SAP Activate Implementation Methodology

Final Cutover Checklist


INTERNAL
TABLE OF CONTENTS
INTRODUCTION 3
TECHNICAL – INFRASTRUCTURE ACCEPTANCE CRITERIA 3
FUNCTIONAL – FUNCTIONAL SYSTEM DESIGN ACCEPTANCE CRITERIA 3
DEVELOPMENT – DEVELOPMENT SYSTEM DESIGN ACCEPTANCE CRITERIA 4
AUTHORIZATIONS – SYSTEM SECURITY ACCEPTANCE CRITERIA 4
DATA CLEANSING – DATA CLEANSING ACCEPTANCE CRITERIA 5
DATA CONVERSION – DATA CONVERSION ACCEPTANCE CRITERIA 5
TRAINING – TRAINING ACCEPTANCE CRITERIA 5
ORGANIZATIONAL READINESS – ORGANIZATIONAL READINESS ACCEPTANCE CRITERIA 6
Project Management – Deployment Acceptance Criteria 6

2
INTRODUCTION
The Final Cutover Checklist reviews points of readiness, and provides the basis for approval to proceed with
the cutover. It is intended to capture all of the signatures that are needed in order to approve the
organization to go live with the new system.

The Final Cutover Checklist contains the acceptance and approval criteria for each key area that has been
identified as part of the overall Migration process. The items listed should be checked and completed by the
“AIM Company “organization in order to successfully go live. This document complements the Cutover
Checklist. The Cutover Checklist details all of the activities, dependencies, dates, times, resources and
status’ in depth related to the entire cutover process. This checklist serves as an additional validation list for
approving all of the work completed as part of the overall deployment.

The following key areas have been defined:

Technical (Infrastructure)
Functional (System Design)
Development (System Design)
Authorizations (System Security)
Data Cleansing
Data Conversion
Training
Organization (Readiness)
Project Management, (Deployment)

TECHNICAL – INFRASTRUCTURE ACCEPTANCE CRITERIA


The acceptance criteria for the hardware infrastructure, system performance and SAP BASIS functions
for the SAP technical environment are as follows:

Acceptance Criteria
1. Volume and stress tests have been completed and results are successful;
2. The SAP landscape is consistent with SAP Support Pack levels;
3. Cutover test runs (min. of 3 cycles) have been completed and results documented;
4. Infrastructure system & connectivity testing are complete
5.

Authority Name Signature Date


Technical PM First Last

FUNCTIONAL – FUNCTIONAL SYSTEM DESIGN ACCEPTANCE CRITERIA


The acceptance criteria for the functional SAP HR system are as follows:

Acceptance Criteria
1. Configuration work is complete and meets requirements as defined;
2. Integration/Regression testing is complete and results successful;

3
3. Customer Acceptance Testing, (CAT) is complete and results successful.

Authority Name Signature Date


Functional PM First Last

DEVELOPMENT – DEVELOPMENT SYSTEM DESIGN ACCEPTANCE CRITERIA


The acceptance criteria for development for the SAP system are as follows:

Acceptance Criteria
1. SAP Development work is complete and meets requirements as defined;
2. Bid Management Development work is complete and meets requirements as defined;
3. Payroll interface is complete and meets requirements as defined;
4. Interface testing is complete and results successful;
5. SAP Development testing is complete and results successful;
6. AIM Development work is complete and meets requirements as defined;
7. AIM Regression testing is complete and results successful.
8.

Authority Name Signature Date


Technical Project First Last
Lead

AUTHORIZATIONS – SYSTEM SECURITY ACCEPTANCE CRITERIA


The acceptance criteria for authorizations for the SAP HR system are as follows:

Acceptance Criteria
1. User accounts are established and meet requirements as defined;
2. User account testing is complete and results successful;
3.

Authority Name Signature Date


HCM Program First Last
Manager
Portfolio Program First Last
Manager

4
DATA CLEANSING – DATA CLEANSING ACCEPTANCE CRITERIA
The acceptance criteria for data cleansing for the SAP HR system are as follows:

Acceptance Criteria
1. Employee Master Data to be converted is clean, accurate and has been validated;
2. Organizational Structure data to be converted is clean, accurate and has been
validated;
3. Position/Job Slot data to be converted is clean, accurate and has been validated;
4. Job Bid Management data to be converted is clean, accurate and has been validated;
5. Qualifications data to be converted is clean, accurate and has been validated.

Authority Name Signature Date


ERP Integration First Last
PM

DATA CONVERSION – DATA CONVERSION ACCEPTANCE CRITERIA


The acceptance criteria for data conversion for the SAP HR system are as follows:

Acceptance Criteria
1. Data conversion programs are complete and meet requirements as defined;
2. Data conversion program testing is complete and results successful;
3. Data conversion process is defined, sequenced, timed, tested and documented for final
cutover.

Authority Name Signature Date


Technical Project First Last
Lead

TRAINING – TRAINING ACCEPTANCE CRITERIA


The acceptance criteria for the planning, design, development and delivery of all training courses for the
SAP HR system are as follows:

Acceptance Criteria
1. End user training materials are complete and meet requirements as defined;
2. Work instructions are complete and meet requirements as defined;
3. Initial end-users have been identified and trained.

Authority Name Signature Date

5
Training Lead First Last

ORGANIZATIONAL READINESS – ORGANIZATIONAL READINESS ACCEPTANCE CRITERIA


The acceptance criteria for the organizational readiness and overall Business Process Implementation
planning, and delivery applicable to the SAP HR system is as follows:

Acceptance Criteria
1. Change Management activities complete for areas affected by transition.

Authority Name Signature Date


Change First Last
Management PM

PROJECT MANAGEMENT – DEPLOYMENT ACCEPTANCE CRITERIA


The acceptance criteria for the overall structure of acceptance for all of the above areas, and the overall
management of issues and risks associated with the cutover process applicable to the SAP HR system
are as follows:

Acceptance Criteria
1. Designated management identified and available for immediate decision making;
2. Signoff on items listed above has been obtained.
3.

Authority Name Signature Date


HCE Program First Last
Manager
Portfolio Program First Last
Manager

6
www.sap.com/contactsap

© 2018 SAP SE or an SAP affiliate company. All rights reserved.


No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP SE or an SAP affiliate company.

The information contained herein may be changed without prior notice. Some software products marketed by SAP SE and its distributors contain proprietary software components of other software vendors.
National product specifications may vary.

These materials are provided by SAP SE or an SAP affiliate company for informational purposes only, without representation or warranty of any kind, and SAP or its affiliated companies shall not be liable for errors
or omissions with respect to the materials. The only warranties for SAP or SAP affiliate company products and services are those that are set forth in the express warranty statements accompanying such products
and services, if any. Nothing herein should be construed as constituting an additional warranty.

In particular, SAP SE or its affiliated companies have no obligation to pursue any course of business outlined in this document or any related presentation, or to develop or release any functionality mentioned
therein. This document, or any related presentation, and SAP SE’s or its affiliated companies’ strategy and possible future developments, products, and/or platform directions and functionality are all subject to
change and may be changed by SAP SE or its affiliated companies at any time for any reason without notice. The information in this document is not a commitment, promise, or legal obligation to deliver any
material, code, or functionality. All forward-looking statements are subject to various risks and uncertainties that could cause actual results to differ materially from expectations. Readers are cautioned not to place
undue reliance on these forward-looking statements, and they should not be relied upon in making purchasing decisions.

SAP and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP SE (or an SAP affiliate company) in Germany and other countries. All