPUERTA DE BRONCE DE 1 1/2" + ACCESORIOS glb 1.00 S. 1,011.93 S. 1,011.93 0.00 S/ - 1.00 S/ 1,011.93 0.00 S/ - 1.00 S. 1,011.93
08.05.02 TAPA METALICA SANITARIA 1.10 X 0.85 m glb 1.00 S. 305.08 S. 305.08 0.00 S/ - 1.00 S/ 305.08 0.00 S/ - 1.00 S. 305.08
09 CERCO PERIMETRICO RESERVORIO S. -
09.01 OBRAS PRELIMINARES S. -
09.01.01 TRAZO, NIVELACION Y REPLANTEO m2 37.06 S. 2.88 S. 106.73 0.00 S/ - 37.06 S/ 106.73 0.00 S/ - 37.06 S. 106.73
09.02 MOVIMIENTO DE TIERRAS S. -
09.02.01 EXCAVACION EN MATERIAL SUELTO m3 1.47 S. 36.68 S. 53.92 0.00 S/ - 1.47 S/ 53.92 0.00 S/ - 1.47 S. 53.92
09.03 OBRAS CONCRETO SIMPLE S. -
09.03.01 CONCRETO CIMIENTO f'c=175 kg/cm2 m3 1.47 S. 484.15 S. 711.70 0.00 S/ - 1.47 S/ 711.70 0.00 S/ - 1.47 S. 711.70
09.04 CARPINTERIA METALICA S. -
09.04.01 PANEL PUERTA 1.00X2.10 m MALLA CON ALAMBRE GALV. N"12 COCADA DE 2" und 1.00 S. 379.52
S. 379.52 1.00 S. 379.52
0.00 S/ - 1.00 S/ 379.52 0.00 S/ -
09.04.02 SUMINISTRO DE INSTALACION DE TUBO F°N° DE 2" m 26.00 S. 107.64 S. 2,798.64 0.00 S/ - 26.00 S/ 2,798.64 0.00 S/ - 26.00 S. 2,798.64
09.04.03 PANEL CONTINUO 2.00X2.10 MALLA C/ALAMB. GALV. N°12 COCADA 2" und 2.00 S. 626.87 S. 1,253.74 0.00 S/ - 2.00 S/ 1,253.74 0.00 S/ - 2.00 S. 1,253.74
09.04.04 PANEL CONTINUO 2.15X2.10 MALLA C/ALAMB. GALV. N°12 COCADA 2" und 1.00 S. 693.39 S. 693.39 0.00 S/ - 1.00 S/ 693.39 0.00 S/ - 1.00 S. 693.39
09.04.05 PANEL CONTINUO 2.45X2.10 MALLA C/ALAMB. GALV. N°12 COCADA 2" und 4.00 S. 745.05 S. 2,980.20 0.00 S/ - 4.00 S/ 2,980.20 0.00 S/ - 4.00 S. 2,980.20
09.04.06 PANEL CONTINUO 2.60X2.10 MALLA C/ALAMB. GALV. N°12 COCADA 2" und 2.00 S. 795.65 S. 1,591.30 0.00 S/ - 2.00 S/ 1,591.30 0.00 S/ - 2.00 S. 1,591.30
09.04.07 PINTURA ANTICORROSIVA EN CARPINTERIA METALICA m2 51.49 S. 12.36 S. 636.42 0.00 S/ - 51.49 S/ 636.42 0.00 S/ - 51.49 S. 636.42
10 SISTEMA CLORACION
10.01 CASETA DE PROTECCION DE MADERA Y CALAMINA glb 1.00 S. 500.00 S. 500.00 0.00 S/ - 1.00 S/ 500.00 0.00 S/ - 1.00 S. 500.00
10.02 BASE O PEDESTAL DE ESTRUCTURA METALICA glb 1.00 S. 450.00 S. 450.00 0.00 S/ - 1.00 S/ 450.00 0.00 S/ - 1.00 S. 450.00
10.03 TANQUE ROTOPLAST DE 750 LT und 1.00 S. 355.93 S. 355.93 0.00 S/ - 1.00 S/ 355.93 0.00 S/ - 1.00 S. 355.93
10.04 SUMINISTRO E INSTALACION DE ACCESORIOS DEL SISTEMA DE CLORACION glb 1.00 S. 1,984.76
AUTOCOMPENSANTE S. 1,984.76 1.00 S. 1,984.76
0.00 S/ - 1.00 S/ 1,984.76 0.00 S/ -
11 GESTION DE RIESGOS S. -
11.01 PLAN DE GESTION DE RIESGOS glb 1.00 S. 3,000.00 S. 3,000.00 1.00 S/ 3,000.00 0.00 S/ - 0.00 S/ - 1.00 S. 3,000.00
11.02 CAPACITACION PERSONAL glb 1.00 S. 500.00 S. 500.00 0.15 S/ 75.00 0.70 S/ 350.00 0.15 S/ 75.00 1.00 S. 500.00
11.03 EQUIPAMIENTO PARA INCENDIOS und 1.00 S. 200.00 S. 200.00 1.00 S/ 200.00 0.00 S/ - 0.00 S/ - 1.00 S. 200.00
11.04 SEÑALIZACION und 2.00 S. 130.00 S. 260.00 2.00 S/ 260.00 0.00 S/ - 0.00 S/ - 2.00 S. 260.00
11.05 EQUIPAMIENTO PRIMEROS AUXILIOS und 1.00 S. 350.00 S. 350.00 1.00 S/ 350.00 0.00 S/ - 0.00 S/ - 1.00 S. 350.00
12 FLETE
12.01 FLETE TERRESTRE glb 1.00 S. 2,529.39 S. 2,529.39 0.50 S/ 1,264.70 0.00 S/ - 0.50 S/ 1,264.70 1.00 S. 2,529.39
12.02 FLETE RURAL glb 1.00 S. 2,573.90 S. 2,573.90 0.50 S/ 1,286.95 0.00 S/ - 0.50 S/ 1,286.95 1.00 S. 2,573.90
COSTO DIRECTO S. 78,158.39 S. 19,832.68 S. 49,129.13 S. 9,196.62 S. 78,158.39
GASTOS GENERALES 15% 0.15 S. 11,723.76 S. 2,974.90 S. 7,369.37 S. 1,379.49 S. 11,723.76
UTILIDAD 10% 0.1 S. 7,815.84 S. 1,983.27 S. 4,912.91 S. 919.66 S. 7,815.84
============ ============ ============ ============ ============
SUB TOTAL S. 97,697.99 24,790.85 61,411.41 11,495.78 97,697.99
IGV 18% S. 17,585.64 4,462.35 11,054.05 2,069.24 17,585.64
============ ============ ============ ============ ============
PRESUPUESTO TOTAL S. 115,283.63 29,253.20 72,465.46 13,565.02 115,283.63

PORCENTAJE PARCIAL 25.37% 62.86% 11.77%


PORCENTAJE ACUMULADO 25.37% 88.23% 100.00%