Sei sulla pagina 1di 25

Part 2

Structural Design and


Construction
Alfred A. Yee
Alfred A. Yee Division,
Leo A. Daly
Honolulu, Hawaii

Chang Nai Kim


Alfred A. Yee Division,
Leo A. Daly
Honolulu, Hawaii

T he challenge faced by our firm, as


structural engineers for One Hun-
dred Washington Square, was clear: to
work out the logistics of balancing the
office tower on its pedestal.
Our solution to this assignment is
based on an exterior wall system acting
as an understated, 19-story precast con-
crete Vierendeel wall truss, spanning
from corner column to corner column,
which provides an economical but visu-
ally interesting means of lifting the bulk
of the building 40 ft (12.2 m) above its
Lyra plaza, The truss opens the ground level
for pedestrian use and provides unim-
peded views of both the main head-
quarters building and the gardens
around the new building (Fig. 6).
During the conceptual planning of the
building system, various structural
schemes were considered in developing
the Vierendeel wall truss. These in-
Fig. 6. View of plaza and gardens. cluded structural steel, cast-in-place

24

th

H ! II?
trar^S l parking

11 ! 1. i. ^__ l 1 J11.111

7 # 7 I entrarrce

ml ^4 cqr' ,^r-

° y—.
aSrtr.. '

truck ramp
y ti::..c4UF

do
rr..v^JiLv.

^iR

0m
- a a

E• i l■I^lI U^^!^^^^
l E

r e
. lg

^C - .. 5
= ems r '# }' a; .;i
p,
IiC

wasrrton ave„^a
PLAZA FLOOR FLAN • 0 S S 2

Fig. 7. Plaza floor plans of office tower with shaded vertical columns and center core wall
elements.

reinforced concrete, and precast con- • Precast concrete sandwich exterior


crete sandwich panels combined with wall panels,
t)ost-tensioned concrete girders. The • Slip-formed in situ concrete center
final solution evolved from a careful re- core.
view of the total design impact upon • Four in situ double corner col-
mechanical, electrical, architectural, umns.
structural and construction systems. • Cast-in-place bottom chord perim-
Considering all the design and eco- eter post-tensioned girders.
nomic factors, the structural system and • Cast-in-place transverse post-ten-
construction methodology included the sioned girders through slip-formed
following major elements: center core walls.
• Precast prestressed double tee • Construction sequences of post-
floor joists and inverted tee floor tensioning girders at different
beams. stages of building erection.

PC! JOURNALlJanuary-February 1984 25


mil

• TOT. Of 1 RGRE9 a
COLUJ. NTEI+IORS Ct
la nOORS (ZSAOfJ EG FT_
PER FLOp11 OFFER SMIWA
PLM" 'A FLeXS&lTv

FOI11 POBI-IEMTU *O PERK


DETER 0051555 (OESNMEU
,-v tot SOTTO T 01010 CF
THE 0105EI51EEL 19U55 FE-
TERIOR W q U •O' SOOYE
cc•]• LEVEL. •GCEMl LOAD
051 sROr PREC•SI ROOR
FR/^~ IMI 5O51A SO 05
0851 WALL E55118 To PE -
ATE 45 EST%EIELT STROyO

Fig. 8. Diagrammatic perspective of tower structure showing major elements of the


structural system.

Fig. 7 shows the street level plan of tance. Any changes which occurred
the central core and double corner col- during the design development re-
umns. A diagrammatic perspective of quired a full understanding of the impli-
the building system is illustrated in Fig. cation upon the total building system.
8. A transverse building section, in- Some design items which affected the
cluding dimensions of floor and tower exterior wall system were: (1) Within
heights, is shown in Fig. 9. the Vierendeel wall truss there were
A retrospective review of the com- many openings for the mechanical sys-
pleted design effort confirms that the tem; (2) The exterior finish of the Vie-
execution ofthe construction documents rendeel truss was the finish of the
required close teamwork among the building; and (3) Within the exterior
consultants electrical, mechanical and finish of the Vierendeel wall panel were
structural engineers. Complete and fre- railing elements for the window wash-
quent coordination of all the disciplines ing equipment.
by the architect was of primary impor- These and other similar items re-

26
a le
TRANSVERSE SECTION • ° J
Fig. 9. Transverse section through building.

quired complete planning to insure ac- design criteria. Additional superim-


curate prefabrication of the wall panels posed loadings were assigned to areas
and timely construction performance on which were designated for mechanical
the total building. equipment, roof areas where potential
The Uniform Building Code was snow and ice accumulation could occur,
adopted with amendments set forth by and for the earth-filled landscaped gar-
the Minneapolis Building Code. Design den and plaza levels. Any exposed area
loadings recommended by the Minne- where ponding could occur due to
apolis Building Code for gravity and lat- heavy rain or drainage system failure
eral loads (such as live, snow and wind were considered for design superim-
loads) were included in the structural posed loadings.

PCI JOURNAL/January-February 1984 27


H.V.AC. DUCT
OPENING

STEEL REefFORCWG

PAST- OUTED
RECESSED
SPLICE SLEEVE

CAST-IN-PLACE
SPANDREL

POST-GRO4JTED
SPUCE SLEEVE

—PRECAST
STRUCTURAL
4 WALL PANEL

RIGID TFERF
INSULATION

PRECAST
CONCRETE
E KTERIDN
WALL PANEL

PRECAST
DOUBLE—TEE
FLOOR JOISTS

STEEL CABLE
TENDONS

• --!POST-TENSIONED
CONCRETE GIRDER
I

0
C

Fig. 10. Structural section through typicaI exterior wall construction showing assembly of
elements in Vierendeel truss.

28
Structural Concept kPa), After the center core walls were
constructed by the slipforming tech-
The basic intent of the engineering nique to their full height, the tower cor-
design was to provide an economical ner columns were constructed to a
structural system which could be height 2 ft (610 mm) below the third
erected readily with construction tech- floor, which was 40 ft (122 m) above the
niques available in the Minneapolis re- street level. The corner columns above
gion and which would be sufficiently the street level were architecturally
versatile to accommodate a fairly wide shaped and tapered with a maximum
range of weather conditions. A precast overall size of 4 x 11 ft (12 x 3.4 m) for
exterior wall system combined with each segment of the double column.
precast double tee floor framing was ex- The reinforcement consisted of 58-#18
plored and confirmed as feasible. Grade 60 reinforcing bars with a W14 x
To further speed construction, the 311 structural steel column placed in
slip-formed center core walls were de- each segment.
signed to precede the precast construc- At an intermediate height between
tion. This permitted the entire erection the plaza street level and the third floor,
of the center core walls before any con- a concrete tie was required to assist in
struction of the precast wall and floor the comer column stability. The struc-
system was started, thus concentrating tural steel column was designed to sup-
labor and equipment for the various port Vierendeel wall truss and perime-
tasks at different time periods. ter girders until the wall truss was
A diagrammatic view of the assembly structurally functional for six stories
of the Vierendeel truss elements, in- (third floor to ninth floor). During this
cluding precast double tees, post-ten- construction sequence, three stages of
sioned girders and precast sandwich post-tensioning were performed on the
wall panels, is shown in Fig. 10, perimeter and transverse girders,
The third floor plan of Fig. 11 shows thereby subjecting the steel column to
the post-tensioned perimeter girders horizontal and rotational displacements
and the transverse cantilever girders. It due to prestress axial shortening. The
further outlines the positions of the cor- corner columns were originally de-
ner columns and the central core, The signed to be constructed with the Vie-
fourth floor plan (Fig. 12) shows the rendeel wall truss keeping not more
upper flanges of the post-tensioned pe- than four stories behind erection of the
rimeter and cantilever girders. Exterior wall panels.
precast wall panels serve as elements of The transverse girders cantilever 19 ft
the Vierendeel truss, which begins at (5.8 m) from the core wing walls to pro-
the fourth floor. Elements of the typical vide a flexible support to the north and
floor framing system (Fig. 13) are pre- south perimeter girders. Reterto Fig. 11
stressed double tees and prestressed in- for the plan location of the transverse
verted tees. cantilever girders, to Fig. 7 for outline of
core wing walls, and to Fig. 9 for the
Construction Methodology elevation view of the cantilever trans-
verse girder located 40 ft (12.2 m) above
The foundations for the corner col- the plaza street level. The core wing
umns and the center core are conven- walls, which are 2 ft thick x 20 ft wide
tional spread footing pads founded on (0.6 x 6.1 m), were cast with the slip-
limestone bedrock approximately 35 ft furmed core -walls. The maximum un-
(10.7 m) below street level. The bedrock supported height of the core coring
stratum was dense and substantial, ca- walls is 40 ft (122 m) between the plaza
pable of supporting 70,000 psf (3346 street level and the third floor. Core

PCI JOURNALJJanuary-February 1984 29


222'-I I"
0

DBL-TEES

POST-TENSIONED
GIRDER- -

DOUBLE
PRECAST
BEAMS
NED

^1.,,,JNED
GIRDER
Fig. 11. Structural plan for third floor.
C) CORNER COLUMNS EXTERIOR PRECAST
0 ALL PAN ELS
C
m
z
n
I^ I^
C-
w
MI
C
,^ f
li 1 1 Ali
II

T 4u
DOUBLE TEES POST-TENSIONED
i I DOUBLE GIRDER------
TEES
li! u!
co
T _J'
-Tr ^ _----_—
ii II

DOUBLE i ----
TEES
r,

DOUE
PRE AST
j BEAMS ^l l r_i r
I ^

Fjl II ^I
^I I j POST-TENSIONED_± DOUBLE TEES
I II I I TRANSVERSE
I it GIRDERS
^I^E, `I III

k -- ---_^^ _------------ _^i tL

POST-TENSIONED GIRDER
Fig. 12. Fourth floor plan.
W
N
COLUMNS EXTERIOR PRECAST
PANELS
1
•I

.1

.Ir ^
- -----z

i d q^
r, d^ a
Ili

i DOUBLE-
PRECAST
BEAMS

1; h
j^ it 1

i4
Fig. 13. Typical floor plan, 7th through 12th floors.
t OF TRANSVERSE ? POUR GIRDERS
GIRDERS a -^ —3rda41hFLRS
4th F10OR
3 rd FLOOR _ - -W k4 Cot_.

BASEMENT .-
SUB-BASEME'

Fig. 14, Construction of north and south girders, Sequence 1.

CONCRETE STRENGTH
L OF TRANSVERSE AT TIME OF STRESSING SHALL
GIRDERS - -_ BE 6000 PSI OR GREATER
4th FLOOR PERIMETER GIRDER
'^'^_ _ELQQI3_ ^;^ _
-^= _ _ __ POST TENSIONING
STAGEI

J I
W !4 COL.-- -P ES RE S TRANSVERSE
GIRDERS STAGEfII I ADJUST SHORES AFTER
POST TENSIDNING FOR
r SHORING { ^
SNUG FIT
Is t FLOOR
BASEMENT__
SUB =BASEMENT .

Fig. 15. Construction of north and south girders, Sequence 2.

POUR 5 th, 6th & C OF TRANSVERSE


7 th FLOORS
GIRDERS
7^h FLOOR —__
—^
_ J Z
6th FLO OR
— - -- - oo a
`i^h. FL048 -
—— —
__ a-
4 tti FLOOR 0o^w^
I- z d.
3 rd FLOOR__ .__ t _ —_.1^ _ _ aa^vr
ST i GE ^^ TES R SS RA SUERS£ ADJUST SHORES T
i GIRDERS STAIGE 2 I BE LOOSE FIT SHORES
MAY BE REMOVED
SHORING I I I ^
AFTER 7 th FLR. CONC.
Iat.FLOOR — STRUCTURE HAS CURED
TO THE REQUIRED 28
BASEMENT — DAY STRENGTH.
SUB-BASEMENT

Fig. 16. Construction of north and south girders, Sequence 3.

wing wall vertical reinforcement con- structural steel members provided im-
sisted of #18 reinforcing bars at 6-in. proved stiffness at the free ends of the
(152.4 mm) spacing on each face. wing wall to cope with the large reac-
In addition, two W14 x311 structural tions generated by the cantilevered
steel columns were added on the east transverse girders.
wing walls and two W14 x370 structural Integral with the construction of the
steel columns on the west walls. These perimeter post-tensioned girders was

PC! JOURNAUJanuary- February 1984 33


{F --t OF TRANSVERSE
91h FLOOR I GIRDERS
tth FLOOR ----
7 th FLOU R
6th FLOOR
5th FLOOF _
4tfi F^00
3 rd FLOOF

--PRESTR $5 RA SVERSE -SHORES MAY BE REMOVED


GIRDERS STAGE3 AFTER 7 t h FLR. CONCRETE
STRUCTURE HAS CURED TO
SHORING THE REQUIRED 28 DAY
I 51 FLOQR
STRENGTH
BASEMEN
SUB -BASI =MENT

Fig. 17. Construction of north and south girders, Sequence 4.

POUR GIRDERS
3rd 8, 4th FLRS.
41h
I-- ELOOR
rd FLOOR ____
W 14 COL.

iTh
^ 1 I I I^
--SHORING
LS1 FLOOR
BASEMENT
SUB-BASEMENT EEitEIEt;b 7E)
Fig. 18. Construction of east and west girders, Sequence 1.

the requirement for shoring the post- After completing the third stage
tensioned girders, precast wall panels post-tensioning of the east and west
and floor system, This shoring was re- cantilever girders (with six stories of
quired from the third floor to the seventh Vierendeel exterior precast wall assem-
floor with superimposed loading ac- bled), it was planned to place the in situ
counting for construction to the ninth comer columns from the third floor to
floor, until the Vierendeel wall was con- the sixth floor so that the corner column
structed and structurally effective. At construction would be progressively
this point in the construction sequence, completed within three floors of the
three post-tensioning stages were to be on-going installation of precast wall
completed and shoring removal would panels and precast floor framing.
therefore be permitted. At this stage, the contractor would also
The construction sequences for the be permitted to remove the perimeter
north and south post-tensioned perim- shoring, thereby activating the partially
eter girders are shown in Figs. 14 through constructed Vierendeel truss to support
17. East and west post-tensioned perim- the external loads. However, during the
eter girders are shown in Figs. 18 actual construction the contractor re-
through 20. East and west post-ten- quested that this restraint he modified to
sioned cantilever girders are shown in permit continued construction of the
Figs. 21 through 24. precast wall panels and floor framing

34
PERIMETER GIRDER CONCRETE STRENGTH AT
POST TENSIONING TIME OF STRESSING SHALL
STAGE I BE 6000 PSI OR GREATER
4th FLOOR
3 r d FLOOR
W14 COL: ADJUST SHORES AFTER
POST TENSIONING FOR
SNUG FIT
I St FLOOR
BASEMENT _
SUB-BASEMENT

Fig. 19. Construction of east and west girders, Sequence 2.

POUR 5th, 6 th B, —PERIMETER GIRDER


7 th FLOORS ti • POST TENSIONING
STAGE 2
7 th FLOOR
6 th FLOOR IIi TL uz
5^ h _FL_OOR _
rTi Wu)(
4th FLOOR
3rd FLOOR_

ADJUST SHORES TO
BE LOOSE FIT SHORES
MAY BE REMOVED
Ist FLOOR __ AFTER 7 th FLR CONC.
STRUCTURE HAS CURED
BASEMENT TO THE REQUIRED 28
S UB - BAS E MENT DAY STRENGTH.

Fig. 20. Construction of east and west girders, Sequence 3.

before corner columns were constructed


to their intended schedule. SE
To accommodate this request, the GIRDER
Vierendeel wall system was reviewed ORING
IstELQc
and the contractor was permitted to pro-
ceed with a new criterion. This revised
111 I SUB-BASEMENT
construction sequence allowed the con-
tractor to proceed with the Vierendeel Fig. 21. Construction of east and west
wall tntss to the 13th floor but necessi- transverse girders. Sequence 1.

4th FLOOR _
^r
I RESTRESS TRANSVERSE
T 11 GIRDER STAGE I
SHORING
^1
Ls1 FLOOR
EASEMENT
SUB-BASEMENT

Fig. 22. Construction of east and west transverse girders, Sequence 2.

PCI JOURNAL/January-February 1984 35


7 th FLOOR
6 th FLO OR
5 th FLOOR
4!! FLOO R
3 rd FLOOR
STRESS TRANSVERSE
DER STAGE 2
SHORING
I st FLOOR
BASEMENT
SUB-BASEMENT

Fig. 23. Construction of east and west transverse girders, Sequence 3.

9th FLOOR
8th FLOOR
7th FLOOR
6th FLOOR
5th FLOOR
4AFLOOR --
3rdFLOOR
TRANSVERSE
SHORING ^E 3

I St FLQOR _
BASEMENT
SUB-_BASEMENT

Fig. 24. Construction of east and west transverse girders, Sequence 4.

tasted the existing perimeter shoring to


remain in place until the corner columns
were installed to the 10th floor. At this
stage of construction, the contractor
55 MORTAR
would be permitted to remove the pe-
rimeter shoring. This revised criterion
was actually followed by the contractor. DEFORMED BAR
Connection of the precast wall panels
to the post-tensioned girders at the
DEFORMED BAR
fourth floor and to upper floor wall pan-
els from the fifth floor to the roof was
achieved by using the NMB Splice SLEEVE
Sleeve Post Grout System (see Fig. 25).
This permitted installation of wall pan-
els on each exterior side before grouting
the connections. Further, the capacity of
these connections allows development
of the ultimate strength of the reintorc- Fig. 25. NMB splice sleeve.

36
1,I J-I r71I
Fig. 27. Explosion detail of precast wall and floor assembly.

ing steel, which was a necessity for the mid-depth of the spandrel and midspan
Vierendeel wall truss. of alternate windows in plan. The pre-
The typical precast Vierendeel truss cast sandwich panel consisted of 12-in.
wall panel was 10 ft wide x 13 ft high (3 x (305 mm) thick structural concrete, 2½
4 m). Details of the wall panel are in. (64 mm) of polystyrene insulation,
shown in Fig. 26. Jointing was located at and 3 in, (76 mm) of precast concrete

38
exterior facing. Details of the concrete
jointing may be seen in Fig. 27. The
maximum vertical reinforcing in the
columns was 8414 bars and the maxi-
mum spandrel beam reinforcing was
6411 bottom bars and 2411 top bars.
During installation of the precast pan-
els as many as 28 reinforcing bars re-
quired proper fitting and connections
for one panel assembly. The NMB
splice sleeve was able to accommodate
this assembly resulting in the efficient
erection of the precast panels. Refer to
Figs. 28 through 32 for installation of
precast wall panels. Actual installation
of panels took place from November
1979 to June 1980, during both very
cold, windy, wintry conditions and mild
spring weather. Grouting of the sleeves
was permitted when ambient tempera-
tures were 40 F (4 C) or higher. During
certain periods of erection, artificial
heating was required to keep the ambi-
ent temperature at the acceptable mini- Fig. 28. Top view of installed precast wall
mum level. panels.

Fig. 29. Precast wall panel being lowered into splice sleeves.

PCi JOURNAUJanuary-February 1984 39


Fig. 30. Precast wall panel with horizontal splice sleeves prior to setting.

I;

Fig. 31. Precast wall panel with horizontal splice sleeves in final setting.

40
Fig. 32. Erection of prestressed double tees on precast wall panels.

Other Construction Details


The arrangement of reinforcing steel,
structural steel, post-tensioning tendons
and anchorages at the corner columns is
illustrated in Figs. 33, 34, and 35. Be-
cause of the numerous and dense steel
requirements, accurate detailing and
placement of the steel was submitted to
a very complete review. Full-scale
drawings were performed to insure
proper location for all the steel ele-
ments. Splices for the reinforcing steel
and the structural steel were carefully
examined for their strength require-
ments and their positioning to avoid in-
terference. Careful detailing minimized
the difficulties and prevented many
potential delays in the construction of
the corner columns and perimeter
post-tensioned girders.
Further significant assistance was Fig. 33. Location of reinforcing steel and
provided by the use of superplasticizers. structural steel in corner columns for plaza
Slump at the time of pouring was in- to third floor levels.

PCI JOURNAL/January-February 1984 41


SPC PANEL
STRESSING ANCHOR
PLATES FOR VSL ES-31
c. VSL TENDONS
POST- TENSIONING
TENDONS

a♦

w14, 311
STL. COL.

FIRST STAGE POUR

,' ,^o

Via'•:''--^:^- .-q. . ,
- -FIRST STAGE POUR
SECOP
STAGI OUTLINE OF 3•-O"
POUR WIDE GIRDER

C~ —T' -€ VSL TENDONS

Fig. 34. Corner column junction with post-tensioned girder at third floor level.
f ?.' `FIRST STAGE POUR

/ // /r,\ OUTLINE OF CORNER


COLUMN BELOW 3R0 FL-

/ / / /
/ *QO

/ y

FIRST STAGE POUR

Fig. 35. Corner column junction with post-tensioned girder below start of precast
Vierendeel wall panels.

creased to 6 in. (152 mm) with this addi- Fig. 40 shows construction of the cor-
tive. The installed concrete exhibited ner columns being performed after the
high quality placement and compressive third and final post-tensioning of perim-
strength. eter girders and transverse girders has
The post-tensioned perimeter girder been completed. Splicing of column
concrete and steel arrangement are reinforcing steel was performed by me-
shown in Fig. 36. The post-tensioned chanical connectors. Due to the density
transverse girder cross section is shown of the reinforcement, the use of smaller
in Fig. 37. Construction of the west and bars and lapping of column vertical
south perimeter girders is shown in Figs. reinforcing was not possible. A further
38 and 39, respectively. Shoring of these refinement of the corner column was
perimeter girders is also shown, These that the finish marble chip cladding was
shorings are kept in place and adjusted used as the form for the in situ column.
to bear snugly to the girders after each Placement of exterior cladding was
post-tensioning stage. The slipformed done prior to the second stage of post-
central core walls are visible in the tensioning. However, two panels were
background of Figs. 38 and 39. delayed in their placement on the north

PCI JOURNAL/January-February 4984 43


N1
C'

Fig. 36. Post-tensioned north and south girder sections.

The typical floor framing consists of


18-in, deep x 7 ft 6 in. wide (457 mm x
2.3 m) double tees. In situ topping was
2 1/2 in. (64 mm) thick minimum. The
typical span for this system was 41 ft
(12.5 m). Interior inverted tee beams
supporting the double tees (see Fig. 13
for floor framing plan) were 2 ft 3 in.
(686 mm) deep. The total composite
depth at the inverted tee beams, in-
cluding in situ slab thickness, was 2 ft 9
in. (838 mm). The inverted tee beams
were designed to span 39 ft (11.9 m) on
the east side and 48 ft (14.6 m) on the
west side. Midspan shoring for the in-
Fig. 37. Post-tensioned transverse girder verted tee beams was required during
section. construction.
Along the south and north side of the
tower building the double tee was sup-
and south girders, as shown in Fig. 41. ported on the precast exterior wall panel
After completion of the third stage (Vierendeel wall truss) at one end and
post-tensioning of the transverse gird- on the prebuilt center core at the other
ers, the two remaining cladding panels end. Bearing connection of these floor
were installed. Views of the exterior members was accomplished by welding
precast wall during the final stages of embedded metal devices. (See Figs. 43
construction are shown in Fig. 42. and 44 for details of double tee support

44
Fig. 38. West perimeter girder prior to first stage of post-tensioning.

Fig. 39. South perimeter girder indicating layout of post-tensioning tendons.

PCI JOURNAL/January- February 1984 45


f A

r S

_rc11!

Fig. 40. Preparation of corner columns Fig. 41. Placement of two cladding panels
after third stage of post-tensioning of was delayed until after post-tensioning of
perimeter girders. perimeter girders.

connections.) Overall structural inte-


gration of precast exterior wall panels,
precast double tee joists, inverted tee
.^i beams and the interior prebuilt outer
core walls was performed by reinforced
composite in situ concrete. These
joineries were located in beam sections
between precast wall panels and in the
topping over precast floor members.

Computer Analysis
An important contribution to the sue-
cessful structural design of the Vieren-
deel wall was the application of com-
puter analysis. A modified in-house ver-
sion of the SAP program was applied in
conjunction with a General Automation
SPC 16/40 minicomputer with accessory
disc drive peripheral equipment.
For the north and south Vierendeel
wall truss, the analysis consisted of3949
Fig. 42. Partial view of Vierendeel truss nodal points and 1591 members. The

46
DOUBLE-TEE

Fig. 43. Precast double tee connection at Vierendeel wall truss.

4-S/8"0 L4x3x3/8
BOLTS DBL-TEE

STIFF PL
L6x6xI/2xO'-7"
PL I/2 x 3 x I -O PL I /2 x 8 x 1'- 0"
10"
AT CORE WALL

[Li_
DOUBLE-TEE CONNECTION DETAIL

f- --
Fig. 44. Precast double tee connection at slipformed center core wall.

east and west Vierendeel wall truss running time for each cycle of the north
analysis consisted of 2011 nodal points and south wall truss was 20 hours and
and 1952 members. A subprogram was for each cycle of the east and west wall
added to SAP to permit story by story was 12 hours. The total design effort to
adjustment of the Vierendeel wall truss realize an efficient structure required
in the same manner that the construc- numerous cycles of computer analysis.
tion sequence was performed. Historical The selection of construction se-
data of internal forces were accumulated quence and post-tensioning stages was
and stored until the total structure was optimized through analysis of the com-
completed. puter's calculations. Maximum dead
One complete cycle of each Vieren- load and total load displacements were
deel wall truss analysis consisted of 22 calculated at 1.0 and 128 in. (25 and 33
runs, which considers in sequence 19 mm), respectively. Actual field mea-
structural configuration levels and three surement of maximum deflections was
post-tensioning stages. Total computer 1.12 in. (28 mm). Computer tabulations

PCI JOURNAL/January-February 1984 47


yielded satisfactory and realistic results place concrete provided a rigid system
and were invaluable to the engineering capable of resisting substantial vertical
design. and lateral superimposed loads. The
During installation of the Vierendeel system further demonstrated the instal-
wall truss, the construction sequence lation efficiency of precast concrete and
was varied according to the availability the high quality of its finish.
ofmaterial, equipment and men. Corner The computer analysis of the Vieren-
column completion lagged behind the deel wall truss clearly depicted the
panel installation. Precast wall con- many redundancies available in the
struction also preceded precast floor structure. Studies were performed to
construction, thereby requiring modifi- provide hinges at various locations of
cation of the post-tensioning stages and high bending. Results showed that load
shoring removal sequence. The com- transfer could he directed to other
puter data were changed for each varia- member of the truss without any drastic
tion and the analysis was rerun on the change in displacements or build-up of
SAP program. These changes were sim- internal forces on the adjusted structural
ple to perform since the basic structure configuration.
was modeled in the design phase. The There was an obvious chronological
structure was then scrutinized to insure accumulation of internal forces in the
that its performance was within the cri- Vierendeel wall truss lower floor mem-
teria of the original design. In this re- bers due to the story-by-story erection of
gard, the computerized engineering wall panels. To provide a wider dis-
played a significant role in determining tribution of forces, the post-tensioning
the flexibility permitted in the con- of the perimeter and transverse girders
struction sequence. was divided into three different con-
struction stages. Further distribution
was accomplished by timing the re-
Concluding Remarks moval of shoring so that the partially
constructed structure would accommo-
Based on the early studies of the office date and integrate with the remaining
tower and an evaluation of the different upper portion of structure yet to be
construction methods and materials built. There appeared to be a sensitive
available to implement the design, the demarcation of architectural proportions
precast concrete system selected was of the wall panel sizing, window open-
the most feasible method. After project ing, corner column dimensions and pe-
completion and observation of the con- rimeter girder depth with the structural
struction and structural performance, it requirements of strength and rigidity.
may be concluded that the precast sys- The final design provided a building
tem did indeed provide an exceptionally system which satisfied both the ar-
sound solution. The combination of pre- chitectural concept and requirements
cast concrete with composite cast-in- for structural integrity.

48

Potrebbero piacerti anche