Project Status

New South Glasgow Hospital


Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

Introduction:

Detailed design of 'walking' / 'raked' columns. Calculations include:

1. Assesment of 'strut and tie' forces based on column geometry and gravity loading.
2. Concrete compressive strut check and reinforcement as required.
3. Tie forces local to walking column within the slab above and below. Reinforcment requirements.
4. Vertical shear check. S concrete.
5. Horizontal shear check at slab interface.
6. Assessment of secondary moments to columns above and below walking column.
7. Reinforcement Summary.

Diagram:

Geometry
Column Walk Width Head Level Base Level Walk Angle, 1 Fcu_Walk
Reference mm Lvl (ref) Lvl (m) Lvl (ref) Lvl (m) (m) Deg. N/mm2
E146 300 2 18.45 1 13.95 2.95 57 55
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

1 - Loading:

Please refer to gravity load takedown information in section 1.2. A hand load takedown and a Ram C load takedown has been
carried out with the most conservative results adopted.

SLS Load Combination = 1.0 DL + 1.0 LL


ULS Load Combination = 1.4 DL + 1.6 LL

Loading Hand LTD Loading RAMC LTD Vertical Loading Load in Raked Column - F Strut

Dead Imposed Dead Imposed SLS ULS Dead Imposed ULS


kN kN kN kN kN kN DL/SIN 1, kN DL/SIN 1, kN kN
3208 1335 3215 1138 4550 6637 3844 1596 7936

Lateral Load to Diaphragm (kN) - Tie Force - F tie

Dead Imposed Total SLS Total ULS


DL/TAN 1, kN LL/TAN 1, kN kN kN
2108 875 2983 4351

2 - Compression Strut Capacity:

The 'virtual' compression strut width will be calculated based on reasonable geometry over which stress can be assumed to distribute. In
order to allow distribution of stress from wall to column below a downstand is to be included.

Column Width (mm) Downstand (mm) dd 2 3 Strut Width bs Concrete Cap(kN) Fc Asreq As Prov

Above Below Calculated Selected deg. deg. (mm) (mm2) (mm2)


b1 b2 b2.tan 1 user tan-1(dd/b2) 180- 1 2 b2/cos 2.sin 3 0.4fcu wall.bs.Walk Width (Fstrut-Fc)/0.87fy user
600 400 610 850 65 58 801 5944 4579 4910
10-H25

3 - Tension 'Tie' Capacity

Column depth (mm) Asreq As Prov Beam Above Dims (mm) Beam Below Dims (mm)
Above Below (mm2) (mm2) Width Depth Width Depth
h1 h2 Ftie/0.87fy user
600 900 10002 11260 600 850 900 850
14-H32

Distribution of the lateral forces imparted to the slab diaphrgm are to be considered in the slab analysis. An additional mat of reinforcement
local to the walking column is envisaged. The slab designer should be advised of the applied loads or a hand calculation/mark up provided
showing additional rebar requirements.
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

4 - Vertical Shear Check


Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

5 - Horizontal Shear Check


Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

6 - Secondary Moments to Columns

The columns at levels above and below are fixed by a continuous monolithic connection to the walking column. To assess secondary moments
arising in the columns above and below the walk a 2d s-frame model has been adopted in accordance with TRM 261. The main factor
influencing the rotation of the walking column, and therefore moments to columns is the elongation of the slab strut and tie. The walking
column itself is a very stiff element and as such deformation of the panel itself contributes to a lesser extent.

The virtual strut within the wall panel has been modelled as a beam element based on the dimensions determined in section 2. This is
deemed to be conservative as an increased rotation is expected at the joints in comparison to if the full rigidity of the wall panel were
modelled.

The section dimensions of the slab struts and ties and the representative lengths back to the supports have been assesed on a column by
column basis. Assuptions are conservative in this regard as it is difficult to approximate the true behaviour of the floor plate in a 2d model.
Typically a half bay width of 3750mm has been considered of length equal to 'distance to closest point of support' i.e. core walls or Full Slab
Diaphragm.

These moments are to be considered in addition to Ram Concept Slab Moments

S-Frame Member Properties

Member Dims Stress pt 2


I (mm4) A (mm2)
Element Description b (mm) d (mm) Stress pt 1 (mm) (mm)
Col L01 900 400 4.80E+09 360000 200 -200
Col L02 0.00E+00 0 0 0
Col L03 600 600 1.08E+10 360000 300 -300
Col L04 400 900 2.43E+10 360000 450 -450
Col L05 600 600 1.08E+10 360000 300 -300
Col L06 0.00E+00 0 0 0
Col L07 0.00E+00 0 0 0
Col L08 0.00E+00 0 0 0
Virtual Strut 300 801 1.28E+10 240161.565 400.2692757 -400.269
Slab Strut/Tie 3750 300 8.44E+09 1125000 150 -150

Strut Dimensions

Column E146 is located in close vicinity to core C. A minimum strut length of 5.2m has been adopted in the assessment.
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

S-Frame Model Geometry S-Frame Member Properties


Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

S-Frame - Applied Loads/Axial Strut-Tie Loads


Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

S-Frame Column Moments

Column Moments
Head Base
(kNm) (kNm)
L08
L07
L06
L05
L04
L03 20 65
L02 65 202
L01 WC WC
L00 140 90

Column moments considered negligable L04


and above.

These moments are to be considered in


addition to Ram Concept Slab Moments
Project Status
New South Glasgow Hospital
Design
Date 10/11/2011 Job no. Section Sheet no. Rev
By GJ
24140333 5.1 1
Checked
Rev Date Details Tel 44 (0)141 429 3555
Fax 44 (0)141 429 3666
Part
ZE - Walking Column E146

7 - Reinforcement Summary

Raked Compression Strut Reinforcement = 10-H25 Split Half FF + Half NF

Tension Tie Reinforcement = 14-H32 Total per Douwnstand Beam

Horizontal Wall Reinforcement = H20 - 200 CRS NF1 + FF1

Vertical Wall Reinforcement = H20 - 200 CRS NF2 + FF2

Downstand Beam Above Dimensions = 600mm Wide by 850mm Deep from SSL

Downstand Beam Below Dimensions = 900mm Wide by 850mm Deep from SSL