Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Index
1.0 Introduction
2.0 Scope
3.0 Reference
4.0 Procedure
5.0 Curing
6.0 Safety Plan
7.0 Attachments
1.0 Introduction
This document states the procedures that NSH propose to adopt and carry out the
repairing of concrete required in the concreting works such as foundations, walls,
columns, footings, pits, manholes etc. at Saudi Aramco Onshore Maintain Potential
Program-NA1A - KSA.
2.0 Scope
This method statement covers the repair of non-structural types of concrete defects. The
defects like honey combing, blow holes, peeling, blistering, tie rod holes etc. which are
not affecting the strength of structure can be rectified as per this statement. For structural
type of repairs, specific method statement and material to be adapted with approval
3.0 Reference
SAER-5803 Concrete Repair Manual
4.0 Procedure
After the removal of formwork, NSH QC personnel and PID SAUDI ARAMCO
shall thoroughly check whether any voids, honey combs, blistering, air holes, hair
line cracks etc. have appeared on the concrete surface. If found any, the repair
shall be as per the procedure mentioned below using the factory prepared
repairing materials according to manufacturer’s recommendation.
Any repair should be done only after the curing period, PMT approval and
a) The air holes, honey combs or the defects which are less than 10mm
depth (Vertically or Horizontally) can be repaired with Approved Repair
Material as per the manufacturer’s recommendation.
Remove the laitance, loose materials using appropriate tools and make
the surface rough & sound concrete without any cavity, clean the
roughened area with water and soak the surface thoroughly. Then apply
an approved bonding agent if recommended by the manufacturer and
apply Approved Repair Material with trowel/ scrapper and cure it for
required time as per manufacturer’s recommendation.
b) If the defective surface in vertical faces is more than 10mm and below
50mm Approved Repair Material shall be used as per manufacturer’s
recommendation
c) The repair thickness more than 50mm and up to 75mm vertically shall be
repaired with Approved Repair Material as per manufacturers specification/
recommendation.
For repairing defective surface more than 10mm, all loose concrete should
be removed carefully till a non-porous sound concrete surface is obtained.
To perform this hilti hammer with flat chisel or brush hammer can be used.
Also care should be taken to avoid damage to surrounding concrete
surfaces and rebar.
e) Tie rod holes will be chipped off to 75mm thickness and PVC sleeves
should remove to a depth of 75mm and use backup road before applying
Approved Repair Material extra for sealing tie rod holes.
Special care should be taken for repairing the defect where reinforcement
is exposed. It should also be cared to avoid damaging the coating of rebar,
if the coating is damaged it should be rectified before applying mortar.
The repair material, receiving inspection shall be done for review and
approval prior to use. Sample mock up shall be provided prior to start the
repairs. All repair materials shall comply with ASTM or ACI requirements.
Qualified repair crews shall repair the defects and technical support can be
obtained from supplier first time for right application.
5.0 Curing
Safety for men and material have higher priority and all safety measures should be taken
before doing any of these activities mentioned above. MSDS must be available at work
location and material storage area. Rubber glove and chemical protective PPE as per
MSDS should use for this job.
7.0 Attachments
Tool box talks shall strictly be observed before starting the work
shift to discuss the Safe Work Plan and other safety concerns for
the work.
Tool box talk shall be conducted by the site supervisor with the
safety supervisor assisting and signing the attendance sheet.
Work can only start when all the provisions in the safe work plan
are fully complied, to include all safety precautions needed.
All tool box talk attendance sheets must be turned over for
submission to HSE department.
7.1.2.2 Housekeeping
7.1.2.6 Electricity
Lighting facility (tower fights & flashing lights) for night work
are provided.