Weightage - Progress Summary

Category Buildings Activity Weightage

Overall 100.00%
MOBILISATION & HSE CERTIFICATE 3.00%
ENGINEERING & DESIGN 2.00%
PROCUREMENT 20.00%
CONSTRUCTION 65.00%
BUILDING 50.95%

SUBSTRUCTURE 6.80%
SUPER STRUCTURE 16.55%
FINISHING WORKS (INTERNAL & EXTERNAL) 23.66%
MEP WORKS 3.94%
BLOCK 3.21%

UG WATER TANK 0.67%


SUBSTRUCTURE 0.45%
SUPER STRUCTURE 0.27%
FINISHING WORKS (INTERNAL & EXTERNAL) 1.64%
MEP WORKS 0.18%
SERVICE AREA 1.29%

SUBSTRUCTURE 0.19%
SUPER STRUCTURE 0.09%
FINISHING WORKS (INTERNAL & EXTERNAL) 0.99%
MEP WORKS 0.02%
MOSQUE 5.17%

SUBSTRUCTURE 0.72%
SUPER STRUCTURE 1.80%
FINISHING WORKS (INTERNAL & EXTERNAL) 2.53%
MEP WORKS 0.11%
SWIMMING POOL 1.38%

MAIN POOL 0.75%


PERIPHERAL STRUCTURE 0.54%
FINISHING WORKS (INTERNAL & EXTERNAL) 0.09%
MEP WORKS 0.00%
EXTERNAL WORKS 2.95%

COMPOUND WALL 1.33%


SEPTIC TANK WITH SOAK PIT 0.14%
SEWERAGE PIPELINE WORKS 0.09%
WATER PIPELINE WORKS 0.11%
FOOT BALL FIELD 0.27%
TENNIS YARD 0.25%
KERBSTONE 0.16%
INTERLOCK PAVEMENT 0.09%
ROAD WORKS 0.20%
LANDSCAPING & IRRIGATION 0.14%
OUTDOOR LIGHTING 0.18%
SUBSTANTIAL COMPLETION, PRE-COMMISIONING & COMMISIONING 5.00%