Sei sulla pagina 1di 37

Highway Safety Audit on

Construction Zones of National


Highways - Traffic Safety
A Case Study

K. Ramachandra Rao
Department of Civil Engineering/TRIPP
IIT Delhi

27th International Course on


Transportation Planning and Safety, 30th Nov – 07th Dec 2017
Outline
}  Construction zone safety
}  Case study – LMNHP corridor
}  Audit process
}  Important observations
}  Compliances: documentation and field
}  Stakeholder survey
}  Way forward
Major Audit Heads
}  Structural Safety (SS)
}  Traffic Management and Safety (TS)
}  Mechanical/Electrical Machinery/ Fire Safety (ME)
}  Construction Safety (CS)
}  Worker/Work Zone Safety (WO)

For each of the above major heads, the documentation


and field audits were performed for all the
12 packages/contracts during the months of June-Aug 2009
(Package/contract 9 was abandoned)
Lucknow-Muzaffarpur National
Highway Project (LMNHP) – Location
(Length: 483 km)
Audit Statistics

Total no. of work packages/contracts: 12

Road length: 483 km

No. of audit locations: 53


Work zone
Package/ Locations Package/ Locations Package/ Locations
Contract Contract Contract
34+970  (Road)   142+800  (Road)   306.380
1 (8) 30+900   4 (3) 1 4 6 + 4 5 0   7 (6) 303.900
(underpass)   (underpass)   299.500
28+000   157+210  (Road)   295.980
20+000  (Road)   290.940
16+400  (Road)   290.000
11+260  (Road)  
10+573  (Road)  
9+850  (Flyover  
76+600   164+000  (Road)   326+000
2 (10) 73+045   5 (7) 171+720  (Road)   8 (3) 331+200
71+300   175+000  (Road)   337+000
63+080   190+340  (Road)  
58+000   191+800  (Road)  
82+800   196+764  (Flyover)  
57+650   203+764  (Flyover)  
57+000  
50+000  
48+000  
92+135   225+000   411+980  
3 (11) 102+000   6 (4) 236+540   10 (4) 402+000  
105+500   237+000   417+120  
108+680   242+000   426+000  
110+500  
118+100  
120+500  
122+900  
126+300  
130+400  
132+780  
Package/ Locations Package/ Locations Package/ Locations
Contract Contract Contract
444+000  
11 (5) 449+100  
442+236  
462+800  
473+000  

444+000  
12 (5) 449+100  
442+236  
462+800  
473+000  
Traffic Safety findings
}  Documentation compliance in most of the packages is good
However, the field compliance needs lot more be done
}  Traffic diversions and related documentation is prepared
generally in compliance with IRC: SP-55: 2001 (now
SP-55:2014) and IRC:67-2001 (now IRC:67-2012)
}  However, ground implementation needs much more to be
done than compliance with these guidelines, i.e., they need to
be revised
}  Traffic control is only passive with no enforcement
Some field views

a) Barricades not there fully at the minor b) non standard signages


bridge approaches

a) Poor barricading of work space, no b) Confusing signage at the crossing road; traffic
markings signal signage although there is none
Accidents and record keeping
}  Accident data record is kept as required by the
NHAI, however, it is not used to improve or modify
safety and traffic management on the field
}  Present accident records are not being used for
analysis of risk factors. The details collected, in any
case, do not provide information that would be of
help in analysis.
}  The procedure for data collection and format for the
same needs to be revised.
}  This can lead to some actionable points based on the
accident trends
Traffic management plans
}  Very often work starts before the final approval of traffic
diversion plans
}  The field staff understanding is that "work cannot be kept
pending for minor changes and finalisation of the traffic
plans"
}  Bridge/flyover construction safety, particularly when there
is a road crossing needs special attention – these are
potential traffic hazard zones
How is the good compliance going to
help in improving the road safety?
}  Almost nothing, yes, this is true!!
}  The best packages which are following traffic
diversions plans, and the worst packages where site
specific plans are not prepared there is a very small
difference in accident rates (according to the records
maintained by the site office of the respective
package)!
}  This also means that there needs to be an active
traffic control, where the speeds can be reduced
Good and bad practices
}  Good practices:
}  Overall Good compliance in documentation and
}  Flag men presence at diversions
}  Presence of most signages
}  Clear walkway secured with Safety nets all along towards
market side
}  Use of plastic bags filled with sand to demarcate edges has
improved visibility of edges
}  Temporary brick wall is used for signage.
}  Bad practices:
}  Poor barricading
}  No visible lighting at construction zones during nights
}  Non-standard signages
}  Drop in levels between existing and new carraigeways
Findings: Compliances (Documentation and Field)
Compliance: Documentation

CONTRACTUAL COMPLIANCE QUALITY OF COMPLIANCE


Percent Percent
Package/ 1,Yes 0, No Good Average
Contract
1 50 50 50 0
2 78 22 67 11
3 67 33 67 0
4 89 11 78 11
5 58 42 50 8

6 82 18 36 0

7 82 18 36 0
8 70 30 70 0

10 91 9 45 45
11 80 20 80 0

12 83 17 83 0
Compliance: Field
Package/ RANGE OF RANGE OF
Contract CONTRACTUAL QUALITY OF
COMPLIANCE COMPLIANCE
1 11-100 11-100

2 36-55 22-36

3 27-64 27-64

4 22-36 10-23

5 36-55 22-36

6 17-36 17-26

7 18-33 18-33

8 9-25 9-25

10 17-50 17-50

11 20-50 20-36

12 20-55 8-33
Recommendations
Package Component Observation Recommendation

1,5,6,11 TMP Site specific TMPs are Site specific TMPs should be
not prepared prepared for sections passing
through SHs
3,4,8,10,12 TMP Site specific TMPs are prepared They shall also include lighting
arrangement to improve night
time visibility.
TMP should show signage
indicating type of work in
progress, distance from the
work sites, speed limits, and
end of construction.
The TMP shall show the
facilities to be provided for
pedestrians especially at
Underpasses and Major bridge
locations. The pedestrian
paths and crossings need to
be provided near townships
and villages on either side of
the carriageway

2,3,4,5,6,7,8 Speed No Speed control devices Speed reducing measures as


10,11 are used in the work suggested shall be provided.
zones Refer details in Annexure 11
for rumble strip
Recommendations
Package Component Observation Recommendation

All Packages Barricades Barricades were not Proper barricading has to be in


satisfactory place as per IRC: SP 55, (clause
3.4). Indicate specific locations
where drums and cones are to
be
used. There is a need to
standardize the barricade
design
which is rugged and not theft
prone.

All Packages Checklist CSCs should include the


checklists
provided in Annexure for RFI
approvals

2,3,5,7,8,10,11,12 Signages Some of the signs are All signages must comply with
non standard. Sign the
indicating two way specifications in the codes IRC:
traffic movement is SP
missing 55 and IRC: 67
3,4 Flagmen Present at most of the site Should be continued
Changes in the contract documents, code
(MORTH Specifications)
Existing Clause (Introduction) Proposed Amendment from the angle of safety in
construction zone

The quality of materials, processing of The quality of materials, processing of


materials as may be needed at the site, materials as may be needed at the site or
salient features of the construction work elsewhere, salient features of the
and quality of finished work shall comply construction work and quality of finished
with the requirements set forth in work, measures for safety of workers
succeeding sections. Where the drawings and public and traffic arrangements
and Specifications describe a portion of during execution shall comply with the
the work in only general terms, and not in requirements set forth in succeeding
complete detail, it shall be understood sections. Where the drawings and
that only the best general practice is to Specifications describe a portion of the
prevail, materials and workmanship of the work in only general terms, and not in
best quality are to be employed and the complete detail, it shall be understood
instructions of the Engineer are to be fully that only the sound engineering practice is
complied with. to prevail, materials and
Rumble Strip Design
Road accident form
Questionnaire to Stakeholders
}  Rating Scale: 1– Most Unimportant, 2– Unimportant, 3– Not Applicable/Indifferent,
4– Important, 5– Most Important
Item Importance
a)  Field Related Less More

1 2 3 4 5
Signages
Marking:
1.  Placement of sandbags to demarcate carriageway edge
1.  Compulsory road marking during construction phase
Flags and Flagmen
Special Lighting

Barricades:
1.  Pole with reflectors
1.  Barricades with corrugated sheets
1.  Steel Barricades
Minimum lane width in work zone area (3.5 m)
Item Importance

a)  Field Related Less


More

1 2 3 4 5

Retro-reflective light for night time visibility


Work zone safety training to work zone participants
Work zone speed enforcement by Policing
Work zone safety education of workers
Periodic work zone safety inspection
Rumble strip/Speed Breaker before and after work zone area

Collection of traffic accident data in work zone area


a)  Document/Contract Related
Traffic Management Plans (TMPs)are necessary
Site specific TMPs
TMP submissions made in time
TMP drawings show arrangements during day and night
TMPs reflect safety provisions for pedestrians and local residents

Advance approval of TMPs


Alignments, Longitudinal Sections including temporary cross
drainage works
Special Provision for compulsory expenditure in safety measures
Overall rank for field criteria according to
stakeholders -NHAI (3), CSC (11), Contractors (11)
5  

4.5  

4  

3.5  

3  

2.5  
4.48  
4.31   4.21  
2  
4.43   4.00  
3.72   4.58  
1.5   4.08   4.20   4.33   4.28  
4.00  
1   3.61   3.08  
3.96  
2.83  
0.5  

0  
1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16  

Series1  
Overall rank for documents criteria according
to stakeholders
4.6  

4.5  

4.4  

4.3  

4.2  

4.1  

4  

3.9  
4.54  
4.50  
4.23  
3.8   4.17   4.17   4.33  
4.17  
4.00  
3.7  
1   2   3   4   5   6   7   8  

Series1  
Perception variations: Stakeholders
Item Variation
Flag and flagmen

Retro-reflective lighting for night visibility


Way forward
}  Contract document specifications
}  Strengthening the safety practices
}  Continuous safety monitoring and incentives
}  Developing/Improving codes of practice
Thank You

Potrebbero piacerti anche