SEPTEMBER 2019

BELMONT HOTEL
-Belmont Hotel (Opening Sept. 23, 2019)
-MEPF
- On-going Testing & Commissioning – Cluster 1
- PR (Sewage Ejector Pump for C3) for replacement and rectification (PR 305496) – with proposal
(June)
- Additional Holding Tank (PR 305475) – For presentation tomorrow
- Testing & Commissioning – Chiller, PAHU, AHU & FCU – assistance from Contract for pursuance
of warranty claim (Advance copy of PO send tomorrow, for PR)
- RFI-BHB-LS-014 (for confirmation on budget)
- For CO (PMI-2-LS-041-513) c/o site
- PR 305519 – target to present October 1, 2019 (replacement access trellis polycarbonate)
- PO 311207 – Delivery date 1st week of November
- PO 311351 – 2nd week of October (Replacement pool guidelines)
- Courtyards turnover by October
- Color for unit signage, papalitan (bright colors)
- Tint for Skylight (PR 305521) – September 25, advance PO
- Delivery Evacuation Plans (2nd week of October)
- Zabana Pool Bar and Pipe Cladding, for recon. Target approved by next week.
- Final location of signages – September 26, 2019
- C1 guestrooms target completion October 30, 2019
- C1 guestrooms – on-going minor painting works c/o RVN, MEPF Works at 2F
- Proper safekeeping of OFM c/o RVN
- Issues and Concern: replacement of 79 pcs ball type holder for C3.
- Leak coming from ACP – Site used elastosea (temporary)
- Delivery of Main Door (PO 306291)
- Busted Pin Light – delivery today
- Metalcrest to replace defective / damaged evaporator
- PR 305485 – October (Contractor’s Proposal) – To monitor the dripping of water from slab
- PO of Sump Pit
- Proc (concerns) : follow-up on billings (specifically signages)
- Grate bar TOR and DAR (Follow up IEF)
- TOR: follow up for all PO’s
- Genset Concern: alternator (moisture)

OR2
Construction agreement of approved BOQ of Datem: August 7
MEPFS Contractor : Kick-off meeting on Tuesday
Utility Building Plans conflict : on-going structural
Final Direction regarding failed tensile 16mm and 20mm – PDD to email
Failed coring test result – PDD to email
Architectural Concern : Contracts to check, site to email , list of works awarded to DATEM

EWB
Pending works: Signages (supplier will submit tom for sample, for approval of designer) , replacement of
busted light (delivered 2 pcs)
Telephone Data & Speaker at Retail Area : PhilTesla missed out 1 item (commitment date – Today)
Proc Concern: backload of busted light (hinihingi ni Supplier)

LAND DEV
BPRM
305250 – Sealer (Pending to be delivered on Site on Sept. 25, 2019)
305210 – waiting for approved shopdrawing
BN
Plans of Wharf and Welcome Center (2nd week of October)
Location of CMRF – DENR requires, LGU denied, to set meeting with DENR and LGU
304116 (VFI – SWTGR-D) End of September
BND
CO Form for EE 005/005 and 006/006
BAP
LVSG – End week of October
CHANCELLOR
-Target completion: Feb 2021
-Tapping of Cluster 1 – October (As per JLR, dapat 2 months lang interval)
Cluster 2 – Feb 2020 is too long as per JLR
-PR 303974 – (delivery date)
- Mock up (Nov 15 is the target completion, start of ID Contractor)
-Shopdrawing – On going, contracts to submit to site immediately when done
- Target: Month of October
-Follow up PO of PR 304651
-Final dimension of glass around atrium: follow up final plan c/o PDD – proceed with 1.2m, plans to give
when done.
-October 11, 2019 – design requirement for the FCU
-Tagging (to PDD nung Sept 13)
-Follow up 2nd FCD Plans (Fitness: October 4, 2019 & Spa: Ongoing Revision)
-Approved shopdrawing on concrete pad dimensions (Target: October)
-BMS System Awarding – to present October 29
-ASEC to provide self closing louvers proposal (motorized or fusable) c/o PDD. Adk assistance from RCD
regarding BFP requirement – ASEc to RFA and PDD to check if it is necessary
-Softscape and Hardscape of trench drain (October 1)
-Costing of NEMA, QS waiting for other supplier’s proposal for comparison- QS will rush para umabot sa
mock-up
-Contract of MUR (revised) for submission of revised proposal; target of structural by Monday
-Lifting eyes specifications (to retain to 28mm diameter)
-Hot water system shopdrawing – PDD to provide
-BMS to present October 24, 2019
-CB5 to release on October 11
-Fireman’s lift- not provided
-Kitchen Equipment – Monday for approval of operator
-100 steps – under BPRM and follow up PR
-Heated pools – Site to PR
-Swimming pool – Design and build b FKCLC
- EE/AUX PRR for all equipments e.g.: Transformer, UVSG, etc
-AUX – October 20
-PR305811 wala pa kay contracts
-RFA-AR-093 wala pa kay PDD
-Metal doors- procurement follow up to site the final quantity of hardwares AAP
-PRR305804
-PR Fire exit door – site to PR
-ASEC billing 11 – as per JLR, site to submit immediately bec. ASEC has been calling her
-RMC Batching Plant contact details – to give to Maam Henie because of the new supplier of RMC
-PWD Strobe light – to proceed