Commissioning
23rd October 2017
Executive Summary
• Vessel arrived in Nigg on 8th October and was deployed in the field on 18th
October
• Removal of cone plate and hook-up with the buoy have been completed
• Hook-up of risers ongoing; hook-up of umbilicals plus reinstatement of
equipment and leak testing of pipework will follow
• Commissioning activities are running in parallel
• Introduction of hydrocarbons after flushing of gas export line and final
rotation testing
• Forecast for first oil remains on track for before year end
• Field ramp up will be over 3-4 month period with Catcher being the first field
on line followed by Varadero and Burgman
• Full field plateau production of 60kbopd will be achieved at this time
• Expected to trade in line with Brent
October 2017 | P1
Catcher Hook Up
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks
Harbour On location
Harbour On location
CATCHER
Gas Export 10" 3T
• Umbilicals will be pulled up by 5 metres and • ESDV valves will be removed from storage, installed on risers,
permanently hung-off bolts torqued and valves tested
• Seal cans will be installed and packed with resin
October 2017 | P3
Catcher Hook Up
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks
Harbour On location
ESDVs pipework
Shipside Pipework
Removed structure
• Swivel stack (270t) in sail away location to allow buoy • Geostationary pipework will be reinstated along with
installation power, instrumentation and shipside structures
• Will be skidded to the centre of the turret, aligned • Production lines will be connected to the swivel
with the buoy, mated and bolts tensioned • Hook-up equipment such as buoy bumper bars, hang-
offs and sheave arrangements will be removed
October 2017 | P4
Catcher Commissioning
Arrival in the UK and Hook-Up Commissioning
4-6 Weeks 3-4 Weeks
Harbour On location
October 2017 | P5
Catcher Commissioning & Production Profile
Fuel Gas Catcher Oil Stabili- Produced Fuel Primary Varadero Permeat. Flash Gas Burgman Water
Gas Export First Oil sation Water Gas Gas First Oil Comp Gas Lift First Oil Injection
Import Comm. Handling Comp
70,000
60,000
Daily Oil Potential (stb/d)
50,000
40,000
30,000
20,000
10,000
0
Catcher Varadero Burgman
• Catcher is the initial field on production due to it’s ability to produce oil in a stable fashion for the first stages
of the FPSO plant commissioning
• Each field will be brought on in the following manner
– Well clean up (initial clean up restricted by rig surface equipment)
– Well test through the subsea multi-phase meters
– Restricted rate to manage gas rates through commissioning period
• Following gas train commissioning completion and the introduction of Burgman fluids the plant will be run at
60 kbopd
October 2017 | P6