Sei sulla pagina 1di 9

determination of the dynamic voltages

Out-or-Phase Switching Voltages and which can appear across the circuit
breaker poles. Since the extinction of an
Their EKect on High-Voltage a-c arc will generally take place at a zero
of the current wave, the currents in each
phase of a balanced 3-phase circuit will
Circuit Breaker Performance not be interrupted at the same instant.
Therefore, the dynamic voltages which
are of interest for this investigation are:
W. M. LEEDS D. J. POVEJSIL 1. The dynamic voltage existing across one
FELLOW AIEE NONMEMBER AIEE open circuit breaker pole when the other two
poles are conducting.
2. The dynamic voltages existing across
THE possibility that transmission line the more probable conditions involving each of two open circuit breaker poles when
circuit breakers may be subjected to this unusually severe duty. the third pole is conducting.
as much as double normal line-to-ground This paper comprises an analytic study 3. The dynamic voltages existing across
voltage if opened during a system dis- of dynamic voltages to be expected at the each of three open circuit breaker poles.
turbance when sections on either side of terminals of a tie-line circuit breaker dur-
the circuit breaker are out-of-phase, has ing the separation of two parts of a system In order to calculate the dynamic
been recognized by manufacturers and 180 degrees out of phase. Transient voltages, it is necessary to define the
operating personnel for a long time. How- voltage crests have been investigated on following quantities.
ever, only a few isolated cases of trouble the analogue computer for a typical sys- Rl+jX,=R2+jX2=positive and negative
have been traced to this exceptional cir- tem under faulted and unfaulted condi- sequence impedances looking into network
cuit breaker duty, and therefore it has tions and the results are compared with from circuit breaker terminals
not been felt justifiable in circuit breaker oscillographic records obtained on an ac- Ro+jXo=zero-sequence impedance looking
specifications to insist on proven ability tual power system. Finally, high power into network from circuit breaker terminals
to handle double voltage interruptions.1 laboratory data obtained on modern high- E1 and E2=vector voltages to neutral on
Experience indicates that many circuit voltage circuit breakers opening fault each side of circuit breaker when all three
breakers have struggled through out-of- currents at twice normal voltage and poles are open
phase operations (which inherently in- higher are evaluated in the light of the El.= El-E2= vector voltage across circuit
volve only a fraction of the circuit break- maximum possible duty indicated by the breaker poles when all three poles are open
er's current interrupting capacity because analytic study.
It will be noticed that all quantities
of considerable line impedance) by con-
have been defined at the point of the cir-
tinuing to arc until separating parts of the Analytical Study cuit breaker location in the circuit. The
system have swung sufficiently in phase
purpose of this method of definition is to
again to permit interruption. For a sy7stem disturbance, the total re-
allow such factors as shunt loads and line
Nevertheless, there is evidence that this covery voltage across a circuit breaker at
capacitance to be taken into account
problem is becoming of greater impor- any point in the system can be considered without changing the fundamental ex-
tance because of the tremendous increase to consist of two components.
pressions. These factors are considered
in power concentration resulting from the 1. Dynamnic or normal frequency v-oltage in the calculation of E12, which depends
integration of large generating centers into component. upon:
gigantic interconnected power pools. 2. Transient component.
Circuit breaker intermpting capacities
now are required in the range from 3,500,- In the case of disturbances initiated by Paper 52-16, recommended by the AIEE Switch-
gear Committee and approved by the AIEE Tech-
000 to 10,000,000 kva, and the conse- switching, the magnitude of the transient nical Program Committee for presentation at the
AIEE Winter General Meeting, New York, N. Y.,
quences of faulty operation are likely to component is a function of the dynamic January 21-25, 1952. Manuscript submitted
become much more serious than hereto- voltage. Therefore, the first step in this October 24, 1951; made available for printing
November 20, 1951.
fore. study was the analytical determination of W. M. LEEDS and D. J. POVEJSIL are both with
These conditions justify a more de- the dynamic voltages which could exist Westinghouse Electric Corporation, East Pitts-
tailed inquiry into the actual condi- across the poles of a circuit breaker open- burgh, Pa.
tions to which tie line circuit breakers ing under completely out-of-phase condi- The authors are indebted to the Bonneville Power
Administration for the test data obtained during
may be subjected. Also, there is a nec- tions. special fault tests on their system made to deter-
essity for definite data to show that such An understanding of the operation of mine the magnitude of transient voltages which
could be obtained under out-of-phase conditions on
circuit breakers are capable of handling 3-pole circuit breakers is important in the an actual power system.

88 Leeds, Povejsil-Out-of-Phase Switching Voltages JANUARY 1952


Ld Cfl 1. Voltage behind subtransient reactance
4DO W of all machines.
2. Initial loads on all machines.
3. Line impedance (including capacitance).
-cn DI-
w Z
4. Shunt loads.
5. Machine and transformer subtransient
reactances.
10- Since all of this information is not
usually known, the calculation of the ex-
act value of E12 is somewhat difficult.
However, in general, when the systems on
each side of the circuit breaker are 180
degrees out of phase, the value of E12 will
fall in the range of 220 to 200 per cent of
normal line-to-neutral voltage.
CM o
1Ix/o The calculation of the dynamic voltage
-W IL.0
x across the first pole to open, and of the
-0
dynamic voltages across the first two
poles to open, was made by conventional
ix symmetrical components methods (Ap-
pendix I). The results are plotted in form
of families of curves as shown in Figure 1.
x ._
The numbers on the curves represent the
x percentages of E12, the 60-cycle voltage
cz across the circuit breaker with all three
0 poles open, and the area below each curve
represents the region in which the dy-
0

io namic voltage is below the value indicated


0.
on that curve.
v As an example of the use of these
0
#U curves, consider a system of the type
U
._
shown in Figure 2. For this system
-0
Xo/X1=2.0; Ro/X1=1.0; Rl/X1=0.2
Assume E12=210 per cent for the com-
pletely out-of-phase condition; therefore:
._

6)
v
Dynamic voltage across first pole to open
U
VW
(122)(210)=256 per cent
Dynamic voltage across second pole to
044 open=(110)(210)=231 per cent
Dynamic voltage across third pole to open =
lx/oH 61
210 per cent
C-
.E0,
This example shows that the dynamic
voltages across the circuit breaker poles
for completely out-of-phase conditions
in an effectively-grounded system are
LL considerably greater than double voltage,
the figure generally mentioned in dis-
cussions of out-of-phase switching duty.
This fact has been recognized by Hans
Thommen,2 who suggested an added
factor of 20 per cent to allow for shifting
of the neutral potential caused by cur-
rents flowing through the ground circuit.
The maximum values of dynamic
voltages occur on a completely un-
grounded system. If the system of
Figure 2 were ungrounded, the maximum
dynamic voltages would be
Dynamic voltage across first pole to open =
(1.50)(210)=315 per cent
Dynamic voltage across second pole to
open =(1.73)(210)=363 per cent
zX/OH Dynamic voltage across third pole to open =
I; 210 per cent

JANUARY1952 Leeds, Poveisil-Out-of-Phase Switching Voltages 89


A

~%-0--- LINE A 6
GROUNDING
3 BC
LINE

TRANSFORMER
A
, A

PHASE SEQUENCE - A B C
OPENING SEQUENCE a A C B
Figure 3. Single-line diagram of general system used for analogue
Figure 2. Typical system used for example computer study

Therefore, it can be seen that the out- was represented was assumed to have no of transmission line on each side of the
of-phase switching problem is even more ground wires because it was expected that circuit breaker, the maximum recovery
acute for systems which are not effec- the most serious recovery voltages would voltage does not necessarily occur on the
tively grounded. (The region of "ef- occur for this case. first peak of the recovery voltage wave.
fective grounding" as defined by the The subtransient reactance of the gen- This phenomenon is shown by Figure 4,
AIEE is shown by the shaded portions of eration and the connected transformer and can ke explained by the fact that the
Figure 1; that is, Xo/X1 < 3, Ro/X, < 1. 3) capacity at each end of the line was as- asymmetry of the circuit causes a time-
At this point, it should be emphasized sumed to be 40 per cent on a 324-mega- phase difference in the reflected waves
that the Xo/Xl ratio which is used to as- volt-ampere base, and the voltages be- which reach the circuit breaker. A sub-
certain dynamic voltages during out-of- hind subtransient reactance were made sequent discussion in this paper will in-
phase switching is not the same as that equal to 100 per cent of nominal system terpret this result as it applies to circuit
used to calculate dynamic overvoltages voltage. The transformers were con- breaker performance.
during faults. This difference can be seen nected delta-Y, grounded on the high
by referring to Appendix I. During side. A synchronous switch, which could
faults, the X0/Xl ratio at the fault loca- be adjusted to interrupt each phase at a Table 1. Test Numbers 1, 2, 3, and 4 for
tion is equal to the parallel combination zero of the current wave, was used to Generator Voltages 180 Degrees Out of Phase
of the zero-sequence networks on each simulate the circuit breaker. Sending and Receiving End Transformers Neu-
side of the fault divided by the parallel Using the basic system shown in Figure trdl Solidly Grounded. Generdtion at Each
combination of the positive-sequence net- 3, an extensive series of tests were per- End Equivalent to 324 Megavolt-Amperes
works on each side of the fault. How- formed to determine the magnitude of the
ever, for calculations involving voltages recovery voltages which would occur Maximum Recovery
across open conductors, the proper X0/Xl upon the opening of the tie circuit breaker Voltage Across Pole
in Per Cent of
ratio is equal to the series combination of when the opposite ends of the system were Normal Line-to-
180 degrees out of phase. The type of Line Length, Neutral Peak
the zero-sequence networks on each side Miles First Maximum
of the opening divided by the series com- tests performed and the results obtained A B Phase Peak Peak
bination of the positive-sequence net- are summarized in Table I. The crest
works on each side of the opening. recovery voltage figures are expressed in Test Number 1. Grounded Transformer Bank at
Circuit Breaker Not Connected. Circuit Breaker
per cent of normal line-to-neutral peak Opening Sequence ABC
Analogue Computer Study voltage. 100 ..100 . A. 366 . 366
In addition to the tests outlined in (a) 100 ..100 . B . 360 . 360
100. .10..C . 310 . 310
The characteristics of the analogue Table I, other tests were performed to de- 100 ..150 . A. 336 . 336
(b) 100. .15. .B . 336 . 336
computer4 make it ideally suited to the termine the effects of various system 100 ..150 . . C 250 . 276
parameters. The results of all tests are 100 ..200 . A . 270 . 366
solution of practically all power system 100 ..200 . B . 246 . 348
transient problems. In most cases, the discussed in the following sections. 100. .20..C . 240 . 284
procedure for setting up a problem and Test Number 2. 100-Megavolt-Ampere Grounded
EFFECTS OF CIRCUIT BREAKER POSITION Transformer Bank Connected to "A" Line at
obtaining a solution is the same with the Circuit Breaker Location. Circuit Breaker Open-
ing Sequence =ABC
analogue computer as with the a-c net- The tests show that the highest re- 100 ..100 . A . 324 . 324
work calculator. However, for transient covery voltages appear when the system (a) 100 ..100 . B . 324 . . 324
studies it is more advantageous to use a is symmetrical, or approximately sym- 100 ..100 . C . 300 . 300
100 ..200 . A . 326 . 326
3-phase representation of the system metrical, about the circuit breaker. (b) 100 ..200 . B . 300 . 300
100 ..200 . C . 260 . 260
rather than the positive, negative, and (Tests 1(A) and 4(A).) On the basis of
Test Number 3. 100-Megavolt-Ampere Grounded
zero sequence network representation this observation, it may be concluded that Transformer Bank Connected to "B" Line at
which is commonly used in network cal- the maximum recovery voltages under Circuit Breaker Location. Circuit Breaker Open-
ing Sequence=ABC
culator studies. In this way the transient completely out-of-phase conditions are 100 ..200 . A . 246 . 340
voltages can be measured directly rather approximately equal to twice the volt- (a) 100 ..200. B . 282 . 320
100 ..200. C . 224 . 294
than as positive, negative, and zero se- ages which would appear across the cir-
Test Number 4. Same as Test Number I Except
quence components. cuit breaker poles if the circuit breaker that Generation at End of "A" Line is Increased to
The basic system studied on the ana- were switching a grounded 3-phase fault 1,000 Megavolt-Amperes
at the circuit breaker location. Further 100 ..100. A . 370 . 370
logue computer is shown in Figure 3. Two (a) 100 ..100 . B . 370 . 370
pi sections per phase were used to repre- proof supporting this conclusion is shown 100..100 .10.C . 330 . 330
later in the paper. 100. .150 . A . 350 . 350
sent each 100-mile section of 230-kv line (b) 100. .150 . B . 350 . 350
since it was found that additional pi sec- When the circuit is decidedly asym- 100 150 . C . 320 .
100. .200 . A . 340 .
320
370
tions mnade no appreciable difference in metrical about the circuit breaker loca- 100. .200 . B . 320 . 370
the recovery voltages. The line which tion, especially with regard to the length 100. .200 . C . 240 . 330

90 Leeds, Povejsil-Out-of-Phase Switching Voltages JANUARY19-2


ground wires to the circuit was checked faults of all types were placed at many
by reducing the impedance of the ana- locations on the basic system. The basic
logue to zero-sequence currents. It was system also was varied as to the amount
found that this reduced the total recovery of generation and transmission line on
voltages in the same proportion as the each side of the circuit breaker and also
dynamic voltages were reduced. There- as to the method of grounding.
fore, recovery voltages for lines with In no case did the resulting recovery
Figure 4. Phase A recovery voltage during ground wires will be less than the values voltages exceed the values for the same
out-of-phase switching indicated in Table I by about 5 to 10 per system without a fault. Therefore, for
(A) Test 1(a). Circuit breaker at impedance cent. systems of the type studied, the presence
center of a permanent fault does not increase the
(B) Test 4(a). Circuit breaker not at imped- EFFECT OF GROUNDED TRANSFORMER recovery voltages during out-of-phase
ance center BANKS AT CIRCUIT BREAKER LOCATION conditions.
In Table I, Tests 2 and 3, the effect of
RECOVERY VOLTAGE COMPONENTS EFFECT OF SYSTEM LOADS
adding a 100-megavolt-ampere, 10 per
Of considerable interest in the analysis cent impedance, grounded transformer To determine the effect of system loads
of the circuit breaker recovery voltages bank at the circuit breaker location is on out-of-phase recovery voltages, vary-
is the separation of these voltages into shown. These figures show that the ing amounts of load were placed at the
transient and dynamic components. As grounded transformer bank reduces the sending and receiving ends of the line and
an example, consider Test number 1(A). magnitude of the maximum recovery at the circuit breaker location. This
For this test the system constants were: voltage. On the basis of previous discus- study showed that loads at the sending
and receiving ends caused a slight reduc-
Xo/XI= 1.65; Ro/X1=0.30; R1/X1=0.15 tion in the magnitude of the recovery
Using these values to obtain the dy- 13.8/230 voltages. Loads at the circuit breaker
namic voltage from the curves of Figure 1, location were very much more effective
the maximum transient overshoot of the in reducing the magnitudes of the re-
maximum recovery voltage was calcu- covery voltages.
lated approximately by subtracting these Since the amount of load at any point
peak dynamic voltages from the corre- in a system is extremely variable, it is
sponding value of the peak recovery volt- difficult to assign a quantitative value to
age given in Table I. the reductions of recovery voltages due to
The results are shown in Table II along system loads. However, from the stand-
with the results of a similar analysis of EACH MACHINE AND TRANSFORMER point of out-of-phase switching recovery
Test 2(A). For these cases, the average 108,000 KVA voltages, it is desirable to locate the tie
maximum transient overshoot is about 60 Xd'+Xt-40% circuit breaker at a load point.
Xg +Xt-40X
per cent of the peak dynamic voltage. A
similar analysis of the other system con- Figure 5. Test circuit used by Bonneville Figure 6. Interruption of 3-phase grounded
figuration yielded overshoots ranging Power Administration faults fed from Grand Coulee over a 100-mile
from 40 to 65 per cent of the peak dy- line through a 230-kv circuit breaker at Mid-
namic voltage. While the meaning of these way Station of the Bonneville Power Adminis-
results is somewhat obscured by such sions, this result is to be expected since the tration indicates half of the transient recovery
variables as asymmetry and damping, a grounded transformer bank reduces the voltage magnitudes that might be expected
fairly definite relationship between peak X0/XI ratio at the circuit breaker loca- across a tie circuit breaker separating two sys-
recovery voltage and peak dynamic tion. tems completely out of phase. Voltage and
current records from phase B on Test 5 and
voltage is indicated. phase C on Test 6 are reproduced. The high-
EFFECT OF LINE RESISTANCE
EFFECT OF GROUND WIRES est crest voltage obtained indicates the pohi-
The resistance of the transmission line bility of 1.77X2 or 3.54 times normal crest
In the basic analogue computer study, was varied in an attempt to.evaluate the voltage across one circuit breaker pole
the presence of ground wires was not con- effect of line resistance on the magnitude -60 KV. (1l77% NORM.)
sidered. However, the effect of adding of the recovery voltage. It was found
that a 200 per cent increase in line re-
Table II. Comparison of Transient and Dy. sistance made very little difference in the
namic Components of Test Numbers I and 2 magnitude of the first peak of the re-
covery voltage, although subsequent
Transient peaks were reduced appreciably.
Over-
shoot
Recovery Dynamic Transient Peak EFFECT OF FAULTS
Voltage Voltage Overshoot Dynamic
Phase (Peak) (Peak) (Maximum) Voltage It is conceivable that at some time a
circuit breaker may be required to open Ekcof- 135 KV(RMS)
Test Number l(a)
under out-of-step conditions when a
IC -1300 AMP CRMS)
A .366 .. 232 .. 134 .. 0.58
B . 360 . 218 . 142 . 0.65 faulted condition exists on the line being
C . 310 . 200 . 110 . 0.55 TESTV<. NORM.)
switched. This condition is most likely to
Test Number 2(a) exist on single tie lines which are loaded
A . 324 . 202 .
C .0.
300 . 0.
122 . 0.60
B. 324 .. 196 .. 128 . 0.65
100 . 0.50
close to the stability limit.
To investigate this effect, permanent
S)~~~TETN
JANUARY 1952 Leeds, Povejsil-Out-of-Phase Switching Voltages 91
EFFECT OF DELAY IN OPENING mately half-way between Grand Coulee and
SUCCESSIVE PHASES North Bonneville.
2. In making these exploratory tests, it
In the basic study, it was assumed that was desirable to avoid any possibility of
the phase currents were extinguished on damaging the circuit breaker. Therefore,
successive current zeros; that is, 60 de- the assumption was made that the recovery
grees apart. Since the circuit breaker voltages which would appear across the cir-
does not always operate in this fashion, a cuit breaker poles when Grand Coulee was
180 degrees out of phase with North Bonne-
study was made of delayed opening of one ville are equal to twice the recovery voltages
or two phases with respect to the first which would appear if the circuit breaker
phase to open. It was found that the re- were switching a 3-phase grounded fault on Figure 9. The transient recovery voltage
the North Bonneville side of the circuit
covery voltages were slightly less than breaker. appearing across a dead-tank circuit breaker
those which occurred when opening took when clearing a grounded fault is not divided
place at successive current zeros. There- 3. The test circuit used is shown in Figure equally between the two interrupting assem-
5. Three 108,000-kva machines were iso- blies Cl and C2 because of the unbalancing
fore, the basic study was pessimistic in lated from the rest of the system and con-
this respect. nected through transformers to one of the effect of the capacitance Ca from cross bar to
100-mile 230-kv Coulee-Midway lines. A tank which is effectively in parallel with C2 as
permanent fault was placed on the line at shown by the diagram. Resistor units R, and
Bonneville Power Administration the Midway station. The circuit breaker R2 of about a megohm each will serve to re-
Tests was closed into this fault and then opened. store substantially equal voltage division
The resulting voltages and currents at the
For economic reasons, it has been the circuit breaker were measured by an oscillo-
practice of the Bonneville Power Admin- graph. Enough time was allowed between
istration to operate their long high-volt- closing and opening to permit the direct that oscillograms of the transient over-
current component of fault current to decay voltages appearing on an actual system
age transmission lines at relatively high to a negligible value. can be obtained. Therefore, the results
kilowatt loadings. This has resulted in a of the Bonneville Power Administration
decrease in the stability margins with con- A A -
tests offered an excellent opportunity to
sequent increase in the possibility that the 0rI
demonstrate the effectiveness of the ana-
high-voltage circuit breakers used to CiF
F8 C-. B~~~ logue computer for transient voltage prob-
switch these lines may occasionally be VECTOR lems.
subjected to out-of-phase switching duty. DIAGRAM
Accordingly, the Bonneville Power Ad-
Therefore, this problem of out-of-phase POWER SOURCE BREAKER
switching of high-voltage transmission ministration test circuit was set up on the
Figure S. The frst pole of a circuit breaker to analogue computer. Photographs of the
lines has been given considerable atten- clear a 3-phase ungrounded fault such as Phase recovery voltages which were obtained
tion by the Bonneville engineers. A in this circuit must withstand a dynamic re- are shown in Figure 7. The maximum re-
In order to obtain fundamental infor- covery voltage AF which the vector diagram
mation governing the severity of out-of- shows to be 86.6 per cent of line-to-line volt- covery voltages appeared on the first two
phase switching duty, the Bonneville age. The two poles B and C in series divide phases to open, and their magnitude was
Power Administration recently conducted the duty of clearing the line-to-line fault which 190 per cent of normal line-to-neutral
a number of actual system tests. The remains peak voltage. The dominant frequency
following reasoning and procedures were of the transient voltage was between 250
used for these tests: The oscillographic records showed that and 300 cycles. For comparison with
the maximum value of transient recovery these values, the maximum recovery volt-
1. The Bonneville Power Administration voltage was 177 per cent of normal line- age on the Coulee-Midway line was 169
was primarily interested in the switching to-ground crest voltage. Actually, the per cent and the dominant natural fre-
duty imposed upon circuit breakers at their quency also was between 250 and 300
Midway switching station, located approxi- peak recovery voltage may be somewhat
higher than this value because the value cycles.
of 177 per cent is in per cent of the peak It was to be expected that the analogue
Figure 7. Recovery voltages obtained From of a normal voltage wave which contains computer results would be higher than
analogue of Bonneville Power Administration considerable third harmonic peaking. actual system tests because in addition to
tests For interruptions not characterized by the inherent error in reading the actual
(A) First pole to open prolonged arcing in the circuit breaker, system oscillograms due to third harmonic
(B) Second pole to open the maximum value of the transient re- peaking in the reference wave, sources of
(C) Third pole to open covery voltage was 169 per cent as read damping such as corona and transformer
(D) Steady-stdte voltage across poles with from the oscillogram shown in Figure 6. saturation were not considered in the ana-
three poles open Once again the value of 169 per cent is logue computer study. Taking all of the
probably low. aforementioned factors into considera-
Applying the reasoning stated earlier in tion, it may be concluded that a good
this section, the maximum voltages which agreement between analogue computer
would appear across the circuit breaker results and field results was obtained.
poles during a completely out-of-phase Of considerable interest is the validity
opening would be twice the values des- of the assumption that the maximum
ignated in the previous paragraphs. recovery voltages during completely out-
In addition to the importance of these of-phase condition are equal to twice the
studies to the out-of-phase switching recovery voltages which appear when the
problem, they are extremely valuable circuit breaker switches a grounded 3-
from another standpoint. It is seldom phase fault at the circuit breaker location.

92 Leeds, Povejsil-Out-of-Phase Switching Voltages JANUARY 1952


x x y x Y
Y
a
POSITIVE
I
o
POSITIVE
b o on
b 0 0
I on

0 c xy
c o NEGATIVE
l NEGATIVE on
Ion
n n x ---
ZERO ZERO
on
on

A B
Figure 10. Sequence network connections
(A) One circuit bredker pole open (B) Two circuit bredker poles open

Referring to Table I, it is seen that the come the voltage unbalancing effect of part of this paper shows that during out-
maximum recovery voltage is 370 per cent the capacitance between the moving con- of-phase switching the neutral shift
of normal line-to-neutral voltage. Doub- tact cross-arm and the grounded tank, caused by ground return currents before
ling the results obtained for switching see Figure 9. the third phase clears may result in
grounded 3-phase faults on the Coulee- However, under out-of-phase switching dynamic voltages of as high as 2.5 times
Midway line and also the results from its conditions at a time when there are no normal. It is doubtful whether most
analogue yields 338 per cent and 380 per faults on the lines connected to either side present-day circuit breakers are capable
cent respectively. of the circuit breaker, the approximatelv of handling such an extreme condition
symmetrical location of potentials results consistently. However, considering the
Circuit Breaker Interrupting Ability in a fairly equal division of voltage be- low probability of encountering this
tween the halves of each circuit breaker theoretical maximum voltage, it may not
The short-circuit interrupting ability pole. In fact, it can be argued that if a be economical to make such performance
of a high-voltage circuit breaker is usu- circuit breaker with no voltage-dividing a definite specification which could in-
ally verified by single-phase fault tests at means has been tested successfully in the vrolve considerable additional cost to pro-
normal line-to-ground voltage either in a laboratory with at least 87 per cent of vide the necessary factors of safety in in-
high power laboratory or on a large power rated line-to-line voltage applied to one terrupting ability. Before coming to a
system. Since the first circuit breaker pole with one terminal grounded (in- conclusion on this point, it will be well to
pole to clear a 3-phase ungrounded fault stead of the actual 3-phase ungrounded consider the magnitude of the transient
on a system with grounded neutral will fault condition of two-thirds voltage overvoltages that could be encountered
have a dynamic recovery voltage of 1.5 above ground on one terminal of the first under the more pessimistic of out-of-
times line-to-neutral voltage, 86.6 per pole to clear and one-third voltage below phase switching condition.
cent of line-to-line voltage, (see Figure ground on the other terminal) then the
8) until the line-to-line fault which re- same circuit breaker should be capable of RATE OF RISE OF RECOVERY VOLTAGE
mains is cleared by the other two poles, handling the balanced out-of-phase condi- AND TRANSIENT VOLTAGE CRESTS
some further fault testing is often in- tion of approximately double line-to- It is well known that the criterion of a-c
cluded either at this voltage or even with neutral voltage across each circuit breaker arc interruption is based on building up
full line-to-line voltage across a single pole. To take a 230-kv circuit breaker as dielectric strength in the contact gaps
pole. an example, a single-pole test at 198 kv to immediately folloAing a current zero at
The situation at the present time and ground with a very conservative estimate such a rate that the voltage required for
probably in the future is that high power of 70 per cent 30 per cent voltage dis- breakdown is always above the rising re-
laboratories are not of sufficient capacity tribution between the two halves of the covery voltage. Therefore, a knowledge
to test the largest circuit breakers at circuit breaker would indicate that the in- of the transient voltage crest and the time
their full short-circuit interrupting rating terrupting units on the high side were to reach it is necessary in addition to the
even on a single-phase basis. However, capable of handling 139 kv which is ap- magnitude of the dynamic voltage in
the unit method of testing by which only proximately half of the out-of-phase order to establish the actual severity of
a subdivision of a circuit breaker is veri- voltage that might appear across the cir- the interrupting duty on a circuit breaker.
fied at a proportionately reduced voltage- cuit breaker. Traveling waves over the connecting
for instance, a half-pole tested at half W0here voltage division in a circuit transmission lines and the interaction of
line-to-neutral voltage-provides fault breaker is controlled, for instance by re- reflected waves make calculations of
currents of greater magnitude by appro- sistor units of a megohm or less, the per- transient voltage conditions during
priate changes in the test transformer formance under out-of-phase conditions switching very difficult. However, some
ratio. The validity of the unit method of might be checked up to double voltage by of the answers to typical situations have
testing, of course, depends on the effec- field tests at normal line-to-neutral volt- been indicated by the analogue computer
tiveness of shielding means or voltage- age but with one-half of the interrupting on which transient conditions of a system
dividing impedances in establishing an units shunted out. In fact, the sym- set up in miniature have been studied.
equal share of the recovery voltage across metrv of out-of-phase voltages, as just These show transient overshooting of as
each unit of the circuit breaker. discussed above, might make such a half- much as 60 per cent above the dynamic
The dead-tank circuit breaker pro- pole test also reasonably valid even for voltage crest. Under the most unfavor-
vides an unequal division of voltage dur- circuit breakers without voltage dividing able out-of-phase switching conditions
ing grounded fault conditions unless suit- impedances. within the limits of effective grounding
able compensation is provided to over- However, the analytic study in the first (RoIX1 <1 and XO/X1 <3), using a dy-
JANUARY 195-2 Leeds, Po-vejsil-Out-of-Phase Switching Vloltages 93
namic voltage factor of 130 per cent from resistors in the circuit breaker as part of Table Ill. High Power Laboratory Over-
the curves of Figure 1 (A), the peak of the the contact assembly. voltage Interrupting Tests
transient voltage could theoretically reach
1.3X2X1.6 or a little over four times HIGH POWER LABORATORY TESTS Inter-
rupted
Inter-
rupting
Single-Phase
normal line-to-ground crest voltage. On Test Test Voltage Current, Time,
A number of modern high-voltage cir- No. Ky X Normal Amperes Cycles
a 230-kv system this amplitude would be cuit breakers have been tested at double
230/V/3 X V/2 X4.16 = 780 kv, which ex- voltage and higher with quite satisfac- A. 138-kv 3,500-Megavolt-Ampere Circuit Breaker
ceeds by 30 per cent the crest voltage of tory results. Table III shows data taken 2-91303.. ..160 . 2.0 ....... 210.. 2.4
2-91304.... 160 . 2.0 ....... 1140 .. 2.4
the 425-kv 1-minute insulation test ap- from High Power Laboratory tests on 05....160 . 2.0 ....... 1060 .. 2.8
plied across the fully-open contacts of cir- typical circuit breakers from the 138-, 06.... 160 . 2.0 ....... 1160.. 2.9
2-91307... .160 . 2.0 ....... 3500 .. 2.8
cuit breakers for use on 230-kv systems 161-, and 230-kv voltage classes. Note 08... .160..... 2.0...... 2550 ......2.9
09....160 . 2.0 ....... 3300.. 2.6
with effectively grounded neutrals. This that on the 10,000-megavolt-ampere 230- 2-91310. ...160 . 2.0 ....... 4550 .. 2.9
emphasizes the extreme duty that is in- kv circuit breaker, the tests were carried 11 .... 160 ..... 2.0....... 6050 ..... 2.8
12 .... 160. 2.0. 4550 .. 2.7
dicated by these calculations. as high as 360 kv across a single-pole
B. 161-kv 10,000-Megavolt-Ampere Circuit
In some cases, the maximum voltage is unit, or 2.7 times normal line-to-ground Breaker
reached on a later crest than the first peak voltage, without damage to the inter- 2-95215.... 198. 2.1 ....... 95 . 2.5
16....198 . 2.1 ....... 105 . 2.5
of the transient recovery voltage, see rupters. The maximum crest voltage 17.... 198 . 2.1 ....... 80 . 2.3
Figure 4, which greatly lowers the prob- withstood on the recovery voltage tran- 2-95218.... 198. 2.1 ....... 250 . 2.4
19....198. 2.1 ....... 235 ... 2.3
ability of arc reignition since the proc- sient was in the neighborhood of 560 kv. 20.... 198 ..... 2.1 ....... 235......2.5
esses of deionization in the interrupter Although damping in the laboratory cir- 2-95221. ...198 . 2.1 . 1000 .. 2.6
22....198 . 2.1 . 1000 .. 2.6
will have had time to be practically com- cuit limited the overshooting to approxi- 23.... 198 . 2.1 . 1280 .. 2.6
pleted. Also, it has been shown that mately 20 per cent, the frequency oscilla- 2-95224... ..198 . 2.1 . 2600 .. 2.8
25 ... .198 ..... 2.1 ...... 2600 ..... 2.7
there are many factors in practice which tion was quite high, around 3,000 cycles, 26 ... .198 ..... 2.1 ...... 2900......2.5
compared to the 300- to 400-cycle oscilla- 2-95227... ..198 . 2.1 . 4400 .. 2.6
can reduce the magnitude of the transient 28.... 198 . 2.1 . 4600 .. 2.7
voltage that theoretically may appear tion encountered in the field. 29....198 . 2.1 . 6100 .. 2.7
across the terminals of a tie circuit breaker. C. 230-kv 10,000-Megavolt-Ampere Circuit
Breaker
For instance, unequal line lengths on Conclusions 2-100323. ..264 . 2.0 . 1500 . ..2.6
either side of the circuit breaker, unequal 2-100324. ..330 . 2.5 . 2050.. 2.5
25...330 . 2.5 . 1800 .. 2.9
generating capacity on the two ends of 1. An analytic study, supplemented 26...330 . 2.5 . 2050.. 2.8
the line, grounded transformers or heavy by measurements on the analogue com- 2-100327 ... 360 . 2.7 . 2250 .. 2.7
28...360 . 2.7 . 2000.. 3.0
loads in the vicinity of the circuit breaker, puter, has been made for the typical volt-
overhead ground wires, attenuation of age transmission systems under out-of-
traveling waves due to corona and other phase voltage conditions to determine with transient overshooting of approxi-
losses in the lines and iron losses in the magnitude of possible recovery voltages mately 25 per cent, opening fault currents
transformers, any and all of these may that may appear across opening tie-line up to, say, 25 per cent of the current in-
cut down the maximum value of the volt- circuit breakers. Even on effectively- terrupting capacity rating.
age. grounded systems, it appears that dy-
In addition, it is quite probable that namic voltages up to 2 to 2.5 times nor-
interruption under an out-of-phase con- mal plus 25 to 60 per cent transient over- Appendix 1. Calculation of
dition, which is an infrequent occurrence shoot are theoretically possible. These re- Dynamic Voltages
in itself, will usually occur when the dif- sults are in agreement with data from field
ference in-phase is much less than the full tests on the Bonneville Power Adminis- With one pole open, Figure 10, assume cir-
cuit breaker pole in phase a has cleared.
180 degrees. tration 230-kv system made for the pur- Then
At the present time, there are no test pose of indicating possible voltages under
specifications for circuit breakers covering completely out-of-phase conditions. Ia = 0
interrupting ability under out-of-phase 2. The presence of permanent faults Vxyb Vxyc 0
= =

voltage conditions. If the most unfavor- on a system under out-of-phase conditions since
able conditions indicated by this study as does not increase the magnitude of the Vxya Vxya,l + Vxya,2+ Vxya,o
=

theoretically possible, although extremely maximum recovery voltages on the circuit Vzxb a2 Vxya,i+a Vxya,2+ Vxya,o
=

unlikely, were taken as the basis of a breakers separating parts of the sys- Vxyc a Vzya,i+a2 Vxya,2+ Vzya,o
=

specification, the cost of suitable circuit tem.


then
breakers would probably be increased 3. More consideration seems justi-
considerably more than warranted by fied in the verification of high-voltage Vzya, = Vxya,2 VXiia,O
=

difficulties now experienced with present circuit breaker interrupting performance Ia,l -(Ia,2+Ia,o)
equipment. However, a reasonable test to checking the ability to handle higher These relations dictate the sequence net-
might be the interruption of moderate than normal recovery voltages encoun- work connections shown in Figure 10.
short-circuit currents up to, say, 25 per tered by tie-line circuit breakers under Employing Thevenin's Theorem, and de-
cent of rating at twice normal line-to- out-of-phase conditions. In view of the fining constants as was done in the text, the
ground voltage. The natural frequency relatively minor damage attributed to voltage across the open pole can be written:
of the recovery voltage transient should such relatively infrequent overvoltage in-
be not less than 300 cycles, with no more terrupting duty in service, it may be un- XI
Ey= 3E121 R021 2XI
economical to design for the theoretical ErV=El20R, +2R 2(1 2Xo
external circuit damping than enough to 2]
limit the overshooting to approximately maximum voltages indicated by this IXIo XI+e +X
25 per cent of normal crest. Additional study. Tests are suggested, however, up
damping could, of course, be provided by to at least double line-to-ground voltages For constant values of Exy/E,2 and Ru/X1,
94 Leeds, Povejsil-Out-of-Phase Switching Voltages JANUARY 1952
this equation can be rewritten in the form of AGES UP TO 400 Kv, Hans Thommen. Report 109, Transactions), volume 58, August 1939, pages 386-
a family of circles with radii equal to International Conference of Larch High Voltage 94.
Electric Systems (Paris, France), 1946.
6. PRACTICAL CALCULATION OF ELECTRICAL
3K V\11+(RI/Xl)1 2. STANDARD FOR NEUTRAL GROUNDING DEVICES.
AIEE Standard Number 32, 1947.
TRANSIENTS ON POWER SYSTEMS, R. D. Evans,
R. L. Witzke. Electrical Engineering (AIEE
4K2-9 Transactions), volume 62, November 1943, pages
3. ELECTRICAL TRANSMISSION AND DISTRIBUTION 690-96.
where K = Exv/E12, and centers at REFERENCE BOOK. Westinghouse Electric Corpo-
7. TRANSIENT PERFORMANCE OF ELECTRIC POWER
ration (East Pittsburgh, Pa.), 1950.
SYSTEMS (book), Reinhold Rudenberg. McGraw-
-2K2 2(R1/X1)K2 4. SYSTEM RECOVERY VOLTAGE DETERMINATION Hill Book Company, New York, N. Y., 1950.
4K2 -9' 4KI2_9 BY ANALYTICAL AND A-C CALCULATING BOARD 8. TRANSIENT RECOVERY VOLTAGES AND CIRCUIT-
METHODS, R. D. Evans, A. C. Monteith. Electrical BREAKER PERFORMANCE, R. C. Van Sickle. Elec-
Engineering (AIEE Transactions), volume 56, July trical Engineering (AIEE Transactions), volume 61,
References 1937, pages 695-703. November 1942, pages 804-13.
5. POWER-SYSTEMS TRANSIENTS CAUSED BY 9. TRANSIENTS IN POWER SYSTEMS (book), H. A.
1. PROBLEMS CONNECTED WITH THE RUPTURING SWITCHING AND FAULTS, R. D. Evans, A. C. Mon- Peterson. John Wiley and Sons, Inc., New York,
OF ALTERNATING CURRENTS AT VERY HIGH VOLT- teith, R. L. Witzke. Electrical Engineeiring (AIEE N. V., 1951.

Discussion R. L. Webb (Consolidated Edison Company


of New York Inc., New York, N. Y.):
conveniently located at load points than
anywhere else.
Our systems in New York City are probably On the whole, the paper is reassuring in
K. J. Falck (Philadelphia Electric Company, among the least likely to require the type that the maximum unfavorable conditions
Philadelphia, Pa.): The paper is a valuable of out-of-phase switching referred to by the seldom exist. The experience of a sub-
contribution and presents a number of authors. committee of the Switchgear Committee of
important facts previously either not sub- Yet we did experience such a duty on an the AIEE bears this out. When the sub-
stantiated or not generally recognized. older oil circuit breaker on our 27-kv sys- committee was studying this problem 2 or 3
This discussion does not dispute any of the tem on October 26, 1949. The condition years ago, it was unable to get a sufficient
facts and conclusions but merely offers was caused by a cross-phase connection amount of data having to do with actual
clarifications and additional emphasis on being made at a 3-conductor cable splice occurrences in the field to be able to draw
some points.
in a street manhole plus a second error any conclusions from it. It finally asked
In the first paragraph of the paper a being made in checking the phase-out indi- to be discharged because it did not feel
statement is made that ". it has not been cations when the feeder was energized back that it was able to cope with the problem to a
to the generating station from the sub- sufficient degree to warrant keeping it in
. .

felt justifiable in circuit breaker specifica-


tions to insist on proven ability to handle station. A and B phases had been crossed. existence.
double voltage interruptions." This may be The feeder was de-energized after the There is no question, however, that fur-
entirely correct but at the end of the state- phase test, declared ready for service, and ther study is necessary on this subject to
ment reference is made to the 1949 report was made alive at the generating station. make sure that all phases of it have been
of the AIEE subcommittee on out-of- The substation circuit breaker was then covered. To conclude that unfavorable
phase switching. This report concluded closed again and an explosion and oil fire conditions are not likely to occur very often
that circuit breakers capable of handling followed immediately. is not sufficient to warrant our ignoring the
double voltage interruptions are not gener- This circuit breaker is a 1923 vintage with problem.
ally justifiable but it did not intend to plain break contacts. The arc was not
exclude proven ability for specific cases. interrupted by this circuit breaker. It E. J. Harrington (Bonneville Power Ad-
It actually suggested that such cases be played around enough to burn the bottom ministration, Portland, Oreg.): We at the
referred to the manufacturers. of the circuit breaker tanks on the two Bonneville Power Administration are in-
Referring to the second paragraph of the crossed phases. There was no system out- debted to the authors for their efforts in
paper there is no question about the impor- of-step condition. The fault was cleared by obtaining these additional data on this
tance of the subject but large power concen- operation of other circuit breakers, without subject. It is gratifying to know that sys-
tration does not in itself have to mean further circuit breaker distress. tem conditions can be duplicated reliably
greater chances of out-of-phase switching. This is a type of out-of-phase circuit by analogue computer methods thereby
Higher capacity or multiple tie lines could breaker duty which the Subcommittee greatly extending the range over which such
reduce such chances but it is, of course, may want to consider. investigations may be carried.
recognized that if unsuccessful switching Because of our concern in regard to pos-
occurred it might be more serious on large sible out-of-phase switching voltages at
systems. A major reason for the increased F. A. Lane (American Gas and Electric several points on our system, we devised
importance of the subject of this paper is Service Corporation, New York, N. Y.): and conducted at Midway Substation the
the present tendency to operate lines closer The paper gives a very excellent discussion field tests described by W. M. Leeds and
to the steady state stability limit which of conditions which exist when switching D. J. Povejsil. We are certainly pleased to
has been made possible by the availability occurs between two systems out-of-phase. have our results checked so well on the
of higher speed circuit breakers, relays and It is notable, however, that many of the analogue computer and to have the study
voltage regulators. worst incidences which might occur are extended to unbalanced switching locations.
The paper provides further justification likely to be extremely rare. Even the absence of corona damping in the
for the general practice of solidly grounding One situation has to do with the fact that latter studies apparently introduced no
the neutral of high-voltage systems and also when the system is symmetrical around the particular error.
shows the definite need for the testing of circuit breaker in question, the highest We had for some time been aware that
circuit breakers with voltage across one rate of recovery of voltage occurs. In the out-of-phase switching might produce ab-
phase at least equal to full line-to-line complex systems with which we deal ordi- normally high voltages across the circuit
voltage. narily, it seems unlikely that this peculiar breaker but did not become actively con-
It is to the credit of the authors that they state of affairs will occur often so that we cerned until routine inspection of a 230-kv
are presenting the results of their analytical probably will not need to be seriously con- line circuit breaker disclosed burns indicat-
study in such convenient form that any cerned with it, as might be the case other- ing the circuit breaker had failed to clear
application can be checked by merely deter- wise. properly during some operation since the
mining the ratio of reactances and resist- It is interesting to note that the authors previous inspection. A check of operation
ances. have concluded that from the standpoint has indicated that an out-of-step condition
In addition to its direct contribution this of out-of-phase switching, it is desirable to resulting in operation of this circuit breaker
paper should stimulate further studies and locate the tie circuit breaker at a load point. must have been responsible for the damage.
tests in this important field. Fortunately, in most cases they are more The authors mention that it is quite prob-

JANUARY 1952 Leeds, Povejsil-Out-of-Phase Switching Voltages 95


able that interruption will occur when the It might be appropriate to caution system of restrikes occurred. The circuit breaker
voltages across the circuit breaker are less designers not to neglect these transient might eventually separate the intercon-
than 180 degrees apart. This would as- voltages that can appear during out-of-phase nected system into two components. Where
sume interruption before the systems have switching if they are planning systems of high speed of separation was essential to
rotated to this angle or continued arcing reduced basic impulse level, as such voltages maintain stability of the components, the
in the circuit breaker until the angle has might well set the level of maximum switch- restriking might lead to instability of one
passed through a maximum and becomes ing overvoltages on a system. or both components, and an extended inter-
less than 180 degrees. Either assumption is As shown by the authors' curves in Figure ruption. The consequences might be seri-
valid, and in the latter case prolonged arcing 1 of the paper, anything which increases ous, although the circuit breaker itself
at the low values of current involved prob- the ratios X0/Xl and Ro/X, will increase the suffers little or no damage.
ably would not damage the circuit breaker dynamic voltages appearing across the
very much. This assumption as to only circuit breaker. The use of series compen-
minor damage is justified only if the arcing sation will increase these ratios and conse- W. M. Leeds and D. J. Povejsil: The
is controlled and is confined to the space quently the circuit breaker duty if the comments and supplementary discussion
between contacts within the interrupters. system parts through a compensated sec- on the subject of out-of-phase switching
If during the interrupting period a high tion. are greatly appreciated by the authors.
dielectric strength is attained between con- Both Mr. Falck and Mr. Floyd mentioned
tacts within the interrupter, it may suc- that the growth of power systems does not
cessfully withstand the overvoltages be- G. D. Floyd (The Hydro-Electric Power necessarily increase the chance of out-of-
tween contacts but flashover may occur Commission of Ontario, Toronto, Canada): phase switching since points of generation
over the outer surface of the interrupter The paper refers to a study made by a sub- are usually tied together by more than one
due to venting of the hot gasses from the committee of the AIEE set up a few years line in a large closely integrated system.
arc chambers. If this should happen total ago to study the incidence of circuit breaker Nevertheless the consequences of a circuit
destruction of the circuit breaker could failures due to out-of-phase switching. breaker failure become more serious as the
occur unless it is cleared by another circuit The scope of this committee's activities did power concentration increases, so that care-
breaker. not permit an analysis such as has been so ful consideration of unlikely but hazardous
In the case of the 230-kv circuit breaker ably done and reported here. Information operation conditions seems desirable.
mentioned above, flashover of the inter- such as recorded in the paper will be of Mr. Webb's experience of circuit breaker
rupters had occurred and major damage is great value to those who recognize and are trouble resulting from a cross-phase con-
believed to have been averted only by near still studying this problem. The rather nection in a cable splice is an interesting
simultaneous opening of the circuit breaker limited survey made by the committee example of an improbable occurrence which
at the other end of the line. This left only indicated the condition was not wide- actually happened and put excessive volt-
line charging current in the arc over the spread. However this condition may have age on a circuit breaker.
interrupters which probably was interrupted existed and also may have been the cause of We must agree with Mr. Harrington that
by the gaps forned between the crosshead circuit breaker restriking, if not failure, prolonged arcing in a high-power circuit
and the interrupters as the circuit breaker without being recognized. breaker under out-of-phase conditions may
went to the full open position. It should not be inferred from the second have serious consequences, and, therefore,
This writer is in agreement with the paragraph of the paper, and I do not be- it is natural for a customer to want as large a
authors as to verification of high-voltage lieve the authors intended that it should factor of safety in voltage interrupting
circuit breaker interrupting performance that with the growth of systems there was a ability as possible. If, however, as Mr.
under such voltage conditions. While it greater tendency, per se, for failures or Lane has pointed out, the probability of
may prove uneconomical to design circuit restriking of this kind. As the systems obtaining the more severe overvoltage
breakers for the theoretical maximum volt- grow, the short-circuit ratings of their as- conditions is relatively low, the risk involved
ages which may occur under out-of-phase sociated circuit breakers also increase. in using standard circuit breakers in tie
switching, care should be taken to main- The currents involved in the out-of-phase line positions should be balanced against the
tain sufficient dielectric strength external switching also increase. I believe it is higher cost of circuit breakers designed to
to the interrupter by proper dimensioning, reasonable to conclude that the ability of meet a more drastic test specification.
control of venting, and so forth, so that the circuit breaker of higher interrupting Fortunately recent progress in circuit
current conduction is confined to within the rating to prevent restrikes increases more or breaker designs has been such that modern
interrupter at all times, giving the circuit less in proportion. A serious situation might high-voltage switchgear actually has suf-
breaker a chance to interrupt when the volt- develop in an extended interconnected sys- ficient margin to operate satisfactorily under
age conditions have been ameliorated. tem of large capacity, however, if a number all reasonable operating conditions.

96 Leeds, Povejsil-Out-of-Phase Switching Voltages JANUARY 19052

Potrebbero piacerti anche