“Am I supposed to be
“My boss doesn’t want able to read this?”
to see all of that detail.”
Ron Drake, PE
• Leading complex infrastructure projects for 40 years, including:
1990-1993: Metro Red Line (Los Angeles, CA)
1993-1998: Tri-Met Westside Light Rail (Portland, OR)
2005-2007: Brightwater Conveyance Project (Woodinville, WA)
2014-Present: LA Metro Regional Connector (Los Angeles, CA)
• Has made linear scheduling a cornerstone of his project management approach for decades.
4
What We Believe:
We believe that the vast majority of people that work on these projects really
do want to know what’s in that huge schedule with thousands of activities.
They want to know the master plan. They want to see the big picture and understand the relationships
between activities. They want to know about the deadlines that their crew must meet. But our industry
lacks the tools to communicate that information in a way that the entire team can understand.
We believe that if you make your schedule beautiful, your team will use it!
If you place a good-looking linear schedule on the table in any project office or jobsite trailer, people will
go out of their way to look at it, pick it up, and study it. Then they will ask questions, and give you
valuable feedback about how the work will actually be built.
(But if you don’t make your schedule beautiful, it will be ignored and forgotten like all the rest.)
5
We believe that adding a simple graphic of what you’re building makes your
schedule information 10x more useful and effective.
Most people are visual learners, and schedule data doesn’t sink in unless they can visualize the major
work elements and the spatial relationships between them. A one-page illustration of scope of work and
schedule becomes a very useful “talking paper” that helps you quickly explain your entire project to
anyone, anywhere. And your team members will undoubtedly start sketching right on top of it for all
sorts of problem solving, alternatives, and what-if-scenarios. This is when the magic happens – increasing
the chances of your team delivering a winning project.
6
Coming Up:
This guide will walk you through the fundamentals of a linear schedule, give you the vision
for how it can be applied, and show you how to put it to work as your project evolves.
Along the way you’ll hear from more industry leaders about how they’re using linear
scheduling to execute their own challenging projects.
1 The Basics
9
BORED TUNNEL
SOUTH NORTH
SHAFT SHAFT
10
X = Time
90+00
70+00
BORED TUNNEL
50+00
30+00
Y = Location
10+00
SOUTH SHAFT
12
Linear Schedule:
2017 2018 2019
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
NORTH SHAFT
110+00
PREP SITE CONSTRUCT RETRIEVE SUBSTANTIAL
NORTH SHAFT TBM COMPLETION
90+00
70+00
BORED TUNNEL
PUNCH LIST
50+00
30+00
ASSEMBLE
CONSTRUCT TBM
PREP SITE SOUTH SHAFT
10+00
SOUTH SHAFT
13
NORTH SHAFT
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Milestone
110+00
(deadline or
PREP SITE CONSTRUCT RETRIEVE SUBSTANTIAL major event)
Location Axis NORTH SHAFT TBM COMPLETION
(distance units or 90+00
PUNCH LIST
from Point A to
Point B over time)
50+00
Location 2 Location 2
Block Activity
Location 1 Location 1
Start Date
Date
Start Date Finish Date
Bar Activity Milestone
Location Location
Better Answer:
We usually assign one color to each major type of
work (similar to layers in a CADD drawing). This makes
it easy to see how your crews and equipment will
move through the project over time. or
Or, when illustrating a large program with multiple
contracts, we often assign one color to each contract.
This helps everyone see how all of the contracts work
together to complete the program. It also highlights
the interfaces (i.e. touch points) that will require
coordination to make sure everything goes smoothly.
Color is a good thing. Be creative, and don’t hold back!
17
2017
2017
Q2 Q2
Q3 X = Location Q3
Q4 Q4
Q1 Q1
2018
2018
Q2 Q2
Q3 Q3
Q4 Q4
Q1 Y = Time Q1
2019
2019
Q2 Q2
Q3 Q3
Q4 Q4
19
2017
2017
Q2 PREP SITE Q2
Q3 CONSTRUCT PREP SITE Q3
Q4 SOUTH SHAFT Q4
Q1 ASSEMBLE TBM CONSTRUCT Q1
NORTH SHAFT
2018
2018
Q2 Q2
Q3 Q3
Q4 Q4
Q1 Q1
2019
2019
Q2 RETRIEVE TBM Q2
Q3 PUNCH LIST Q3
Q4 SUBSTANTIAL COMPLETION Q4
20
BORED TUNNEL
SOUTH NORTH
SHAFT SHAFT
10+00 30+00 50+00 70+00 90+00 110+00
Timescale Q1 Q1
2017
2017
Q2 PREP SITE Q2
Q3 CONSTRUCT PREP SITE Q3
Q4 SOUTH SHAFT Q4
Bar Activity
Q1 ASSEMBLE TBM CONSTRUCT Q1
NORTH SHAFT
2018
2018
Q2 Q2
Q3 Q3
Q4 Q4 Linear Activity
Block Activity
Q1 Q1
2019
2019
Q2 RETRIEVE TBM Q2
Q3 PUNCH LIST Q3
Q4 SUBSTANTIAL COMPLETION Q4
vs.
Time on Vertical Axis:
Also called a Time-Chainage Diagram
✓ Keeps the drawing horizontal (the way we normally read
plan & profile drawings)
✓ Can illustrate the sequence in the same direction that the
work is constructed (i.e. top-down or bottom-up)
22
People that have never seen a linear schedule before usually find it
easiest to read time from left to right. When meeting with executives,
third party stakeholders or the Mayor, you need to bring them up to
speed quick. So we plot time from left to right whenever possible.
2 Example Projects
24
GIRDERS DECK
PIER A
PIER B
25
Page Setup:
2018
2018
Mar Mar
Feb Feb
Jan Jan
Dec Y = Time Dec
Nov Nov
2017
2017
Oct Oct
Sep Sep
26
Linear Schedule:
2018
2018
GROUT/CURE/POST-TENSION
Mar Mar
PRECAST GIRDERS
Feb SPAN 3 Feb
PRECAST GIRDERS CONCRETE
Jan SPAN 2 ABUTMENT
Jan
PRECAST GIRDERS
Dec SPAN 1 CONCRETE PIER Dec
CONCRETE
Nov Nov
2017
2017
Oct Oct
DRILLED SHAFTS
Sep (TYP) Sep
27
Streetcar Project:
2018 2019
A M J J A S O N D J F M A M J J
130+00 Maintenance Facility
120+00
RAILCAR PLACE INTO
110+00 DELIVERY OPERATION
100+00
PRE-REVENUE TESTING
80+00
70+00 PLATFORM (TYP.)
60+00
50+00
40+00
30+00
20+00 TPSS
10+00
0+00
28
Industry Perspectives:
“The intuitive format of a linear schedule helps us transform detailed
CPM schedules from overwhelming to understanding.”
-Brian Ellingson, Schedule Engineering Supervisor at Sound Transit
“Our linear schedule was extremely helpful on the floating bridge project.
We used it to manage the job and communicate with the public.”
-Walter Tarr, Principal at Polaris Project Controls
29
Jul Jul
Jun Jun
May May
2017
2017
Apr Apr
ENVIRONMENTAL SHUTDOWN
WINDOW (NO WORK)
Mar Mar
Feb Feb
Jan Jan
32
Transmission
Foundation
2017 2018
Tower #
Type
Line Project:
SUBSTATION Sep Oct Nov Dec Jan Feb Mar Apr
14 T DS
13 T DS
12 T DS
11 T DS
10 T DS
9 T DS
8 T DS
7 T DS
6 L HP
5 L HP
4 L HP
3 L HP
2 L HP
1 L HP
WIND FARM
33
70+00
BORED TUNNEL
PUNCH LIST
50+00
SOUTH SHAFT
38
30-Nov-18 50+07
31-Dec-18 50+07
50+00 Breakdown 31-Jan-19 63+87
28-Feb-19 76+03
31-Mar-19 76+03
30+00
ASSEMBLE 30-Apr-19 76+03
CONSTRUCT TBM
PREP SITE SOUTH SHAFT 31-May-19 94+46
10+00 Launch/Learning Curve
30-Jun-19 110+00
SOUTH SHAFT
39
PUNCH LIST
Remaining Work
50+00
30+00
ASSEMBLE
Overlay Actual CONSTRUCT TBM
Progress To-Date 10+00
PREP SITE SOUTH SHAFT
ACTUAL PLANNED
SOUTH SHAFT
40
70+00
PUNCH LIST
50+00
30+00
ASSEMBLE
CONSTRUCT TBM
PREP SITE SOUTH SHAFT
10+00
SOUTH SHAFT
41
2017
2017
Apr Apr
ENVIRONMENTAL SHUTDOWN
WINDOW (NO WORK)
Mar Mar
Feb Feb
Jan Jan
42
A Simple-Yet-Powerful Tool:
“From a risk management perspective, I find great value in using linear schedules to compare
complex base (deterministic) schedules and risk-based (probabilistic) schedules. This helps identify
the “trouble” activities where uncertainty is the highest. Overlaying the two schedules is a simple,
quick, and effective way to help project managers focus their attention and manage their resources.”
-Norman Perez, Senior Engineer at Schnabel Engineering
There are a few products out there. Some are extremely powerful
and sophisticated, and can practically cook you breakfast if you can
get past the steep learning curve.
Step 2: share this guide with your project team, your network, and
your boss. (Bosses love 1-page linear schedules because they can
show it to their boss too…)
Step 3: start sketching up a linear schedule for your own project and
let us know if you need any help along the way.
46
About GraphicSchedule:
We’re a small startup with a big mission: to help
teams communicate their schedules more effectively
and deliver winning projects.
We got tired of drawing linear schedules by hand so
we developed an Excel app that makes it easy.
Visit our website: GraphicSchedule.com
Read our origin story
Get in touch: james@graphicschedule.com