Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
©IstockPhoto.Com/idealistock
By Marcelo E. Valdes, Steve Hinton, The National Electrical Code (NEC) has included requirements
and Francisco Martinez for arc-flash-related labeling for several code cycles [1]. Increasingly rigorous require-
ments for specific arc-flash-related protection attempt to reduce any arc-flash
hazards to which personnel may be exposed. They may be exposed to arc-flash
hazards during planned energized work or accidentally at any time. The risk-
Digital Object Identifier 10.1109/MIAS.2018.2868354
control mechanisms added to the NEC in recent times include additional signage
Date of publication: 5 November 2018 requirements and two articles that intend to reduce arc-flash hazard by decreasing
The formulas are used to calculate a value referred to as ●● variable system topology and varying short circuit current
100% arcing current and another at 85% of the first value. ●● incorrect assumptions regarding conductor impedances
The calculations are based on three factors used as vari- ●● conservative utility high-fault-current assumptions
ables within the equations: ●● conservative fault study methods by power systems
The first parameter, system voltage, is easily determined. ●● a variance in source voltage due to system loading
The second is often estimated at preliminary phases of a ●● incorrect assumptions about bus/conductor gap or
project design. And even in the later stages of a project, the arc environment (i.e., size of equipment enclosure or
short circuit current value may depend on several assump- compartment).
tions, switching or operating scenarios, and worst-case
tolerances. For the short circuit evaluation of equipment,
power system engineers performing short circuit calcula-
Table 3. A portion of IEEE 1584 Table 4, from p. 12
tions purposely drive any potential error toward higher val-
ues because that is conservative from an equipment-rating System Typical Gap Between
perspective. Ensuring properly rated equipment, per NEC Voltage (kV) Equipment Type Conductors (mm)
110.16, involves calculating maximum short circuit fault 0.208-1 Open air 10–40
current and evaluating it against the withstand and inter-
rupting ratings of the electrical distribution and protection Switchgear 32
equipment. Conservatism from the equipment ratings MCC and panels 25
perspective is not necessarily appropriate from an arc-
Cable 13
flash calculation perspective. For arc-flash calculations, it
70% 50%
13 mm, 85%
60% 25 mm, 85%
40% 32 mm, 85%
40 mm, 85%
Ia as % Ibf
Ia as % Ibf
50%
30%
40%
13 mm, 85%
25 mm, 85% 20%
30%
32 mm, 85%
40 mm, 85%
20% 10%
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
FIGURE 1. A plot of 85% arcing current (I a) as the percentage of FIGURE 2. A plot of 85% arcing current (I a) as the percentage of
available bolted fault current (I bf) for a 480-V system, per the IEEE available bolted fault current (I bf) for a 208-V system, per the IEEE
1584-2002 model. 1584-2002 model.
Zone-Selective Interlocking
Zone-selective interlocking (ZSI) is commonly avail- FIGURE 4. A simple three-circuit breaker ZSI scheme with two 1,200-A
able from all circuit breaker manufacturers. In all cases, feeders providing a restrain signal to a single 2,000-A main.
ers is not improved, even though the devices are part of ●● might not be sufficiently trained to know how to
a ZSI scheme. The 1,200-A feeders may meet the letter of operate it
the code text but not its intent. ●● might not be sufficiently trained to know the need to
systems may provide various ways to test the ZSI system, been incorrectly planned with the administrative con-
which has traditionally been a concern when installing trol accidentally omitted
such systems. When installing a ZSI system, it is impor- ●● could operate the incorrect control
tant to verify that it is wired correctly and signals are ●● could operate it at the wrong time
getting to the correct devices. Generally, if the wiring ●● might not know the control could be inoperative.
is damaged upstream, devices will revert to the unre- The possibility of human error will lower the value of
strained timing and, hence, protect well, but selectivity may an administrative control, relative to fully automated solu-
be compromised. tions, regardless of how effective the control is in mitigat-
ing the hazard. See ANSI Z10 [3] for further discussion.
Bus Differential Protection
Bus differential protection works on the simple concept Energy-Reducing Maintenance Switching
known as Kirchhoff’s current law. Simply stated, for this with Local Status Indicator
application, it means that all of the measured currents into
a bus must balance the measured currents leaving it. Any Sensitive to What?
imbalance in current, above the programmed threshold, Energy-reducing maintenance switches are offered by cir-
must be a fault. In a differential protection scheme, the dif- cuit breaker manufacturers and even by at least one manu-
ferential relay is connected to current sensors that measure facturer of fused UL 977 listed power switches [13]. In the
all of the power coming in, sources, and power going out code-defined requirements for this function, there are no
to loads. A fault below a feeder, such as fault 2 fed by the performance requirements, just that they must be provid-
1,200-A feeder shown in Figure 4, has power measured ed. Protection can only work as intended if it is set sensi-
going into the main bus and going through the feeder. The tive to the available arcing current magnitude. The benefit
differential relay will not sense that current as a fault. A fault of these switches is that they generally have a broad range
in location 1 on the bus in Figure 4 will cause power to flow of adjustability and should be able to be adjusted to be
into the bus and be measured at the main circuit. However, sensitive enough to achieve acceptable arc-flash reduc-
neither feeder is carrying the power out of the bus, and the tion. However, a responsible party must establish what
differential relay will sense the bus fault and signal the main the expected arcing current is and ensure the protection is
circuit breaker to open. Like the ZSI scheme described pre- adjusted correctly. Once commissioned, maintenance per-
viously, a differential scheme that includes the three circuits sonnel should only need to enable and disable the func-
shown in Figure 4 will provide additional protection for the tion as prescribed in the planned task procedures.
main bus but not for the feeder circuits. To determine the
exact zone of protection provided, the equipment draw- Indication and Control Local to What?
ings must be examined, with the exact location of current Maintenance switches should be used with indicator lights.
transformers and circuit breakers noted. Again, the letter The code states that a local indicator must be provided,
being controlled by the switch. Most importantly, the per- the switch. The protection provided by the circuit
son who is relying on that protection should be aware of breaker may be improved, but that does not mean the
its status and what circuit or equipment is being protected. circuit breaker or the load circuit is electrically safe.
To facility operators, it may be important to know if the ●● The arc-flash hazard at the line side of the circuit
protection is accidentally left on when not needed. breaker is not affected by an energy-reduction main-
The maintenance control switch should have test pro- tenance setting (ERMS) on that circuit breaker. Protec-
cedures for confirming that the circuit breaker or relay tion for the line side depends on an upstream device
being controlled has received the signal and processed it that may not be affected by the switch mounted in the
correctly. These should be followed up on initial start-up proximity of the circuit breaker.
and at regular intervals afterward. This could be referred ●● A bus, or equipment, may have multiple sources, and,
to as positive feedback of status. The switch should be unless the switch controls all of them, they may need
lockable so it can be properly locked in the on state by to be addressed simultaneously to make sure the haz-
maintenance personnel. ard from each source is minimized.
This function can temporarily compromise coordina- ●● When the switch is local to the circuit breaker but the
tion, until it is disabled. Users are often concerned about actual equipment to be worked on is remote, there are
forgetting to turn this off after a task, and an obvious opportunities for mistakes (e.g., setting the switch on
indication of the status is often designed into the system. the wrong OCPD or having the switch operated by
Indications, such as tower lights evident through the elec- other personnel if it’s not properly locked out in the
trical room, sound alarms, and even e-mails to supervi- enabled position).
sory personnel, have been used to ensure a maintenance ●● The switch may be used properly, but, if the setting is
switch is not left on indefinitely. Similar measures should not sensitive enough, arc-flash protection may not
be used to ensure that a maintenance switch is used be improved.
when needed. The manufacturer should be consulted for ●● Setting the normal instantaneous protection temporari-
device implementation information because wiring and ly lower, and thereby using it as an ERMS, may provide
space requirements may vary. the expected energy-reducing function. However, this
method does not provide the annunciation function
What About the Arc-Flash Label? that is described in the code, and, therefore, it is tech-
Another consideration when relying on an energy-reduc- nically not an acceptable method.
ing maintenance switch to provide lower levels of arc-
flash incident energy is whether that lower level should Approved Equivalent Means Solution
be reflected on the NFPA 70E defined arc-flash label and Energy-Reducing Active Arc-Flash Mitigation System
[2, Sec. 130.5(D), p. 28] installed on the equipment. There The code does not clearly explain what an approved
are many opinions about this subject. One argument is equivalent means or what an active energy-reducing
that arc-flash labels should not be ambiguous or complex arc-flash mitigation system is. However, there are sev-
and should be conservative in case the reader is not fully eral possibilities should the authority having jurisdiction
aware of proper procedures or inadequately trained. (AHJ) choose to accept them. Components of such sys-
tems may include
Administrative Procedures Require Qualified Personnel ●● for sensing: light-sensing relays as event detectors and
maintenance switch can be reflected in the data provided voltage circuit breakers, low-voltage fuses, medium-
by the arc-flash study and form part of the risk assess- voltage fuses, crowbars to divert energy and collapse
ment [2, Sec. 130.5, p. 25] required to plan an energized system voltage, or combinations of these.
work task [2, Sec. 130.2(A), p. 24]. The other argument Arc-flash relays are usually able to directly sense the
is that the maintenance function is embedded in the light from an arc-flash event near the sensor location
equipment and always available to be used, so the better [14]. These devices are fast and considered to be very
protection can be reflected in the arc-flash label, or a sec- good at sensing an arcing fault event. However, they have
ond label, that clearly indicates the incident energy with some drawbacks. They can unexpectedly operate from
the switch turned on or off. However, this may not be the light emanating from a circuit breaker interrupting
rupting circuit breaker within the affecting arcing 240.67 Fusible Switches,
enclosure using ZSI restraint from Improving Protection
the trip unit controlling the circuit current. In 2017, the NEC added Section
breaker [12, C, p. 1643] or via other 240.67, which describes requirements
interlocking methods. similar to those found in 240.87 for
Overcurrent relays, ANSI 50/51 switches with 1,200-A or higher fuses.
devices, may be able to provide additional protection and The requirements, as defined, are not necessary to be
control over and above that provided by circuit breaker enforced until 2020. The existence of the requirements
trip units in some situations. One example is sensing indicates that the code-making panel perceives a poten-
faults on the conductors between the secondary of a sub- tial hazard and consequential risk to personnel that
station transformer and the first secondary low-voltage merit consideration. The 2020 enforcement date seems
devices. Details of these implementations are beyond the to be an attempt to delay a solution having limited com-
scope of this article, and some references on secondary mercial availability.
substation protection are provided in [5]. The section allows fuse protection to be evaluated
Low-voltage circuit breakers and power switches can with the arcing current to investigate if the fuse will
be controlled from various sensing devices. When using a protect sufficiently quickly without additional protective
combination of interrupting devices and external controls, measures being applied in the system. The requirement
it is important to understand the full operation time of is for fuses to clear in 70 ms or fewer at the estimated arc-
sensing, signaling, and switching devices. In many cases, ing current. The authors believe this requirement may be
although the relay sensing may be very fast, the combina- insufficient for various reasons.
tion of the various delays provides for slower protection ●● It forces the AHJ to evaluate complex time–current-
than the integral instantaneous protection provided by curves. Not all AHJ have the skills to evaluate time–
the circuit breaker. In most cases, external relays should current curves.
only be used in special applications that warrant the com- ●● The time–current curves provided will be for a specific
plexity and cost. brand and model of fuse. When a fuse melts, it could
Medium-voltage circuit breakers may be especially be replaced by one with different characteristics. A
suitable to protect conductors and equipment fed from conservative course of action would be to use enve-
a transformer prior to the first low-voltage device. Such lope or test fuses, like fuse-to-circuit breaker series
circuit breakers may be controlled in many ways. See the rating tests do, so not just one manufacturer’s fuses
references on secondary substation protection provided in are considered.
[5] and [12]. ●● The 70-ms clearing time exceeds three cycles, and
Low- and medium-voltage fuses could, potentially, be even a three-cycle clearing time is not the best a fuse
accelerated by use of a crowbar to divert energy, collapse can do. Fuses in this size range are current limiting
voltage, and force the highest available fault current to and provide best performance when operating in
flow through the fuses to ensure they operate in their their current-limiting range. Fuses operating in their
current-limiting range. If the current is high enough, it current-limiting range may provide the best arc-flash
will flow for under half a cycle, and arc-flash protection incident energy mitigation possible for any overcur-
can be very quick with minimal consequences. Crowbars rent device.
are shunt devices that divert current and collapse system ●● Fuse curves are drawn as single-phase devices. When
voltage by causing a minimum impedance fault some- a fuse melts in one phase, the fault current in a three-
where in the system. As arc-flash protection, they should phase balanced fault changes to a single-phase fault at
work very well if the arc fault is detected. However, the 87% of the original fault current, increasing the possi-
bolted fault current may not be desirable and have seri- bility of the second or third fuse melting more slowly.
ous consequences to the distribution system. If such a The fuse curves an AHJ would review are incapable of
mitigation system is considered, the manufacturer should revealing slower melting times.
be consulted to fully understand the implications of the IEEE 1584-2002 (Sect. 5.6, p. 13) includes formulas for
application, how the sensing will operate, and how the fuses based on testing done by the research group for one
energy diversion device will operate. At the time of this brand of fuses. The tests were performed primarily at 600 V.
writing, most crowbar devices seem to be one-time-use The test data were used to derive several fuse formulas