Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. What is estimation?
An estimate is the probable cost of a construction work.
Estimation is the process of calculating quantities and cost.
Page | 1
4. What is difference between cost and estimation?
Cost
It is the actual rate.
The cost of construction can be known from physical measurements of items of
work at site.
Estimation
It is the probable cost.
The accuracy of an estimate depends on a careful study of the various dimensions
on the drawings.
It also depends on the skills of estimator.
Page | 2
10. What is a measurement sheet? And what are the guidelines of writing a measurement
sheet?
Used for finding out the quantities of work from detailed measurements.
The estimator takes of the various dimensions from the drawings and tabulates
them in a measurement sheets.
It contains columns – description, number, length, breadth, depth or thickness
and quantity.
Page | 3
12. What are the spot items?
Items that require alteration or repairs in an existing building or structure.
Spot items need to be inspected on site to gain an understanding of extent of
work that will be involved.
A good knowledge is required in order to identify spot items.
In BOQ spot items are consider as single item.
Page | 4
UNIT-2
Different types of Estimate their uses and characteristics, Schedule of
Quantities, Schedule of Rates and its uses, Stages of work, Complete Estimate
of a Project, Methods of taking out Quantities, Measurement Sheet, Abstract
Sheet, Bill of Quantities.
A. A detailed estimate
Includes the detailed particulars for the quantities, rates and cost of all the items.
Quantities of all items are calculated from their respective dimensions.
Drawing and measurement sheets are used.
Quantities are multiplied by their respective rates.
Best and most accurate estimate
Page | 5
C. A Quantity estimate or quantity surveys
Complete estimate or list of quantities for all items of work required to complete
the concerned project.
D. Revised estimate
Detailed estimate for the revised quantities and rates of items of works.
Deviations of structural nature are not allowed.
Also required when the sanction estimate is more than the actual requirement.
Required when sanction amount is exceeded due to change of rates or addition
of works.
a comparative abstract form showing variations of quantity, rate and amount of
each item is needed
Required due to change of rate or quantity of material.
E. A supplementary estimate
Due material deviation of structural nature.
Comparative abstract form is not needed.
Required due to new works or change of design.
14. What are the factors that are to be considered during preparation of detailed
estimate?
Quantity of materials.
Availability of materials.
Transportation of materials.
Location of site.
Local labour charges.
Page | 6
15. Write a short note on schedule of quantities OR bill of quantities?
Complete list of all items of work.
A detailed statement of work, prizes, dimensions and other details for the erection
of a building by contract.
Required to calculate the quantities of different material required for the project.
The BOQ when multiplied by the corresponding rates and totalled gives estimated
cost.
Page | 7
III. Report.
IV. Design data and calculation.
V. Specifications.
VI. Detail statement of measurements, quantities and rates.
VII. Analysis of rates for unscheduled items.
VIII. Detailed estimate in specify form.
IX. Abstract.
X. General abstract.
XI. Drawings.
Page | 8
UNIT-3
Study of mode of measurement as stipulated in IS – 1200, Classification of
strata as per IS – 1200, trial pit data, lift and leads, Unit of measurements.
1. Guidelines for mode of measurement
Steel work shall be measured in weight (Quintal or Kg.) Thus the quantity of steel –
Volume X density where Volume – Area X length of member and area can be
referred from steel table for an ISA, ISMB OR ISMC sections.
Certain items shall be measured in number such as plumbing fittings.
The items which cannot be measured by surveyors are classified as a job work.
The items which have long length as compared to the cross sections can be
measured in running meter.
The items whose thickness is uniform can be measured in Square meter. For
example Plastering, Flooring, etc.
The items whose Length, Breadth and depth are prominent are classified as
voluminous items which are measured in Cubic meter.
Page | 9
3. Various mode of measurement
Number (No.) Running Meter (Rm) Square Meter (Sq.m) Cubic Meter (Cum)
Wash basins Compound wall Collapsible door Excavation in
foundation
Water closets Barbed wire fencing D.P.C layer P.C.C in foundation
Manhole Retaining wall Flooring All R.C.C items
Inspection chamber Skirting Brick work less than Brick masonry more
230mm thickness than 230mm thick
Plumbing fittings Railing Door grills Stone masonry
Steps in staircase Water supply pipes Door and window Wood work in doors
shutters and windows
C.I. Brackets Sewage pipes Internal plaster 12mm U.C.R in foundation
thick
Pot hole String Course and External plaster B.B.M in foundation
cornices
All types of traps R.C.C or Hume pipe A.C sheet roofing Earth filling
Excavation for gulley Eaves gutter Internal painting Soling
trap chambers
Urinals Excavation for cable External painting Reinforced Brick
masonry
Culverts Concrete Jaali
Roads R.C.C. sun breakers
Footpaths Honey comb brick
work
Expansion joints Dado in bathrooms
Brick bat coba
Floor pavement
Pointing
Glazing work
Varnishing
Page | 10
UNIT-4
Bill certification Part rate certification, Interim/Running bill Certification
1. What is meant by completion certificate or practical certificate?
This certificate is issued when the work is practically complete.
This certificate is issued under following circumstances.
a. When contractor gives a notice.
b. When the architect applies for occupation certificates.
c. When water connection is obtained.
d. When the architect applies completion certificate.
e. When the local authority grants the occupation certificate or completion
certificate.
Page | 11
3. What is meant by Final certificate?
After the completion of work the architect has to issue a final certificate to the
contractor.
The condition for Final certificate is stated below.
a. The certificate is issued at the end of defect liability period which is considered
from the date of virtual completion.
b. The contractor is issued a schedule of defects if there is defect in the work.
c. The final certificate is issued after satisfactory report about the efforts taken by
the contractor to overcome the defect.
d. The final certificate brings out clearly the state of affairs which becomes a debt
from one pert to other.
e. The final certificate is issued after scrutiny (critical observation or examination)
of all work.
f. The final certificate can be withheld on the grounds that the work is not carried
out satisfactory.
g. The issue of final certificate must be within the limitation of contract.
h. The final certificate is the conclusive certificate and is issued after the expiry of
defect liability period
Page | 12
UNIT-5
Working out quantities for load bearing structure (below plinth only) of
approximately 15-30 Sq.m by offset and centreline method illustrating L and t
junctions and preparing measurement sheet and abstract for all items.
UNIT-6
Working out quantities for R.C.C. G+1 structure of approximately 150-200
sq.m and preparing measurement sheet and abstract for all items of work.
Page | 13