Provisional Certificate

1. Highway Engineering Consultant, acting as Authority’s Engineer, under and in accordance with
the (Agreement S.E’s LS AB No .33/2016-17) dated: 29.08.2016 (the “Agreement”). For
construction of the “Four Laning from KM 4/8 To KM 24/6 of Nizamabad-Jagadalpur Section of
NH-63 (OLD NH-16) in the state of Telangana under NH (O) on EPC Mode. (The “Project
Highway”) in the state of Telangana on EPC Mode under Corridor Approach Contract through
M/S.Qingdao Construction Engg. Co. Ltd, hereby certify that the Tests in accordance with Article
12 of the Agreement have been undertaken to determine compliance of the Project Highway
with the Provisions of the Agreement.

Certified Chainages for


Sl. No Completion Side Length (Mts)
From To
1 4800 6700 LHS 1900
2 7930 10090 LHS 2160
3 11110 14500 LHS 3390
4 15100 16750 LHS 1650
5 17055 17230 LHS 175
6 17650 19700 LHS 2050
7 21500 24600 LHS 3100

1 4800 6700 RHS 1900


2 7930 10120 RHS 2190
3 11110 14500 RHS 3390
4 15100 16030 RHS 930
5 16120 16760 RHS 640
6 17084 17230 RHS 140
7 17650 19700 RHS 2050
8 21510 24600 RHS 3090
Total Length : 28755 (Mts)
Or Say : : 14.377 (Kms)

2. Construction Works that are incomplete on account of Time Extension have been specified in
the Punch List appended hereto, and the Contractor has agreed and accepted that it shall
complete all such works in the time and manner set forth in the Agreement. In addition, certain
minor works are incomplete and these are not likely to cause material inconvenience to the
users of the Project Highway or other their safety. The Contractor has agreed and accepted that
as a condition of this Provisional Certificate, it shall complete such minor works within 30 (thirty)
days hereof. These minor works have also been specified in the aforesaid punch list.
3. In view of the foregoing, I am satisfied that that Project Highway can be safety and reliably
placed in service of the users thereof, and in terms of the Agreement, the Project Highway is
hereby Provisionally declared fit for entry into operation on this the Third (03rd )day of October
2018.