Republic of the Philippines

Province of Nueva Ecija


Municipality of San Isidro

DISASTER RICK REDUCTION AND MANAGEMENT PLAN


CY 2019

ISSUES AND RECOMMENDATIONS ACTIVITIES AGENCY TARGET TIME PERFORMANCE MEANS OF BUDGERTARY
CONCERNS RESPONSIBLE RECIPIENT FRAME INDICATOR VERIFICATIONS REQUIREMNTS
Lack of information Conduct of massive 1. Orientation on types LGU 9 brgys 1st-4th qtr Orientations and Attendance sheets 135, 000.00
re: hazards IEC on hazards of hazards MDRRMO information campaigns Photos
conducted Documentations
2. Printing of IEC LGU 9 BRGYS 1ST -4TH Printed pamphlets and Availability of iec 150, 000.00
materials MDRRMO QTR leaflets materials
3. inclusion of DRRM to LGU 9 brgys 1st-4th qtr DRRM included to Photos. Documentation,
school modules and MDRRMO school modules and SB resolution
activities DEPED, schools and activities
universities
No establish data to Identification of 1.Enhancement/ MDRRMO 9 brgys 1st – 4th Database on elements Database 100, 000.00
determine the communities prone to establishment of BDRRMC qtr 201 at risk established, Hazard maps
vulnerable hazards hazard, Vulnerability MPDO hazard map produced Photos
communities capacity and hazards ENGINEERING OFFICE documentation
Capital outlay: map & development of
Procurement of 1 set database on elements
desktop computer or at risk
laptop
2. Training/ Orientation MDRRMC BDRRMC 9 brgys 1st-4th qtr Training Conducted Attendance sheets 135, 000.00
on Map Appreciation MPDO Photos documentation
Lack of awareness Conduct orientation Orientation on MDRRMC 9 brgys 1st-4th qtr Local Climate Change LCCAP 135, 000.00
on climate change on RA 9729 – Climate integration of Climate BDRRMC Action Plan formulated Photos
impact Change Act of 2009 Change Adaptation to MPDO documentation
DRRM plans &
programs
Lack of awareness Conduct continuous Orientation and strict Mayor’ Office 9 brgys 1st-4th qtr RA 9003 implemented Photos 135, 000.00
on RA 9003- orientation on RA implementation of RA MPDO documentation
Ecological Solid 9003 9003 MENRO
Waste Management
of 2000
Training on Waste MPDO MENRO 9 brgys 1st-4th qtr Trainings conducted Attendance sheets 50, 000.00
Management Mayor’s Office Photos Documentation
Massive and intensive MPDO 9 brgys 1st-4th qtr IEC conducted, materials IEC materials 50, 000.00
IEC, brgy and MENRO distributed Photos
community visitation Mayor’s Office documentation
and dialogue
Implementation of 3 Rs- MPDO 9 brgys 1st-4th qtr 3 R system implemented Waste production
reduce, reuse, recycle MENRO decreases
system Mayor’ office Photos documentation
Lack of Evacuation Construction of Construction of Mayor’s Office 3 brgys 1st-4th qtr tents, rechargeable Photo 2,000, 000.00
center evacuation center, evacuation Center. MPDO Poblacion lamps, generators, Documentations
Improvement of Provisions of tents, Engineering Pulo portable toilets Official receipts
existing area as rechargeable lamps, Mangga vouchers
evacuation center generators, portable
toilets
Lack of early Enhancement of early Formulation of MDRRMO BDRRMC 9 brgys 1st – 4th qtr Systems and procedures Copy of plan
warning system warning devices communication plan MPDO installed Define roles and
function
Procurement of Communication devices Vouchers, Ors 500, 000.00
communication devices, procured
bells or sirens
Installation of signage Signages installed Vouchers, Ors 150, 000.00
Posting of emergency & Local communities Photo
disaster hotlines/ informed documentations
directory
Lack of Public Comprehensive Masive information MDRRC 9 brgys 2nd-4th Information Photos 100, 000.00
knowledge and awareness programs campaign BDRRMC qtr disseminated in all brgys documentations
information on and activities on Development of IEC Mayor’s Office
disaster disaster preparedness materials
preparedness.
Insufficient training Provision of Training on: MDRRMC 9 brgys 1st-4th qtr Trained respondents List of trained 300, 000.00
on disaster continuous trainings, 1. Basic Life Support BDRRMC individuals
preparedness in the drills and exercises for and Standard First Aid BFP Photos
barangay level, capacity building on 2. Water Search and PNP documentation
volunteer groups disaster preparedness Rescue Schools
and educational and management 3. Fire Rescue
institutions > Earthquake and fire
drill
Insufficient number Procurement of Procurement of: MDDRMC 1ST – 4TH Necessary tools and Inventory of tools and 700, 000.00
of equipment/ needed equipments, Equipments/tools BDRRMC QTR supplies purchased supplies purchased
machineries/ tools/ materials and supplies 1. Mobile generator set Mayor’s Office Ors / DRs
materials and 2. two way hand held MPDO Vouchers
supplies radio Budget Office Photo
3. emergency light Treasurer’s Office Documentations
3. search lights Health Office
4. Responder’s Personal MSWDO
Equipment (PPEs)
4. first aid kit
Supplies/ commodities MDDRMC 1ST – 4TH Necessary tools and Inventory of tools and 2,743,818.00
1. Food ( rice, canned BDRRMC QTR supplies purchased supplies purchased
goods, noodles, etc) Mayor’s Office Ors / DRs
2. various medicines/ MPDO Vouchers
drugs and medical Budget Office Photo
supplies Treasurer’s Office Documentations
3. hygiene kit and Health Office
hygiene equipments MSWDO
and supplies for all ages
4. agricultural supplies
TOTAL 7,383,818.00

Prepared by: Approved :

ALMARIO L. ORTIZ CESARIO I. LOPEZ, JR


MDRRM Officer Municipal Mayor