Technical Buildings Construction Control

PROGRESS REPORT

Document : Technical Buildings Construction Control


Document No : 26
Period : 08.01.2018 – 22.01.2018
Area : 1, 2 & 3 (Makkah Station-Jeddah Station)
Prepared By : ALPHA-AIS
Controlled By : SIEMENS

This document is property of Siemens Rail Automation SAU and Confidential. The information
contained in the document may not be reproduced.

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 1 of 19


Technical Buildings Construction Control

OVERALL

Buildings` Progress
64%
53% 50% 50%
37% 39% 36%
26% 26% 26% 24%
16% 18% 16%
0% 0%

ISR ISR ISR ISR MSR ISR ISR MSR MSR MSR MSR ISR MSR ISR ISR MSR
170 158 147 136 A 114 103 C C 88 A 78 C 63 50 C 36 23 10 A 2
126 KAIA
Link

Work Package Progress


88%
72% 73% 66%
41%
32%
0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 2 of 19


Technical Buildings Construction Control

MSR A 2
No activity during the period.

MSR A 2
100%
72% 70% 70%

40%

1% 0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 3 of 19


Technical Buildings Construction Control

ISR 10
Lean concrete casted.

ISR 10
100%
87% 80%
76%

40%

1% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 4 of 19


Technical Buildings Construction Control

ISR 23
Precast wall panels erected. Floor screed casted.

ISR 23
100%
80% 80% 76%

40% 40%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 5 of 19


Technical Buildings Construction Control

MSR C 36
No activity during the period.

MSR C 36
100%
80%
69% 70%

40%

0% 0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 6 of 19


Technical Buildings Construction Control

ISR 50
Precast wall panels aligned and grouted. Precast hollow core roof slabs installed.

ISR 50
100%
87% 80%
76%

40% 47%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 7 of 19


Technical Buildings Construction Control

MSR C 63
Soil bearing capacity test (plate load test) conducted.

MSR C 63
100%
81% 80%
70%

40%
24%
0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 8 of 19


Technical Buildings Construction Control

MSR A 78
Precast hollow core roof slab to slab joints grouted. Precast parapets installed.

MSR A 78
100% 100%
83%
70%
61%
40%

0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 9 of 19


Technical Buildings Construction Control

MSR C 88
No activity due to location change.

MSR C 88

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 10 of 19


Technical Buildings Construction Control

MSR C KAIA Link


Strip footing rebars fixed, formworks erected and concrete casted up to -0.35 m level.

MSR C KAIA Link


100%
81% 80%
70%

40%
24%
0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 11 of 19


Technical Buildings Construction Control

ISR 103
Earthing conductors installed. Filling and compaction in progress.

ISR 103
100%
73%
48%
40% 40%

0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 12 of 19


Technical Buildings Construction Control

ISR 114
No activity due to land acquisition problem.

ISR 114

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 13 of 19


Technical Buildings Construction Control

MSR A 126
Slab concrete casted. Precast hollow core floor slabs installed.

MSR A 126
100%
83% 80%
70%

40%
29%

0% 0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 14 of 19


Technical Buildings Construction Control

ISR 136
Cores drilled through precast hollow core roof slabs.

ISR 136
100% 100%
87% 88%
60% 67%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 15 of 19


Technical Buildings Construction Control

ISR 147
Cores drilled through precast hollow core roof slabs.

ISR 147
100% 100%
87% 88%
60% 67%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 16 of 19


Technical Buildings Construction Control

ISR 158
Manholes dug, rebar fixed, formwork erected and concrete casted.

ISR 158
100% 100%
87% 90%
75%
60%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 17 of 19


Technical Buildings Construction Control

ISR 170
No activity during the period.

ISR 170
100%100%100%100% 100%
80%

0% 0% 0% 0% 0%

Area I – II – III Weeks No.2 & 3 of Year 2018 Page 18 of 19


Technical Buildings Construction Control

END OF DOCUMENT