STEEL PIPELINE LAYING STATUS (PROJECT-WISE) - FY 2019-20

Category FY 2019-20
S.No. Project Name Contractor Zone Size FY 2018-19
(Shifting/Project) April May June July Aug Sep Oct Nov Dec Jan Feb Mar
4" 8 272.00 — — — — —
1 AJAY RO Likhitha Project East
8" 0 — — — — — —
4" 0 — — — — — —
2 IFC-4 Sopan Project East
8" 0 — — — — — —
4" 0 — — — — — —
3 IFC-5 Sopan Project East
8" 0 — — — — — —
4" 0 — — — — — —
4 DHAULA KUAN TO MARUTI Bucon Project West 8" 0 — — — — — —
12" 4064.87 629.00 159.00 288.00 32.00 83.44 119.052
4" 0 — — — — — —
5 PATEL NAGAR TO BANSAL RO Likhitha Project West
8" 404 108.00 — 150.00 97.70 — —
4" 0 25.13 — — — — —
6 TULI MOTORS Sopan Project West
8" 0 — — — — — —
4" 0 — — — — — —
7 AJIT MOTORS Sopan Project West
8" 0 — — — — 300.00 587.00
4" 0 — — 685.97 300.21 1.5 —
8 NSG HQ FRS Sopan RO West
8" 0 — — — — — —
4" 0 — — 90.20 — — —
9 SHIV SS Likhitha Project West
8" 0 — — — — — —
4" 40 — 267.00 — — — —
10 AMAR SHAHEED SUDESH Likhitha Project North
8" 0 — — — — — —
4" 0 — — — — — —
11 NALAH CROSSING AT BURARI MDPE Likhitha Project North
8" 0 — — — 375.00 — —
CONNECTIVITY OF SHRI SAI R.O & 4" 3997.8 — — 430.00 1784.00 1492.00 —
12 Likhitha Project North
MAHADEV PP KANJHAWALA 8" 0 — — — — — —
4" 0 — — — — 422.00 —
13 DAWAR PART-1 Likhitha Project North
8" 0 — — — — — —
4" 0 — — — — 1505.50 224.20
14 DAWAR PART-2 Sopan Project North
8" 0 — — — — — —
4" 0 — — — — 47.20 10.00
15 DTC BAWANA SECTOR 5 Likhitha Project North
8" 0 — — — — — —
CHANDGIRAM AKHARA TO DHEERPUR
15 NOPS Project North 12" 0 584.00 270.96 384.00 491.00 — —
(SEG-03)
16 SINGHU BORDER TO ALIPUR NH-1 Advance Project North 8" 6675.8 — — — — — 9
17 PITAMPURA METRO STN PARKING G.L. Golden Shifting North 12" 0 — — 94.00 8.00 — —
4" 0 — — — — — —
18 R.K. PURAM Sopan Project South
8" 354 — — 31.00 — — —
4" 0 — — — — — —
19 VASANT VIHAR TO NELSON MANDELA Bucon Project South
8" 0 — — 894.00 55.00 — —
South 4" 0 — — — — — 117.00
20 DFL FRS Likhitha Shifting
South 8" 0 — — — — — —
4" 0 — — — — — —
6" 0 — — — — — —
21 DESU TO LAL QUILA (SEGMENT-1) Sopan Project Central
8" 0 — — — — — —
12" 1182 — 381.00 177.00 577.00 105.00 276
4" 0 — — — — — —
6" 0 — — — — — —
22 IP ESTATE TO DHAULA KUAN M.P. Engineering Project Central
8" 0 — — — — — —
12" 5339.01 180.00 300.48 — — — 4.55
4" 776.2 — — — — — —
23 ANAND PARVAT CNG Likhitha Project Central
8" 0 — — — — — —
8" 0 — — — — — —
23 T-TERMINAL DESU PILOTLINE Likhitha Project Central
12" 0 — — — — — 70
4" 0 — — — — — —
24 UDHYAN MARG Sopan Project Central
8" 0 — — — — — —
8" 0 — — — — — —
25 SAKATPUR TO SOHNA ROAD (SEG-01) Sumit Gas Project Gurugram
12" 4517.64 — — — — — 366.19
MANESAR TOLL TO RAJEEV CHOWK 8" 0 — — — — — —
26 Sumit Gas Project Gurugram
(SEG-3) 12" 5867.52 261.61 241.23 745.20 653.76 546.12 201.22
RAJEEV CHOWK TO BADSHAHPUR (SEG- 8" 0 — — — — — —
27 G.L. Golden Project Gurugram
2) 12" 0 — — — — — 2415
8" 3200.51 84.82 181.14 — — — 134
28 MANESAR TOLL TO KMP (SEG-4) 8" G.L. Golden Project Gurugram
12" 357 54.00 — 629.00 899.00 2426.53 1590
4" 4508.22 4.00 — — — — —
29 SAKATPUR TO NH-8 Shanti Construction Project Gurugram
8" 0 — — — — — —
4" 1467.02 566.00 — — — — —
30 GMDA Shanti Construction Project Gurugram
8" 0 — — — — — —
4" 46 — — — — — —
31 F&G DODO ZI Infra Project Gurugram
8" 0 — — — — — —
4" 45 — — — — 132.00 —
32 SHUBHAM TAPARIA DODO ZI Infra Project Gurugram
8" 0 — — — — — —
4" 0 — — — — — —
SOHNA ROAD TO NH-8
33 Sumit Gas Project (Seg-1A) Gurugram 8" 0 — — — — — —
ALONG GOLF LINK ROAD
12" 5353.62 — — — — — —
4" 0 26.00 — — — — —
34 FRS CONNECTIVITY ZI Infra Project Gurugram
8" 0 — — — — — —
4" 0 — — 74.50 6.00 — —
35 BHARTI SINGH RO ZI Infra RO Gurugram
8" 0 — — — — — —
4" 0 — — — — 41.00 —
36 R.K. FILLING STATION Shanti Construction Project Rewari
8" 0 — — — — — —
4" 0 — — — — — —
37 PARADISE FILLING STATION Shanti Construction Project Rewari
8" 0 — — — — — —
4" 1763.5 — — 180.00 286.60 68.10 —
38 JSR RO CONNECTIVITY Shanti Construction Project Rewari
8" 0 — — — — — —
4" 0 — — — — — —
39 RC AUTO FUELS Shanti Construction Project Rewari
8" 0 — — — — — —
4" 0 — — — — 72.00 —
40 SUDHIR JAIN DODO G.L Golden Project Rewari
8" 0 — — — — — —
4" 0 — — — — — —
41 SHAHID SUBEDAR Shanti Construction Project Rewari
8" 0 — — — — — —
42 DHARUHERA TO REWARI Likhitha Project Karnal 12" 14609 4197.00 1084.00 206.00 — — 18.4
43 KARNAL STRETCH-1 Rich Earth Project Karnal 12" 0 — — — — — 0
44 KARNAL STRETCH-2 Sumit Gas Project Karnal 12" 0 — — — — 1082.12 2125.82
45 KARNAL STRETCH-3 Likhitha Project Karnal 12" 0 — — — — — 3957
46 KARNAL STRETCH-4 Sumit Gas Project Karnal 12" 0 — — — — — 312
47 KARNAL STRETCH-5 Siyon Project Karnal 8" 0 — — — — — —
Total 6991.56 2884.81 5058.87 5565.27 8324.51 12536.43 — — — — — —

STEEL PIPELINE LAYING STATUS (ZONE WISE)


STEEL (Km.) FY NORTH SOUTH EAST WEST CENTRAL DELHI GURGRAM REWARI KARNAL TOTAL
APRIL 584.00 — 272.00 762.13 180.00 1798.13 996.43 4197.00 — 6991.56
MAY 537.96 — — 159.00 681.48 1378.44 422.37 1084.00 — 2884.81
JUNE 908.00 925.00 — 1214.17 177.00 3224.17 1448.70 386.00 — 5058.87
JULY 2658.00 55.00 — 429.91 577.00 3719.91 1558.76 286.60 — 5565.27
AUGUST 3466.70 — — 384.94 105.00 3956.64 3104.65 181.10 1082.12 8324.51
SEPTEMBER 243.20 117.00 — 706.05 350.55 1416.80 4706.41 18.40 6394.82 12536.43
FY 2019-20
OCTOBER
NOVEMBER
DECEMBER
JANUARY
FEBRUARY
MARCH
8397.86 1097.00 272.00 3656.20 2071.03 15494.09 12237.32 6153.10 7476.94 41361.45