CRONOGRAMA VALORIZADO DE OBRA

Obra : REPARACION DE BOCATOMA; EN EL (LA) BLOQUE DE RIEGO EL GOLPE DE LA COMISIÓN DE REGANTES VALLE BAJO DEL DISTRITO DE SAMA, PROVINCIA TACNA, DEPARTAMENTO TACNA
Plazo : 60 D.C.

OCTUBRE NOVIEMBRE DICIEMBRE


ITEM DESCRIPCION UND METRADO PARCIAL TOTAL SEMANA-1 SEMANA-2 SEMANA-3 SEMANA-4 SEMANA-5 SEMANA-6 SEMANA-7 SEMANA-8 SEMANA-9 Total
20-Oct-19 27-Oct-19 3-Nov-19 10-Nov-19 17-Nov-19 24-Nov-19 1-Dec-19 8-Dec-19 15-Dec-19
01 SP-01 OBRAS PROVISIONALES, SEGURIDAD Y SALUD
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE OBRA 8.50 x 3.60 m und 1.00 1,671.77 1,671.77 S/. 1,671.77 S/. 1,671.77
01.02 CASETA DE ALMACEN, GUARDIANIA Y RESIDENCIA m2 20.00 97.79 1,955.80 S/. 1,955.80 S/. 1,955.80
01.03 SERVICIOS HIGIENICOS PARA EL PERSONAL DE OBRA glb 1.00 1,500.00 1,500.00 S/. 750.00 S/. 750.00 S/. 1,500.00
01.04 CERCO PROVISIONAL DE PROTECCION DE MALLA ARPILLERA H=2.5M m 80.00 36.72 2,937.60 S/. 2,937.60 S/. 2,937.60

02 SEGURIDAD Y SALUD
02.01 ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 3,000.00 3,000.00 S/. 3,000.00 S/. 3,000.00
02.02 EQUIPOS DE PROTECCION DE PERSONAL P/OBRA glb 1.00 1,765.00 1,765.00 S/. 1,765.00 S/. 1,765.00
02.03 CAPACITACION EN SEGURIDAD Y SALUD EN OBRA ser 1.00 4,000.00 4,000.00 S/. 177.78 S/. 533.33 S/. 533.33 S/. 533.33 S/. 533.33 S/. 533.33 S/. 533.33 S/. 533.33 S/. 88.89 S/. 3,999.98
02.04 AGUA DE MESA PARA CONSUMO HUMANO glb 4.00 25.00 100.00 S/. 13.95 S/. 13.95 S/. 13.95 S/. 13.95 S/. 13.95 S/. 13.95 S/. 13.95 S/. 2.33 S/. 99.98

03 FLETES
03.01 TRANSPORTE DE MATERIALES DE TACNA - OBRA glb 1.00 2,000.00 2,000.00 S/. 2,000.00 S/. 2,000.00

02 SP-02 INFRAESTRUCTURADE PROTECCION


02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO Y REPLANTEO PRELIMINAR Y DURANTE LA EJECUCION glb 1.00 2,000.00 2,000.00 S/. 347.83 S/. 521.74 S/. 521.74 S/. 521.74 S/. 86.96 S/. 2,000.01
02.01.02 CAMINO DE ACCESO m 165.00 17.89 2,951.85 S/. 2,951.85 S/. 2,951.85
02.01.03 DESVIO TEMPORAL DE RIO est 1.00 1,700.00 1,700.00 S/. 1,700.00 S/. 1,700.00
02.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 3,410.00 3,410.00 S/. 3,410.00 S/. 3,410.00
02.01.05 TRANSPORTE DE PERSONAL OBRERO día 25.00 337.45 8,436.25 S/. 1,177.15 S/. 1,177.15 S/. 1,177.15 S/. 1,177.15 S/. 1,177.15 S/. 1,177.15 S/. 1,177.15 S/. 196.19 S/. 8,436.24
02.01.06 ELIMINACION DE AGUA FILTRANTE EN ZONA DE CORTE est 1.00 1,200.00 1,200.00 S/. 400.00 S/. 400.00 S/. 400.00 S/. 1,200.00

02.02 MOVIMIENTO DE TIERRAS


02.02.01 LIMPIEZA DE CAUCE m2 69.00 12.00 828.00 S/. 828.00 S/. 828.00
02.02.02 DEMOLICION DE ESTRUCTURAS m2 28.75 100.00 2,875.00 S/. 2,875.00 S/. 2,875.00
02.02.03 EXCAVACION PARA ESTRUCTURAS m3 58.36 17.08 996.79 S/. 996.79 S/. 996.79
02.02.04 PERFILADO Y COMPACTADO CON EQUIPO m2 69.00 10.94 754.86 S/. 754.86 S/. 754.86
02.02.05 ELIMINACION DE MATERIAL DE EXCEDENTE C/MAQUINARIA m3 87.11 29.70 2,587.17 S/. 2,587.17 S/. 2,587.17

02.03 ENROCADO DE SUB BASE


02.03.01 SELECCION Y ACOPIO DE ROCA m3 124.20 30.73 3,816.67 S/. 3,816.67 S/. 3,816.67
02.03.02 PREPARACION Y CARGIO DE ROCA m3 140.76 20.19 2,841.94 S/. 2,841.94 S/. 2,841.94
02.03.03 TRANSPORTE DE ROCAS (D=30 KM) m3 124.20 30.20 3,750.84 S/. 3,750.84 S/. 3,750.84
02.03.04 ACOMODO DE ROCA m3 124.20 31.32 3,889.94 S/. 3,889.94 S/. 3,889.94

02.04 CONCRETO SIMPLE


02.04.01 SOLADO E=3" m2 69.00 24.42 1,684.98 S/. 1,684.98 S/. 1,684.98
02.04.02 CONCRETO CALZADURAS MEZCLA 1:10 + 30% P.G. m3 20.70 167.68 3,470.98 S/. 1,735.49 S/. 1,735.49 S/. 3,470.98
02.04.03 CONCRETO F'C: 175 KG/CM2 m3 3.00 382.14 1,146.42 S/. 764.28 S/. 382.14 S/. 1,146.42
02.04.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.00 65.04 650.40 S/. 200.12 S/. 300.18 S/. 150.09 S/. 650.39

02.05 CONCRETO ARMADO


02.05.01 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 kg 809.31 5.74 4,645.44 S/. 3,484.08 S/. 1,161.36 S/. 4,645.44
02.05.02 CONCRETO F'C=210 KG/CM2 m3 17.64 437.06 7,709.74 S/. 7,709.74 S/. 7,709.74
02.05.03 CURADO DE CONCRETO m2 483.00 2.32 1,120.56 S/. 747.04 S/. 373.52 S/. 1,120.56

02.06 VARIOS
01.06.01 LIMPIEZA FINAL DE OBRA glb 1.00 2,000.00 2,000.00 S/. 2,000.00 S/. 2,000.00
S/. 11,320.35 S/. 14,514.71 S/. 14,211.66 S/. 9,238.95 S/. 4,895.55 S/. 8,119.14 S/. 7,094.09 S/. 11,342.57 S/. 2,660.93 S/. 83,397.95
COSTO DIRECTO 83,398.00 25,835.06 36,465.30 21,097.59 83,397.95
GASTOS GENERALES 14,770.00 4,575.46 6,458.10 3,736.44 14,770.00
************** ************************************
******************************************************************************************************************
****************************************************************************************************************
********************
SUB TOTAL 98,168.00 30,410.52 42,923.40 24,834.03 98,167.95
GASTO POR SUPERVISION 5,722.00 1,772.56 2,501.91 1,447.53 5,722.00
GASTO POR LIQUIDACION 3,600.00 3,600.00 3,600.00
GASTO POR EXPEDIENTE TECNICO 5,000.00 5,000.00
TOTAL 112,490.00 37,183.08 45,425.31 29,881.61 112,490.00
% AVANCE MENSUAL 33.05% 40.38% 26.57% 100.00%
% AVANCE ACUMULADO 33.05% 73.43% 100.00%