Catcher Hook Up &

Commissioning
23rd October 2017
Executive Summary

• Vessel arrived in Nigg on 8th October and was deployed in the field on 18th
October
• Removal of cone plate and hook-up with the buoy have been completed
• Hook-up of risers ongoing; hook-up of umbilicals plus reinstatement of
equipment and leak testing of pipework will follow
• Commissioning activities are running in parallel
• Introduction of hydrocarbons after flushing of gas export line and final
rotation testing
• Forecast for first oil remains on track for before year end
• Field ramp up will be over 3-4 month period with Catcher being the first field
on line followed by Varadero and Burgman
• Full field plateau production of 60kbopd will be achieved at this time
• Expected to trade in line with Brent
October 2017 | P1
Catcher Hook Up
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks

Harbour On location

Cone Plug Buoy Swivel Reinstate- Pre-Commiss- Commiss-


Risers Umbilical's ESDV’s*
Removal Hook-Up Stack ment ioning ioning

Typical Buoy top

• In place for protection during Permanent hang-off


voyage
• Removed in harbour prior to • Buoy pulled in and locked in • Risers will be pulled up by 2
deployment place metres from temporary hang-off
• Rotation test completed and installed in their permanent
hang-off position

*ESDV: Emergency Shut-Down Valves


October 2017 | P2 Note photographs are from similar operations on other vessels
Catcher Hook Up
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks

Harbour On location

Cone Plug Buoy Swivel Reinstate- Pre-Commiss- Commiss-


Risers Umbilical's ESDV’s*
Removal Hook-Up Stack ment ioning ioning

Riser Size ESDV Weight

Production 10" 3.3T

CATCHER
Gas Export 10" 3T

Water injection 8" 2.2T

Gas lift 6" 0.5T ESDV being lowered


Production 10" 3.3T
BURGMAN
Water injection 8" 2.2T

Gas lift 6" 0.5T


VARADERO

Production 10" 3.3T

Water injection 8" 2.2T

Gas lift 6" 0.5T ESDV installed

• Umbilicals will be pulled up by 5 metres and • ESDV valves will be removed from storage, installed on risers,
permanently hung-off bolts torqued and valves tested
• Seal cans will be installed and packed with resin

October 2017 | P3
Catcher Hook Up
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks

Harbour On location

Cone Plug Buoy Swivel Reinstate- Pre-Commiss- Commiss-


Risers Umbilical's ESDV’s*
Removal Hook-Up Stack ment ioning ioning

ESDVs pipework

Shipside Pipework

Removed structure

• Swivel stack (270t) in sail away location to allow buoy • Geostationary pipework will be reinstated along with
installation power, instrumentation and shipside structures
• Will be skidded to the centre of the turret, aligned • Production lines will be connected to the swivel
with the buoy, mated and bolts tensioned • Hook-up equipment such as buoy bumper bars, hang-
offs and sheave arrangements will be removed

October 2017 | P4
Catcher Commissioning
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks

Harbour On location

Cone Plug Buoy Swivel Reinstate- Pre-Commiss- Commiss-


Risers Umbilical's ESDV’s*
Removal Hook-Up Stack ment ioning ioning

• Where possible equipment was leak tested, commissioned and


Gas export line – commissioned
systems accepted by operations in Singapore prior to sail away prior to start up
• The voyage and movement of the vessel and equipment
requires them to be re-tested ahead of the introduction of
hydrocarbons
• Vessel activities:
– Pipework: Nitrogen/helium testing; and Deluge testing
– Tubing: Leak testing
– Electrical & Instrumentation: Pig tail termination & tests;
and Removed equipment reinstated and tested
• Subsea activities
– Completion of umbilical core flushing
– Gas export riser dewatering
– Tree & manifold valve function testing
• Final activities
– Testing of offloading hose connection
– Final rotation test
• Ready for the introduction of hydrocarbons from Catcher field Teekay shuttle tanker

October 2017 | P5
Catcher Commissioning & Production Profile
Fuel Gas Catcher Oil Stabili- Produced Fuel Primary Varadero Permeat. Flash Gas Burgman Water
Gas Export First Oil sation Water Gas Gas First Oil Comp Gas Lift First Oil Injection
Import Comm. Handling Comp

70,000

60,000
Daily Oil Potential (stb/d)

50,000

40,000

30,000

20,000

10,000

0
Catcher Varadero Burgman

• Catcher is the initial field on production due to it’s ability to produce oil in a stable fashion for the first stages
of the FPSO plant commissioning
• Each field will be brought on in the following manner
– Well clean up (initial clean up restricted by rig surface equipment)
– Well test through the subsea multi-phase meters
– Restricted rate to manage gas rates through commissioning period
• Following gas train commissioning completion and the introduction of Burgman fluids the plant will be run at
60 kbopd