Problemas encontrados :
Ninguna.
Ninguna.
5. Amortizaciones al mes de
* Adelanto Directo
1.1.0 Reintegro
1.1.1 Reajuste reconocido 0.00
2.0.0 DESCUENTOS
2.1.0 Amortización del Adelanto Directo
2.1.1 Amortización del Adelanto Directo 0.00
SUPERVISOR: ING° FLORENCIO EVARISTO RODRIGUEZ AGUIRRE - CIP: 62771 MONTO CONTRATADO: S/. 2,395,727.07
RESIDENTE: ING° VICTOR JOSE URQUIZO SANCHEZ - CIP: 62796 0.00 PLAZO: 120 DIAS CALENDARIOS
INICIO: 12/20/2018 FIN: 4/18/2019
ITEM SUB PRESUPUESTO VALOR REFERENCIAL AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO POR VALORIZAR
01 ESTRUCTURAS S/. 1,765,458.41 S/. 0.00 S/. 27,521.60 S/. 27,521.60 ###
COSTO DIRECTO S/. 1,765,458.41 S/. 0.00 S/. 27,521.60 S/. 27,521.60 ###
GASTOS GENERALES (7.27%) S/. 128,348.83 S/. 0.00 S/. 2,000.82 S/. 2,000.82 S/. 126,348.01
UTILIDADES (7.73%) S/. 136,469.93 S/. 0.00 S/. 2,127.42 S/. 2,127.42 S/. 134,342.52
SUB TOTAL S/. 2,030,277.17 S/. 0.00 S/. 31,649.84 S/. 31,649.84 ###
IGV (18%) S/. 365,449.89 S/. 0.00 S/. 5,696.97 S/. 5,696.97 S/. 359,752.92
PRESUPUESTO REFERENCIAL S/. 2,395,727.06 S/. 0.00 S/. 37,346.81 S/. 37,346.81 ###
FACTOR DE RELACION (0.900000) S/. 2,156,154.37 S/. 0.00 S/. 33,612.15 S/. 33,612.15 ###
SUPERVISOR: ING° FLORENCIO EVARISTO RODRIGUEZ AGUIRRE - CIP: 62771 MONTO CONTRATADO: S/. 2,156,154.37
RESIDENTE: ING° VICTOR JOSE URQUIZO SANCHEZ - CIP: 62796 VALORIZACION DEL 20 DE DICIEMBRE AL 31 DE DICIEMBRE DEL 2018 PLAZO: 120 DIAS CALENDARIOS
INICIO: 12/20/2018 FIN: 4/18/2019
VALOR REFERENCIAL AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO POR VALORIZAR
ITEM DESCRIPCION DE LA PARTIDA
UNID. CANTIDAD UNITARIO MONTO CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO %
´02. INSTALACIONES PROVISIONALES 6,196.62
´02.01. CARTEL DE IDENTIFICACION. und 1.00 1,571.90 1,571.90 0.00 S/. 0.00 0.00% 1.00 S/. 1,571.90 100.00% 1.00 S/. 1,571.90 100.00% 0.00 S/. 0.00 0.00%
´02.02. CAMPAMENTO. m2 40.00 90.26 3,610.40 0.00 S/. 0.00 0.00% 40.00 S/. 3,610.40 100.00% 40.00 S/. 3,610.40 100.00% 0.00 S/. 0.00 0.00%
´02.03. SEÑALIZACION Y SEGURIDAD VIAL. und 1.00 1,014.32 1,014.32 0.00 S/. 0.00 0.00% 0.25 S/. 253.58 25.00% 0.25 S/. 253.58 25.00% 0.75 S/. 760.74 75.00%
´03. TRABAJOS PRELIMINARES 40,715.75
´03.01. MOVILIZACION Y DESMOVILIZACION DE EQUIPOS. und 1.00 30,000.00 30,000.00 0.00 S/. 0.00 0.00% 0.40 S/. 12,000.00 40.00% 0.40 S/. 12,000.00 40.00% 0.60 S/. 18,000.00 60.00%
´03.02. FLETE TERRESTRE. ton 15.30 225.00 3,442.50 0.00 S/. 0.00 0.00% 5.36 S/. 1,206.00 35.03% 5.36 S/. 1,206.00 35.03% 9.94 S/. 2,236.50 64.97%
´03.03. TRAZO Y REPLANTEO. m2 625.00 7.23 4,518.75 0.00 S/. 0.00 0.00% 625.00 S/. 4,518.75 100.00% 625.00 S/. 4,518.75 100.00% 0.00 S/. 0.00 0.00%
´03.04. DESMONTAJE DE PUENTE EXISTENTE (VIGAS DE MADERA CON TABLERO DE MADERA). ton 35.00 78.70 2,754.50 0.00 S/. 0.00 0.00% 35.00 S/. 2,754.50 100.00% 35.00 S/. 2,754.50 100.00% 0.00 S/. 0.00 0.00%
´04. SEGURIDAD Y SALUD EN OBRA. 6,425.84
´04.01. EQUIPOS DE PROTECCION INDIVIDUAL. glb 1.00 2,753.52 2,753.52 0.00 S/. 0.00 0.00% 0.25 S/. 688.38 25.00% 0.25 S/. 688.38 25.00% 0.75 S/. 2,065.14 75.00%
´04.02. EQUIPOS DE PROTECCION COLECTIVA. glb 1.00 864.10 864.10 0.00 S/. 0.00 0.00% 0.25 S/. 216.03 25.00% 0.25 S/. 216.03 25.00% 0.75 S/. 648.08 75.00%
´04.03. SEÑALIZACION TEMPORAL DE SEGURIDAD. glb 1.00 1,108.52 1,108.52 0.00 S/. 0.00 0.00% 0.25 S/. 277.13 25.00% 0.25 S/. 277.13 25.00% 0.75 S/. 831.39 75.00%
´04.04. RECURSOS ANTE EMERGENCIA EN SEGURIDAD Y SALUD. glb 1.00 1,699.70 1,699.70 0.00 S/. 0.00 0.00% 0.25 S/. 424.93 25.00% 0.25 S/. 424.93 25.00% 0.75 S/. 1,274.78 75.00%
´05. INSTALACION DE PUENTE MODULAR. 1,053,983.58
´05.01.01. EXCAVACION CON MAQUINARIA. m3 484.87 30.54 14,807.93 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 484.87 S/. 14,807.93 100.00%
´05.01.02. RELLENO Y COMPACTACION CON MATERIAL PROPIO SELECCIONADO. m3 345.24 24.12 8,327.19 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 345.24 S/. 8,327.19 100.00%
´05.01.03. ELIMINACION DE MATERIAL EXCEDENTE DM=1km. m3 167.56 58.59 9,817.34 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 167.56 S/. 9,817.34 100.00%
´05.02. CONCRETO SIMPLE. 8,604.40
´05.02.01. SOLADO DE CONCRETO E=2" 1:12 C:H. m2 188.90 45.55 8,604.40 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 188.90 S/. 8,604.40 100.00%
´05.03. CONCRETO ARMADO. 213,065.20
´05.03.01. CONCRETO ARMADO f'c=210 kg/cm2. m3 165.69 403.97 66,933.79 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 165.69 S/. 66,933.79 100.00%
´05.03.02. ENCOFRADO Y DESENCOFRADO. m2 484.83 60.05 29,114.04 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 484.83 S/. 29,114.04 100.00%
´05.03.03. ACERO DE REFUERZO fy=4200 kg/cm2. kg 18,341.28 6.38 117,017.37 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 18,341.28 S/. 117,017.37 100.00%
´05.04. SUPERESTRUCTURA (SUMINISTRO, TRANSPORTE Y MONTAJE). 799,361.53
´05.04.01. MONTAJE DE ESTRUCTURA METALICA. ton 40.85 1,021.66 41,734.81 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 40.85 S/. 41,734.81 100.00%
´05.04.02. LANZAMIENTO DE ESTRUCTURA METALICA. ton 40.85 642.93 26,263.69 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 40.85 S/. 26,263.69 100.00%
´05.04.03. DESMONTAJE DE NARIZ DE LANZAMIENTO. ton 27.43 100.00 2,743.00 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 27.43 S/. 2,743.00 100.00%
´05.04.04. TRANSPORTE DE ESTRUCTURA METALICA ACROW. ton 40.85 600.00 24,510.00 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 40.85 S/. 24,510.00 100.00%
´05.04.05. TRANSPORTE DE NARIZ METALICA DE LANZAMIENTO. ton 27.43 200.00 5,486.00 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 27.43 S/. 5,486.00 100.00%
CRONOGRAMA DE CONTROL Y SEGUIMIENTO DE OBRA (VALORIZACION N° 01)
OBRA:
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD EN EL PUENTE JAULABAMBA CASERIO TRES RIOS, DISTRITO DE MES: DICIEMBRE del 2018
CACHICADAN, PROVINCIA DE SANTIAGO DE CHUCO – LA LIBERTAD" VALOR REFERENCIAL: S/. 2,395,727.07
SUPERVISOR: ING° FLORENCIO EVARISTO RODRIGUEZ AGUIRRE - CIP: 62771 MONTO CONTRATADO: S/. 2,156,154.37
RESIDENTE: ING° VICTOR JOSE URQUIZO SANCHEZ - CIP: 62796 VALORIZACION DEL 20 DE DICIEMBRE AL 31 DE DICIEMBRE DEL 2018 PLAZO: 120 DIAS CALENDARIOS
INICIO: 12/20/2018 FIN: 4/18/2019
VALOR REFERENCIAL AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO POR VALORIZAR
ITEM DESCRIPCION DE LA PARTIDA
UNID. CANTIDAD UNITARIO MONTO CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO %
´05.04.06. SUMINISTRO Y COLOC.DE ANGULO. PLATO Y PERNOS DE ACERO. und 1.00 2,624.03 2,624.03 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 1.00 S/. 2,624.03 100.00%
´05.04.07. SUMINISTRO DE PUENTE MODULAR. m 24.00 29,000.00 696,000.00 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 24.00 S/. 696,000.00 100.00%
´06. TRABAJOS COMPLEMENTARIOS. 643,136.60
´06.01.01. CONCRETO EN LOSAS DE APROXIMACION f'c=210 kg/cm2. m3 12.26 403.97 4,952.67 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 12.26 S/. 4,952.67 100.00%
´06.01.02. ENCOFRADO Y DESENCOFRADO EN LOSA DE APROXIMACION. m2 12.20 60.62 739.56 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 12.20 S/. 739.56 100.00%
´06.01.03. ACERO DE REFUERZO fy=4200 kg/cm2. kg 1,868.70 6.38 11,922.31 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 1,868.70 S/. 11,922.31 100.00%
´06.02. MURO CONTRAIMPACTO. 3,121.53
´06.02.01. CONCRETO EN MURO CONTRAIMPACTO f'c=210 kg/cm2. m3 1.44 403.97 581.72 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 1.44 S/. 581.72 100.00%
´06.02.02. ENCOFRADO Y DESENCOFRADO DE MURO CONTRAIMPACTO. m2 12.48 60.05 749.42 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 12.48 S/. 749.42 100.00%
´06.02.03. ACERO DE REFUERZO fy=4200 kg/cm2. kg 216.66 6.38 1,382.29 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 216.66 S/. 1,382.29 100.00%
´06.02.04. PINTURA DE MURO CONTRA IMPACTO. m2 13.08 31.20 408.10 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 13.08 S/. 408.10 100.00%
´06.03. DEFENSA RIBEREÑA. 616,416.15
´06.03.01. CORTE DE MATERIAL SUELTO C/EQUIPO PARA ENCAUSAMIENTO. m3 4,582.30 44.82 205,378.69 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 4,582.30 S/. 205,378.69 100.00%
´06.03.02. SUMINISTRO Y COLOCACION ENROCADO. m3 3,036.40 135.37 411,037.47 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 3,036.40 S/. 411,037.47 100.00%
´06.04. SEÑALIZACION Y SEGURIDAD VIAL. 5,984.38
´06.04.01. SEÑALES INFORMATIVAS. und 2.00 2,012.96 4,025.92 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 2.00 S/. 4,025.92 100.00%
´06.04.02. SEÑALES PREVENTIVAS. und 2.00 979.23 1,958.46 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 2.00 S/. 1,958.46 100.00%
´07. MEDIDAS DE MITIGACION AMBIENTAL. 15,000.00
´07.01. MITIGACION DE IMPACTO AMBIENTAL. glb 1.00 15,000.00 15,000.00 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 0.00 S/. 0.00 0.00% 1.00 S/. 15,000.00 100.00%
COSTO DIRECTO ### S/. 1,765,458.41 S/. 0.00 S/. 27,521.60 S/. 27,521.60 S/. 1,737,936.83
GASTOS GENERALES 7.27% S/. 128,348.83 S/. 0.00 S/. 2,000.82 S/. 2,000.82 S/. 126,348.00
UTILIDADES 7.773% S/. 136,469.94 S/. 0.00 S/. 2,127.43 S/. 2,127.43 S/. 134,342.52
SUBTOTAL S/. 2,030,277.18 S/. 0.00 S/. 31,649.85 S/. 31,649.85 S/. 1,998,627.34
IGV S/. 365,449.89 S/. 0.00 S/. 5,696.97 S/. 5,696.97 S/. 359,752.92
PRESUPUESTO TOTAL S/. 2,395,727.07 S/. 0.00 S/. 37,346.82 S/. 37,346.82 S/. 2,358,380.27
FACTOR DE RELACIÓN 0.90 S/. 2,156,154.37 S/.0.00 S/.33,612.15 S/. 33,612.14 S/. 2,122,542.23
PORCENTAJE DE AVANCE MENSUAL 0.00% 1.56% 1.56% 98.44%
PORCENTAJE DE AVANCE ACUMULADO 0.00% 1.56% 1.56% 100.00%
CONTROL DE PAGOS Y VALORIZACIONES (VALORIZACION N° 01)
PROGRAMADO EJECUTADO %
MES VAL. Nº AVANCE PORCENTAJE AVANCE AVANCE PORCENTAJE
AVANCE MENSUAL EJEC./
ACUMULADO ACUMULADO MENSUAL ACUMULADO ACUMULADO PROG.
OBRA : “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD EN EL PUENTE JAULABAMBA CASERIO TRES RIOS, DISTRITO DE CACHICADAN, PROVINCIA DE SANTIAGO DE CHUCO –
LA LIBERTAD"
PROCESO : A SUMA ALZADA
FINANCIA : MUNICIPALIDAD DISTRITAL DE CACHICADAN
UBICACIÓN : LA LIBERTAD - SANTIAGO DE CHUCO - CACHICADAN - CASERIO TRES RIOS
EJECUTA : CONSORCIO JAULABAMBA
SUPERVISOR : ING° FLORENCIO EVARISTO RODRIGUEZ AGUIRRE - CIP: 62771
RESIDENTE : ING° VICTOR JOSE URQUIZO SANCHEZ - CIP: 62796
MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS
MONTOS (Inc/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
Nov-18 0.00 0.00 0.00% 0.00% Nov-18 0.00 0.00 0.00% 0.00%
Dec-18 39,430.38 39,430.38 1.83% 1.83% Dec-18 33,612.15 33,612.15 1.56% 1.56%
Jan-19 509,921.86 549,352.24 23.65% 25.48% Jan-19
Feb-19 591,288.26 1,140,640.50 27.42% 52.90% Feb-19
Mar-19 Mar-19
(S / .)
2,000,000.00
1692720.16
1,600,000.00 PROGRAMADO
EJECUTADO
1,200,000.00
1140640.5
800,000.00
549352.24
400,000.00
39430.38
33612.149
0.00 0
Nov-18 Dec-18 Jan-19 PLAZO DE EJECUCIÓN (Meses)
Mar-19 Apr-19 May -19
CONTROL DE VALORIZACIONES EJECUTADAS VS. PROGRAMADAS % (VALORIZACION N° 01)
OBRA : “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD EN EL PUENTE JAULABAMBA CASERIO TRES RIOS, DISTRITO DE CACHICADAN, PROVINCIA DE SANTIAGO DE CHUCO –
LA LIBERTAD"
PROCESO : A SUMA ALZADA
FINANCIA : MUNICIPALIDAD DISTRITAL DE CACHICADAN
UBICACIÓN : LA LIBERTAD - SANTIAGO DE CHUCO - CACHICADAN - CASERIO TRES RIOS
EJECUTA : CONSORCIO JAULABAMBA
SUPERVISOR : ING° FLORENCIO EVARISTO RODRIGUEZ AGUIRRE - CIP: 62771
RESIDENTE : ING° VICTOR JOSE URQUIZO SANCHEZ - CIP: 62796
MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS
MONTOS (Inc/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
Dec-18 0.00 0.00 0.00% 0.00% Dec-18 0.00 0.00 0.00% 0.00%
Dec-18 39,430.38 39,430.38 1.83% 1.83% Dec-18 33,612.15 33,612.15 1.56% 1.56%
Jan-19 509,921.86 549,352.24 23.65% 25.48% Jan-19 0.00 33,612.15
Feb-19 591,288.26 1,140,640.50 27.42% 52.90% Feb-19 0.00 33,612.15
Mar-19 552,079.66 1,692,720.16 25.60% 78.51% Mar-19 0.00 33,612.15
Apr-19 463,434.20 2,156,154.36 21.49% 100.00% Apr-19 0.00 33,612.15
(% )
90.00%
80.00% 78.51%
70.00%
PROGRAMADO EJECUTADO
60.00%
52.90%
50.00%
40.00%
30.00%
25.48%
20.00%
10.00%
Fórmula Polinómica
k= 0.085 AAr/AAo + 0.07 CAr/CAo + 0.423 Ir/Io + 0.344 Mr/Mo + 0.078 TMPr/TMPo