Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
24
th
H ! II?
trar^S l parking
11 ! 1. i. ^__ l 1 J11.111
7 # 7 I entrarrce
ml ^4 cqr' ,^r-
° y—.
aSrtr.. '
truck ramp
y ti::..c4UF
do
rr..v^JiLv.
^iR
0m
- a a
E• i l■I^lI U^^!^^^^
l E
r e
. lg
^C - .. 5
= ems r '# }' a; .;i
p,
IiC
wasrrton ave„^a
PLAZA FLOOR FLAN • 0 S S 2
Fig. 7. Plaza floor plans of office tower with shaded vertical columns and center core wall
elements.
• TOT. Of 1 RGRE9 a
COLUJ. NTEI+IORS Ct
la nOORS (ZSAOfJ EG FT_
PER FLOp11 OFFER SMIWA
PLM" 'A FLeXS&lTv
Fig. 7 shows the street level plan of tance. Any changes which occurred
the central core and double corner col- during the design development re-
umns. A diagrammatic perspective of quired a full understanding of the impli-
the building system is illustrated in Fig. cation upon the total building system.
8. A transverse building section, in- Some design items which affected the
cluding dimensions of floor and tower exterior wall system were: (1) Within
heights, is shown in Fig. 9. the Vierendeel wall truss there were
A retrospective review of the com- many openings for the mechanical sys-
pleted design effort confirms that the tem; (2) The exterior finish of the Vie-
execution ofthe construction documents rendeel truss was the finish of the
required close teamwork among the building; and (3) Within the exterior
consultants electrical, mechanical and finish of the Vierendeel wall panel were
structural engineers. Complete and fre- railing elements for the window wash-
quent coordination of all the disciplines ing equipment.
by the architect was of primary impor- These and other similar items re-
26
a le
TRANSVERSE SECTION • ° J
Fig. 9. Transverse section through building.
STEEL REefFORCWG
PAST- OUTED
RECESSED
SPLICE SLEEVE
CAST-IN-PLACE
SPANDREL
POST-GRO4JTED
SPUCE SLEEVE
—PRECAST
STRUCTURAL
4 WALL PANEL
RIGID TFERF
INSULATION
PRECAST
CONCRETE
E KTERIDN
WALL PANEL
PRECAST
DOUBLE—TEE
FLOOR JOISTS
STEEL CABLE
TENDONS
• --!POST-TENSIONED
CONCRETE GIRDER
I
0
C
Fig. 10. Structural section through typicaI exterior wall construction showing assembly of
elements in Vierendeel truss.
28
Structural Concept kPa), After the center core walls were
constructed by the slipforming tech-
The basic intent of the engineering nique to their full height, the tower cor-
design was to provide an economical ner columns were constructed to a
structural system which could be height 2 ft (610 mm) below the third
erected readily with construction tech- floor, which was 40 ft (122 m) above the
niques available in the Minneapolis re- street level. The corner columns above
gion and which would be sufficiently the street level were architecturally
versatile to accommodate a fairly wide shaped and tapered with a maximum
range of weather conditions. A precast overall size of 4 x 11 ft (12 x 3.4 m) for
exterior wall system combined with each segment of the double column.
precast double tee floor framing was ex- The reinforcement consisted of 58-#18
plored and confirmed as feasible. Grade 60 reinforcing bars with a W14 x
To further speed construction, the 311 structural steel column placed in
slip-formed center core walls were de- each segment.
signed to precede the precast construc- At an intermediate height between
tion. This permitted the entire erection the plaza street level and the third floor,
of the center core walls before any con- a concrete tie was required to assist in
struction of the precast wall and floor the comer column stability. The struc-
system was started, thus concentrating tural steel column was designed to sup-
labor and equipment for the various port Vierendeel wall truss and perime-
tasks at different time periods. ter girders until the wall truss was
A diagrammatic view of the assembly structurally functional for six stories
of the Vierendeel truss elements, in- (third floor to ninth floor). During this
cluding precast double tees, post-ten- construction sequence, three stages of
sioned girders and precast sandwich post-tensioning were performed on the
wall panels, is shown in Fig. 10, perimeter and transverse girders,
The third floor plan of Fig. 11 shows thereby subjecting the steel column to
the post-tensioned perimeter girders horizontal and rotational displacements
and the transverse cantilever girders. It due to prestress axial shortening. The
further outlines the positions of the cor- corner columns were originally de-
ner columns and the central core, The signed to be constructed with the Vie-
fourth floor plan (Fig. 12) shows the rendeel wall truss keeping not more
upper flanges of the post-tensioned pe- than four stories behind erection of the
rimeter and cantilever girders. Exterior wall panels.
precast wall panels serve as elements of The transverse girders cantilever 19 ft
the Vierendeel truss, which begins at (5.8 m) from the core wing walls to pro-
the fourth floor. Elements of the typical vide a flexible support to the north and
floor framing system (Fig. 13) are pre- south perimeter girders. Reterto Fig. 11
stressed double tees and prestressed in- for the plan location of the transverse
verted tees. cantilever girders, to Fig. 7 for outline of
core wing walls, and to Fig. 9 for the
Construction Methodology elevation view of the cantilever trans-
verse girder located 40 ft (12.2 m) above
The foundations for the corner col- the plaza street level. The core wing
umns and the center core are conven- walls, which are 2 ft thick x 20 ft wide
tional spread footing pads founded on (0.6 x 6.1 m), were cast with the slip-
limestone bedrock approximately 35 ft furmed core -walls. The maximum un-
(10.7 m) below street level. The bedrock supported height of the core coring
stratum was dense and substantial, ca- walls is 40 ft (122 m) between the plaza
pable of supporting 70,000 psf (3346 street level and the third floor. Core
DBL-TEES
POST-TENSIONED
GIRDER- -
DOUBLE
PRECAST
BEAMS
NED
^1.,,,JNED
GIRDER
Fig. 11. Structural plan for third floor.
C) CORNER COLUMNS EXTERIOR PRECAST
0 ALL PAN ELS
C
m
z
n
I^ I^
C-
w
MI
C
,^ f
li 1 1 Ali
II
T 4u
DOUBLE TEES POST-TENSIONED
i I DOUBLE GIRDER------
TEES
li! u!
co
T _J'
-Tr ^ _----_—
ii II
DOUBLE i ----
TEES
r,
DOUE
PRE AST
j BEAMS ^l l r_i r
I ^
Fjl II ^I
^I I j POST-TENSIONED_± DOUBLE TEES
I II I I TRANSVERSE
I it GIRDERS
^I^E, `I III
POST-TENSIONED GIRDER
Fig. 12. Fourth floor plan.
W
N
COLUMNS EXTERIOR PRECAST
PANELS
1
•I
.1
.Ir ^
- -----z
i d q^
r, d^ a
Ili
i DOUBLE-
PRECAST
BEAMS
1; h
j^ it 1
i4
Fig. 13. Typical floor plan, 7th through 12th floors.
t OF TRANSVERSE ? POUR GIRDERS
GIRDERS a -^ —3rda41hFLRS
4th F10OR
3 rd FLOOR _ - -W k4 Cot_.
BASEMENT .-
SUB-BASEME'
CONCRETE STRENGTH
L OF TRANSVERSE AT TIME OF STRESSING SHALL
GIRDERS - -_ BE 6000 PSI OR GREATER
4th FLOOR PERIMETER GIRDER
'^'^_ _ELQQI3_ ^;^ _
-^= _ _ __ POST TENSIONING
STAGEI
J I
W !4 COL.-- -P ES RE S TRANSVERSE
GIRDERS STAGEfII I ADJUST SHORES AFTER
POST TENSIDNING FOR
r SHORING { ^
SNUG FIT
Is t FLOOR
BASEMENT__
SUB =BASEMENT .
wing wall vertical reinforcement con- structural steel members provided im-
sisted of #18 reinforcing bars at 6-in. proved stiffness at the free ends of the
(152.4 mm) spacing on each face. wing wall to cope with the large reac-
In addition, two W14 x311 structural tions generated by the cantilevered
steel columns were added on the east transverse girders.
wing walls and two W14 x370 structural Integral with the construction of the
steel columns on the west walls. These perimeter post-tensioned girders was
POUR GIRDERS
3rd 8, 4th FLRS.
41h
I-- ELOOR
rd FLOOR ____
W 14 COL.
iTh
^ 1 I I I^
--SHORING
LS1 FLOOR
BASEMENT
SUB-BASEMENT EEitEIEt;b 7E)
Fig. 18. Construction of east and west girders, Sequence 1.
the requirement for shoring the post- After completing the third stage
tensioned girders, precast wall panels post-tensioning of the east and west
and floor system, This shoring was re- cantilever girders (with six stories of
quired from the third floor to the seventh Vierendeel exterior precast wall assem-
floor with superimposed loading ac- bled), it was planned to place the in situ
counting for construction to the ninth comer columns from the third floor to
floor, until the Vierendeel wall was con- the sixth floor so that the corner column
structed and structurally effective. At construction would be progressively
this point in the construction sequence, completed within three floors of the
three post-tensioning stages were to be on-going installation of precast wall
completed and shoring removal would panels and precast floor framing.
therefore be permitted. At this stage, the contractor would also
The construction sequences for the be permitted to remove the perimeter
north and south post-tensioned perim- shoring, thereby activating the partially
eter girders are shown in Figs. 14 through constructed Vierendeel truss to support
17. East and west post-tensioned perim- the external loads. However, during the
eter girders are shown in Figs. 18 actual construction the contractor re-
through 20. East and west post-ten- quested that this restraint he modified to
sioned cantilever girders are shown in permit continued construction of the
Figs. 21 through 24. precast wall panels and floor framing
34
PERIMETER GIRDER CONCRETE STRENGTH AT
POST TENSIONING TIME OF STRESSING SHALL
STAGE I BE 6000 PSI OR GREATER
4th FLOOR
3 r d FLOOR
W14 COL: ADJUST SHORES AFTER
POST TENSIONING FOR
SNUG FIT
I St FLOOR
BASEMENT _
SUB-BASEMENT
ADJUST SHORES TO
BE LOOSE FIT SHORES
MAY BE REMOVED
Ist FLOOR __ AFTER 7 th FLR CONC.
STRUCTURE HAS CURED
BASEMENT TO THE REQUIRED 28
S UB - BAS E MENT DAY STRENGTH.
4th FLOOR _
^r
I RESTRESS TRANSVERSE
T 11 GIRDER STAGE I
SHORING
^1
Ls1 FLOOR
EASEMENT
SUB-BASEMENT
9th FLOOR
8th FLOOR
7th FLOOR
6th FLOOR
5th FLOOR
4AFLOOR --
3rdFLOOR
TRANSVERSE
SHORING ^E 3
I St FLQOR _
BASEMENT
SUB-_BASEMENT
36
1,I J-I r71I
Fig. 27. Explosion detail of precast wall and floor assembly.
ing steel, which was a necessity for the mid-depth of the spandrel and midspan
Vierendeel wall truss. of alternate windows in plan. The pre-
The typical precast Vierendeel truss cast sandwich panel consisted of 12-in.
wall panel was 10 ft wide x 13 ft high (3 x (305 mm) thick structural concrete, 2½
4 m). Details of the wall panel are in. (64 mm) of polystyrene insulation,
shown in Fig. 26. Jointing was located at and 3 in, (76 mm) of precast concrete
38
exterior facing. Details of the concrete
jointing may be seen in Fig. 27. The
maximum vertical reinforcing in the
columns was 8414 bars and the maxi-
mum spandrel beam reinforcing was
6411 bottom bars and 2411 top bars.
During installation of the precast pan-
els as many as 28 reinforcing bars re-
quired proper fitting and connections
for one panel assembly. The NMB
splice sleeve was able to accommodate
this assembly resulting in the efficient
erection of the precast panels. Refer to
Figs. 28 through 32 for installation of
precast wall panels. Actual installation
of panels took place from November
1979 to June 1980, during both very
cold, windy, wintry conditions and mild
spring weather. Grouting of the sleeves
was permitted when ambient tempera-
tures were 40 F (4 C) or higher. During
certain periods of erection, artificial
heating was required to keep the ambi-
ent temperature at the acceptable mini- Fig. 28. Top view of installed precast wall
mum level. panels.
Fig. 29. Precast wall panel being lowered into splice sleeves.
I;
Fig. 31. Precast wall panel with horizontal splice sleeves in final setting.
40
Fig. 32. Erection of prestressed double tees on precast wall panels.
a♦
w14, 311
STL. COL.
,' ,^o
Via'•:''--^:^- .-q. . ,
- -FIRST STAGE POUR
SECOP
STAGI OUTLINE OF 3•-O"
POUR WIDE GIRDER
Fig. 34. Corner column junction with post-tensioned girder at third floor level.
f ?.' `FIRST STAGE POUR
/ / / /
/ *QO
/ y
Fig. 35. Corner column junction with post-tensioned girder below start of precast
Vierendeel wall panels.
creased to 6 in. (152 mm) with this addi- Fig. 40 shows construction of the cor-
tive. The installed concrete exhibited ner columns being performed after the
high quality placement and compressive third and final post-tensioning of perim-
strength. eter girders and transverse girders has
The post-tensioned perimeter girder been completed. Splicing of column
concrete and steel arrangement are reinforcing steel was performed by me-
shown in Fig. 36. The post-tensioned chanical connectors. Due to the density
transverse girder cross section is shown of the reinforcement, the use of smaller
in Fig. 37. Construction of the west and bars and lapping of column vertical
south perimeter girders is shown in Figs. reinforcing was not possible. A further
38 and 39, respectively. Shoring of these refinement of the corner column was
perimeter girders is also shown, These that the finish marble chip cladding was
shorings are kept in place and adjusted used as the form for the in situ column.
to bear snugly to the girders after each Placement of exterior cladding was
post-tensioning stage. The slipformed done prior to the second stage of post-
central core walls are visible in the tensioning. However, two panels were
background of Figs. 38 and 39. delayed in their placement on the north
44
Fig. 38. West perimeter girder prior to first stage of post-tensioning.
r S
_rc11!
Fig. 40. Preparation of corner columns Fig. 41. Placement of two cladding panels
after third stage of post-tensioning of was delayed until after post-tensioning of
perimeter girders. perimeter girders.
Computer Analysis
An important contribution to the sue-
cessful structural design of the Vieren-
deel wall was the application of com-
puter analysis. A modified in-house ver-
sion of the SAP program was applied in
conjunction with a General Automation
SPC 16/40 minicomputer with accessory
disc drive peripheral equipment.
For the north and south Vierendeel
wall truss, the analysis consisted of3949
Fig. 42. Partial view of Vierendeel truss nodal points and 1591 members. The
46
DOUBLE-TEE
4-S/8"0 L4x3x3/8
BOLTS DBL-TEE
STIFF PL
L6x6xI/2xO'-7"
PL I/2 x 3 x I -O PL I /2 x 8 x 1'- 0"
10"
AT CORE WALL
[Li_
DOUBLE-TEE CONNECTION DETAIL
f- --
Fig. 44. Precast double tee connection at slipformed center core wall.
east and west Vierendeel wall truss running time for each cycle of the north
analysis consisted of 2011 nodal points and south wall truss was 20 hours and
and 1952 members. A subprogram was for each cycle of the east and west wall
added to SAP to permit story by story was 12 hours. The total design effort to
adjustment of the Vierendeel wall truss realize an efficient structure required
in the same manner that the construc- numerous cycles of computer analysis.
tion sequence was performed. Historical The selection of construction se-
data of internal forces were accumulated quence and post-tensioning stages was
and stored until the total structure was optimized through analysis of the com-
completed. puter's calculations. Maximum dead
One complete cycle of each Vieren- load and total load displacements were
deel wall truss analysis consisted of 22 calculated at 1.0 and 128 in. (25 and 33
runs, which considers in sequence 19 mm), respectively. Actual field mea-
structural configuration levels and three surement of maximum deflections was
post-tensioning stages. Total computer 1.12 in. (28 mm). Computer tabulations
48