Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
• Status of construction industry – identify the gap
• Overcome stereotypes: “manufacturing”
“this is what we do”
• Establish general awareness of Lean Construction:
What? Why? How?
• Create an incentive to initiate / continue a Lean journey in your
project(s) or organization
• Establish a demand for Lean education
• Status of Lean Construction implementation in Qatar
The Problem – 1) Poor Productivity
Productivity by industry in the US ( indexed; 1.0 = 1950)
The Problem – 2) Waste
Manufacturing Construction
57%
12%
Construction Industry Institute, 2004
The Problem – 3) Inefficiency
McGraw Hill 2013
The Solution – Different Thinking
(Breakthrough Learning)
Different Outcome =>
Change Action
(Incremental Learning)
The Solution – Production Theory
(Koskela 1992)
Does it Work?
• Toyota Production System (TPS) 1950s (Taiichi Ohno)
• Construction Vs. Manufacturing
• Project Vs. Production
• Construction projects are unique and have distinctive peculiarities i.e.
on site production, one‐of‐a‐kind production, and temporary
(Koskela, 2000).
• IGLC: construction is fundamentally different from manufacturing.
Therefore, reinterpretation of the theory of is needed to develop a
theory‐based methodology for construction.
• Lean + Construction = creativity
What is Lean Construction?
• Creating ideal state of designing and constructing a facility
using standard processes to:
• Provide / generate value
• Eliminate waste
• Continuously improve
• Business Philosophy ‐ Operation Strategy
Lean Construction
• Lean Construction Institute (LCI)
“Lean Construction is a production management‐based approach to project
delivery – a new way to design and build capital facilities to maximize value
and minimize waste….”
• AGC OF America
“Lean Construction is a set of ideas, practiced by individuals in the
construction industry, based in the holistic pursuit of continuous
improvements aimed at minimizing costs and maximizing value to clients in
all dimensions of the built and natural environment: planning, design,
construction, activation, operations, maintenance, salvaging, and recycling.”
What is NOT Lean Construction?
• Lean Production grafted onto construction
• Limited to Quality Management
• Cost Cutting
• Eliminating Jobs
• Beating up suppliers and subcontractors
• Doing Value Engineering During Construction
• Being Stingy
Value
• Value is generated when:
• Customer capabilities are expanded, covering new needs
and purposes.
• The facility better fulfills the purposes and demands of
customers, operators, and other stakeholders
• However, value is not just fitness for use or performance
relative to cost
(LCI 2002)
Waste
Wastes Examples of Wastes in Construction
Ohno (1988) ElSabek and McCabe 2018)
Excess Materials of concrete or asphalt
1) Overproduction Over excavation
2) Inventories Raw materials on site
work in progress
3) Over‐processing Scope elegance
4) Defects Non‐conformance to quality
5) Unnecessary motion Movement at site
6) Unnecessary transport Transportation of workers to/from labour camp to
field and to/from break area
Mob / demob of materials
7) Waiting Worker waiting for work or work waiting for workers
Idle equipment
Traditional Construction Management
(Howell 2010)
Integrated Project Delivery
(Howell 2010)
Examples of Enabling Tools
• Integrated Project Delivery (IPD)
• Last Planner ® System (LPS®)
• IMPact Framework
• Lean Design (Target Value Design, Process Design, BIM, and VDC)
• Root cause analysis (5 Why and fishbone)
• Problem Solving Techniques (A3s)
• Decision Making System (Choosing By Advantages)
• Continuous improvement (PDCA, Kaizen, Plus/Delta)
• Error Proofing
• 5S Plus Safety ‐ Lean Assembly (Sort, Set, Shine, Standardize, &
Sustain)
Examples of Enabling Tools (con’t)
• Offsite fabrication
• Just in Time (JIT)
• Value Stream Mapping
• Supply Chain Management
• Daily crew huddles
IMPact Framework
(ElSabek 2017)
Lean Assembly – 5S + Safety
• Sort…Set…Shine…Standardize…Sustain + Safety
• Cleaner site is safer and more productive
BEFORE AFTER
© Walbridge (images)
Lean Assembly – 5S + Safety
• Everything in its place and
a place for everything!
(Abdelhamid 2014)
The Problem - Reasons for
Unmet Weekly Commitments
Golden Mine
We have to change what we
do to get different results
“Breakthrough Learning”
The Problem - Production Variation
Overburden Workload
Variation
Capability
Waste
Planning
Failures Execution Failures
the Solution - LPS®
• Developed by Glenn Ballard & Gregory Howell in 2002
• Process design and not only product design
• LAST PLANNER® SYSTEM (LPS®) ensures:
• Reliable commitment
• Predictable workflows
• Rapid learning
(Ballard et al. 2002)
the Solution - LPS®
Project Zeneca Ag Products - Building 196 Run Date: 2/21/00 12:57
Excavate footing 4-Nov Cal-Wrecking Possible delay caused by overs ized footing.
Total Activities 27
Activities Ready 25
Make‐ready Plan With Constraint Analysis
1) Master Scheduling
2) Phase Scheduling Weekly Work Planning
1 WEEK PLAN
PROJECT: Pilot FOREMAN: PHILLIP
ACTIVITY DATE: 9/20/96
Est Act Mon Tu Wed Thurs Fri Sat Sun PPC REASON FOR VARIANCES
Gas/F.O. hangers O/H "K" xxxx xxxx No Owner stopped work
(48 hangers) Sylvano, Modesto, Terry (changing elevations)
Gas/F.O. risers to O/H "K" xxxx xxxx xxxx xxxx No Sam e as above-worked on
(3 risers) Sylvano, Mdesto, Terry backlog & boiler blowdown
100% 100% 36" cond water "K" 42' xxxx xxxx xxxx Yes
90% 90% 2-45 deg 1-90 deg Charlie, Rick, Ben
80% 80% Chiller risers (2 chillers wk.) xxxx xxxx xxxx No Matl from shop rcvd late Thurs.
70% 70% Charlie, Rick, Ben Grooved couplings shipped late.
60% 60% Hang H/W O/H "J" (240'-14") xxxx xxxx xxxx xxxx xxxx xxxx Yes
50% 50% Mark M., Mike
40% 40% Cooling Tower 10" tie-ins (steel) xxxx xxxx xxxx xxxx xxxx xxxx Yes
30% 30% (2 towers per day) Steve, Chris, Mark W.
20% 20% Weld out CHW pump headers xxxx xxxx xxxx xxxx xxxx xxxx Yes
"J" mezz. (18) Luke
10% 10%
PPC Weld out cooling towers (12 towers) xxxx xxxx xxxx xxxx xxxx xxxx No Eye injury. Lost 2 days
0% 0%
4 Week Moving Average Jeff welding time
F.R.P. tie-in to E.T. (9 towers) 50% xxxx xxxx xxxx xxxx xxxx xxxx Yes
Firt, Packy, Tom
WORKABLE BACKLOG
(LCI 2002)
Domains of Project Delivery
CPM‐based; Activity‐Centered;
Management by Exception
Individual 2D/3D
craft‐contracts
Command & Control
Directives‐Driven
(Abdelhamid 2014)
Domains of Project Delivery
CPM‐based; Activity‐Centered;
Management by Exception
Lean‐based; Management by Means 2D/3D
Individual (planning inclusive of execution party; fire prevention)
craft‐contracts
BIM/VDC
IPD/IFOA
Relational
(system
optimization)
Command & Control
Directives‐Driven
Dialogue & Collaboration
(planning is an ongoing conversations)
(Abdelhamid 2014)
LEAN PROJECT DELIVERY
SYSTEM (LPDS)
(Ballard 2006)
Culture of Lean Construction
• Problems are recognized as opportunities
• It’s okay to make legitimate mistakes
• Problems are exposed because of increased trust
• People are not problems – they are problem solvers
• Emphasis is placed on finding solutions instead of “who did it”
The Radical Shift
Non-Lean Lean
Planning Knowledge Learning
“Start Early” “Finish Early”
Scheduling Activities are performed as Activities are performed at the last
soon as possible responsible moment
Management Trades Cost for Speed Reduce Cost and Increase Speed
• Implemented in 3 pilot projects at Lusail City
• Adapted by PWA in March 2018
How to Start?
• Be patient
• Be determined
• Look for change‐agents
• Conversation
• Leading by examples
• Judging by results
Questions
Email: Luai.Sabek@mail.utoronto.ca
http://linkedin.com/in/luai‐m‐sabek‐phd‐
pe‐peng‐pmp‐3a7b3911
Benefits of Lean Construction
McGraw Hill 2013
Success Stories
• Temecula Valley Hospital 2013
• $700 million project
• 40% below market cost
• Realized 200% increase
in labor productivity through
the 7 partners
• 30% operational cost improvement in the facility
• Sutter Health ( $5 billion program)
Thank you for attending!
See you next year
Attendance certificates are available from the CPD certificate collection point. In order to collect your certificate, you
must attend the first 30 minutes of the workshop(s) you have chosen.