CONSTRUCTION TASK
FORCE MEETING
9/9/2019
The House (residential)
TATA
Innovation Center
Bloomberg
Center
Excavation / Foundation Nov 2018 – April 2018 March 2018 – Oct 2018
Building Façade March 2019 – Fall 2019 May 2019- Fall 2019
Interior framing & finishes on going on going
VEEC
Hotel
(Lobby area)
Meeting Room
Classroom
Breakout Spaces
(Photo taken May 2019) (Photo taken Sept. 2019)