TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 1 of 12
TABLE OF CONTENTS
1. REVISION RECORD ........................................................................................................................................ 3
2. PURPOSE ........................................................................................................................................................ 4
3. SCOPE OF WORKS ........................................................................................................................................ 4
4. SEQUENCE...................................................................................................................................................... 4
4.1. For wet area (bath room, Kitchen etc.)..................................................................................................... 4
4.2. For Dry areas (Bed rooms, living rooms, corridors, lift lobby etc.)....................................................... 4
5. REFERENCES ................................................................................................................................................. 4
5.1. Contract documents .................................................................................................................................. 4
5.2. Contractors Submittal ............................................................................................................................... 5
6. DEFINITIONS / ABBREVIATIONS .................................................................................................................. 5
6.1. Definition .................................................................................................................................................... 5
6.2. Abbreviations ............................................................................................................................................. 5
7. RESPONSIBILITIES ........................................................................................................................................ 6
7.1. Project Manager ......................................................................................................................................... 6
7.2. Construction Manager ............................................................................................................................... 6
7.3. Project Engineer ........................................................................................................................................ 7
7.4. QA/QC Engineer / Inspector ...................................................................................................................... 7
7.5. Surveyor ..................................................................................................................................................... 7
7.6. Foremen/ Works Supervisor ..................................................................................................................... 7
8. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS ..................................................................................... 8
8.1. List of Equipment’s/Tools ......................................................................................................................... 8
8.2. List of Manpower ....................................................................................................................................... 8
8.3. List of Materials.......................................................................................................................................... 8
9. PROCEDURE ................................................................................................................................................... 8
9.1. Approvals ................................................................................................................................................... 8
9.2. Material Delivery, Storage and Handling ................................................................................................. 8
9.3. Completion of MEP Works ........................................................................................................................ 9
9.4. Setting Out.................................................................................................................................................. 9
9.5. Tile adhesive for wall ................................................................................................................................. 9
9.6. Wall tiles installation (wet areas) .............................................................................................................. 9
9.7. Floor tiling ................................................................................................................................................ 10
9.8. Skirting...................................................................................................................................................... 11
9.9. Grouting .................................................................................................................................................... 11
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 3 of 12
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
Signature field
Revision
Revision
Number
Date
2-Oct-13 Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer coordinator contractor
Approved
By Project
Manager
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 4 of 12
2. PURPOSE
The purpose of this Method Statement is to define the procedure of the installation of ceramic walls,
floors, skirting, up stands, etc. at locations shown on the drawing and schedules in according with the
requirements specified in the relevant specifications, procedures and drawings, considering safety and
quality of the work activities.
3. SCOPE OF WORKS
This method statement provides the control sequence of construction and methodology that will be used
for preparation, installation, grouting, cleaning and protection of all floors and walls tiling works in overall
project site.
4. SEQUENCE
4.1. For wet area (bath room, Kitchen etc.)
1. Plaster works
2. High level MEP works and installation water supply pipes
3. MEP clearance for wall ceramic tiles
4. Wall ceramic works ( Excluding bottom 1st row )
5. Grouting wall tiles
6. False ceiling works
7. Wet area water proofing works
8. Floor ceramic works and bottom 1st row ( excluding the tile next to floor traps)
9. Grouting floor tiles and the remainder of wall tiles
10. Installation of floor traps covers
11. Installation of tiles next to floor traps
4.2. For Dry areas (Bed rooms, living rooms, corridors, lift lobby etc.)
1. Plaster works
2. High level MEP works and installation water supply pipes
3. MEP clearance for wall ceramic tiles
4. Wall ceramic works ( Excluding bottom 1st row
5. False ceiling works
6. Wet area water proofing works
7. Floor ceramic works and bottom 1st row ( excluding the tile next to floor traps)
8. Installation of floor traps covers
9. Installation of tiles next to floor traps
5. REFERENCES
5.1. Contract documents
1. Project Specification :- Division 9, Section 093000
2. Contract Drawings :-
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 5 of 12
Sr.
Description Material Sub. No. Rev No. Date Remarks
No.
1 Cement
2 Sand
3 Tile Grout (COLORGROUT
4 Cement Based Tile Adhesive
5 Wall Tiles
6 Floor tiles
Sr.
Description Shop Dwg. No. Rev No. Date Remarks
No.
1
2
6. DEFINITIONS / ABBREVIATIONS
6.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
6.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 6 of 12
7. RESPONSIBILITIES
7.1. Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with company policies and in
accordance with the requirements of this Quality Plan.
2. Ensuring that full compliance of subcontractors with Company Quality policies and with the
requirements of this method statement.
3. To ensure that the equipment required to execute the works according to the construction
programmer are available, in good condition, and mobilize any additional equipment that might be
required.
4. To co-ordinate with the construction Manager, Project Engineer, Safety Engineer, Foreman and
Surveyor for a safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
7.5. Surveyor
1. To establish benchmark form agreed reference points, provide required setting out, level marking, and
follow up with regular checks.
2. Co-ordinate with Project Engineer / Foreman and ensure the approved shop drawings/ constructions
drawings will be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the Project
Manager of any deviation from the drawings.
9. PROCEDURE
9.1. Approvals
1. A mock up shall be made for the Consultant’s approval. The mock up shall cover approximately six sq.
Mtr. Once the mock up is approved, it shall be incorporated into the works but all rejected mock ups
shall be removed. The quality of all subsequent tiling works shall match the approved mock up.
2. All shop drawings and materials must be approved before tiling work activities take place.
shall be rejected/ returned. A Material Inspection Request (MIR) shall be raised for Consultant’s
information. All materials stored on site shall be protected against the inclusion of foreign matter,
water and other damages at all times.
4. Before beginning with tiling, Waterproofing of wet area shall do, tested and protected in accordance
with the project specifications and approved by the Engineer.
5. The tile adhesive material will be applied in areas of approximately 1 M2 and will be combed by the
solid bed trowel.
6. Rib the surface of the adhesive bed in one direction by using notched trowel.
7. The tiles will be placed with pressing and twisting/sliding motion to ensure good contact with the
adhesive with a uniform thickness of 3-6 mm.
8. Before adhesive material sets, within 15 minutes after installation, necessary adjustments will be
made to give true, regular appearance of tiles and joints.
9. All awareness will be given to avoid colour/shade variations. The tiles will be selected based on batch
numbers.
10. Plastic spacers will be used to maintain the proper joint width and alignment.
11. Joints will be true to line, continuous and without steps.
12. Joints on walls will be truly horizontal, vertical and in alignment.
13. Joint widths and colour of grout will be subjected to Client selection through mock-up which will be
prepared by the contractor.
14. Any extra adhesive material from the face of tiles will be removed with a damp cloth before it sets.
15. No tiles will be fixed in location of fixed fixtures like mixers, bib cocks, angle valves. These tiles will be
fixed once fixtures have been positioned in its final position. Tiles will fit closely and neatly around all
plumbing fixtures and around electrical outlets, pipes, fittings etc. so that cover plates or escutcheon
will overlap the tiles properly.
9.8. Skirting
1. The procedure of fixing the skirting is the same as wall tile except that the sequence of fixing skirting
is after completion of the floor tiles
2. For tile skirting’s, the joint’s will match and align with joints in floor tiles if the length of the skirting is
same as the floor tile.
9.9. Grouting
1. Prior to grouting, the contractor will submit RFIA to the consultant for the approval of installation of
ceramic tiles.
2. Grouting will commence only after the tile adhesive has set firmly which requires 24 hrs after the tile
installation.
3. For wet area before proceeding with the grouting check if the required slope for the flooring has been
achieved towards to floor trap and no dead spots remain in the flooring with regards to slope.
4. The colour of the grout will be as per the material approval and the mock-up approval.
5. All plastic spacers will be removed before grouting.
6. The joints will be 6 mm deep and are free from dust and debris.
7. Grout of approved colour will be used based on approval of mock up.
8. Mixing of the tile grout material, LANKO COLORGROUT, will be carefully done as per manufacturer
instructions,
9. Grout not used within the one half hour time of mixing will be disposed from the site and do not re-
temper grout.
10. Grout will be forced to fill the joints by using a flat edge stainless still scraper and completely to its
entire depth.
11. Excess grout on the surface of the tile will be removed using dry cloth or sponge.
12. For uniform cured grout joints, the floor will be allowed to cure (air cure) for 72 hours. Floor will be
protected from traffic and other contaminants by using polyethylene sheets cover or “NO ACESS”
signs.
9.10. Cleaning
1. Any grout spread over the tile will be removed by using a Scotch pad.
2. Upon completion of the work, all debris, equipments and excess materials resulting from the work
will be removed.
9.11. Protection
1. The finished area will be closed to traffic completely until mortar has set usually a complete period of
24 hours
2. The cleaned tiles will be covered by protection carton paper (2 mm thick) or polyethylene to protect
from traffic and stain until building is complete.
9.12. Inspection
1. The contractor will submit RFIA to the consultant for the final acceptance of the ceramic tiles.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-093000-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for ceramic tile works-Wall & Floor
Pages 12 of 12