ID Task Mode Task Name Duration Start Finish 15 Nov '09

1 Engineering Knowledge, Problem Analysis and Design of Solutions 4 wks Mon 08-07-19 Fri 02-08-19
2 Mathematical Modelling of HRV 1 wk Mon 08-07-19 Fri 12-07-19
3 Clear and Innovative objectives along with their requirements 1 wk Fri 12-07-19 Fri 19-07-19
4 Detail discussion on milestone and project deliverables 1 wk Fri 12-07-19 Fri 19-07-19
5 Consideration of OHS and engineering standard of practice during implementation 1 wk Fri 19-07-19 Fri 26-07-19

6 Present an accurate budget 1 wk Fri 19-07-19 Fri 26-07-19


7 Completed and remaining tasks are logically presented 1 wk Fri 26-07-19 Fri 02-08-19
8 Detail plan to do the remaining task 1 wk Fri 26-07-19 Fri 02-08-19
9 Delierable: Progress Report on Initial Detail System Design 0 days Fri 02-08-19 Fri 02-08-19
10 Investigation and Usage of Modern Tools 4 wks Mon 05-08-19 Fri 30-08-19
11 Codding and Debugging 4 wks Mon 05-08-19 Fri 30-08-19
12 Python Programming of Raspberry Pi 4 wks Fri 02-08-19 Fri 30-08-19
13 Development of Heart Monitoring App using Android Studio 4 wks Mon 05-08-19 Fri 30-08-19
14 ECG Acquisition and Analysis (Data Analysis) 3 wks Mon 12-08-19 Fri 30-08-19
15 ECG Signal Acquisition, Preprocessing and Creation of Database for Analysis 1 wk Mon 12-08-19 Fri 16-08-19

16 Feature Extraction of HRV 1 wk Fri 16-08-19 Fri 23-08-19


17 Classification of HRV using SVM classifier 1 wk Mon 26-08-19 Fri 30-08-19
18 Deliverable: Progress Report on Detail System Design and Analysis 0 days Fri 30-08-19 Fri 30-08-19
19 Data Transmission and Cloud-Based System 3 wks Mon 02-09-19 Fri 20-09-19
20 Data Transmission of precessed ECG signal to cloud server 1 wk Mon 02-09-19 Fri 06-09-19
21 Cloud server used for storage, management and monitoring of ECG signals 1 wk Mon 09-09-19 Fri 13-09-19

22 Linking of Cloud server with Heart Monitoring App 1 wk Mon 16-09-19 Fri 20-09-19
23 Deliverable: Engineering Design Report (Complete Thesis) 0 days Fri 27-09-19 Fri 27-09-19
24 Design Analysis 4 wks Mon 23-09-19 Fri 18-10-19
25 Project Modelling and Prototyping 1 wk Mon 23-09-19 Fri 27-09-19
26 Testing and Verification 1 wk Mon 30-09-19 Fri 04-10-19
27 Remodification based on Supervisor's feedback 1 wk Mon 07-10-19 Fri 11-10-19
28 Final prototype for demonstration 1 wk Mon 14-10-19 Fri 18-10-19
29 Deliverable: Final Project Presentation 0 days Mon 11-11-19 Mon 11-11-19