Sei sulla pagina 1di 7

NASSER S AL HAJRI CORPORATION

SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A


CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

CATEGORY METHOD STATEMENT

TITLE REPAIR OF CONCRETE

DOCUMENT REFERENCE NSH-SAOMPP-CMS-CI-005

Index

1.0 Introduction
2.0 Scope
3.0 Reference
4.0 Procedure
5.0 Curing
6.0 Safety Plan
7.0 Attachments

Copies with no seal are Uncontrolled copies. Page 1 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

0 15/02/2015 For Approval Tinu David Jacob Bobby Paul


Revision Date Description Prepared By Reviewed By Approved By
REVISION HISTORY

1.0 Introduction

This document states the procedures that NSH propose to adopt and carry out the
repairing of concrete required in the concreting works such as foundations, walls,
columns, footings, pits, manholes etc. at Saudi Aramco Onshore Maintain Potential
Program-NA1A - KSA.

2.0 Scope

This method statement covers the repair of non-structural types of concrete defects. The
defects like honey combing, blow holes, peeling, blistering, tie rod holes etc. which are
not affecting the strength of structure can be rectified as per this statement. For structural
type of repairs, specific method statement and material to be adapted with approval

3.0 Reference
SAER-5803 Concrete Repair Manual

SAES-H-003 Protective Coating for Industrial Concrete Structures

Manufacturer’s Recommendations for Repair Material

4.0 Procedure

4.1 Identify the Repair

After the removal of formwork, NSH QC personnel and PID SAUDI ARAMCO
shall thoroughly check whether any voids, honey combs, blistering, air holes, hair
line cracks etc. have appeared on the concrete surface. If found any, the repair
shall be as per the procedure mentioned below using the factory prepared
repairing materials according to manufacturer’s recommendation.

Copies with no seal are Uncontrolled copies. Page 2 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

4.2 Preparation & Repair of Concrete

Any repair should be done only after the curing period, PMT approval and

a) The air holes, honey combs or the defects which are less than 10mm
depth (Vertically or Horizontally) can be repaired with Approved Repair
Material as per the manufacturer’s recommendation.

Remove the laitance, loose materials using appropriate tools and make
the surface rough & sound concrete without any cavity, clean the
roughened area with water and soak the surface thoroughly. Then apply
an approved bonding agent if recommended by the manufacturer and
apply Approved Repair Material with trowel/ scrapper and cure it for
required time as per manufacturer’s recommendation.

b) If the defective surface in vertical faces is more than 10mm and below
50mm Approved Repair Material shall be used as per manufacturer’s
recommendation

c) The repair thickness more than 50mm and up to 75mm vertically shall be
repaired with Approved Repair Material as per manufacturers specification/
recommendation.

For repairing defective surface more than 10mm, all loose concrete should
be removed carefully till a non-porous sound concrete surface is obtained.
To perform this hilti hammer with flat chisel or brush hammer can be used.
Also care should be taken to avoid damage to surrounding concrete
surfaces and rebar.

d) If the repair thickness is beyond the reinforcement, special attention to be


given for the repair and it should be informed to the competent authority to
decide the type of repairing method to be obtained.

e) Tie rod holes will be chipped off to 75mm thickness and PVC sleeves
should remove to a depth of 75mm and use backup road before applying
Approved Repair Material extra for sealing tie rod holes.

Special care should be taken for repairing the defect where reinforcement
is exposed. It should also be cared to avoid damaging the coating of rebar,
if the coating is damaged it should be rectified before applying mortar.

Copies with no seal are Uncontrolled copies. Page 3 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

f) Hair line cracks can be repaired by cutting groove (45 degree) to a


minimum of 10 to 15mm depth on both sides of the crack. Make the
surface rough throughout the groove cut area and use Approved Repair
Material as per the recommendation of the manufacturer.

The repair material, receiving inspection shall be done for review and
approval prior to use. Sample mock up shall be provided prior to start the
repairs. All repair materials shall comply with ASTM or ACI requirements.

Qualified repair crews shall repair the defects and technical support can be
obtained from supplier first time for right application.

5.0 Curing

Curing will be done as per the manufacturer’s Instruction

6.0 Safety Plan

Safety for men and material have higher priority and all safety measures should be taken
before doing any of these activities mentioned above. MSDS must be available at work
location and material storage area. Rubber glove and chemical protective PPE as per
MSDS should use for this job.

7.0 Attachments

7.1 Safety Plan

7.2 Catalogue of repair mortar Nitomotar TC2000

7.3 Catalogue of repair mortar Masterbrace ADH2200

7.4 Catalogue of repair mortar Mastermaco N301

7.5 Catalogue of repair mortar Mastermaco S488

7.6 Catalogue of repair mortar Renderoc FC

7.7 Catalogue of repair mortar Renderoc TG

7.1 SAFETY PLAN

7.1.1 Tool Box/ Safe Work Plan

Copies with no seal are Uncontrolled copies. Page 4 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

 Tool box talks shall strictly be observed before starting the work
shift to discuss the Safe Work Plan and other safety concerns for
the work.

 Tool box talk shall be conducted by the site supervisor with the
safety supervisor assisting and signing the attendance sheet.

 Work can only start when all the provisions in the safe work plan
are fully complied, to include all safety precautions needed.

 All tool box talk attendance sheets must be turned over for
submission to HSE department.

7.1.2 General Safety Requirements

7.1.2.1 Personal Protective Equipment’s

 All personnel (workers, drivers, operators, contractor


personnel, client personnel) must wear the project
mandatory PPE (long pants, long sleeve shirt, hard hat,
safety dark glass, safety clear glass, safety shoes, high
visibility vest, hand gloves).
 Special PPE for noise, hand protection, dust pollution, etc.
shall be provided to all concerned workers/ personnel.
 All PPE must be inspected prior to use, damage PPE must
be replaced.

7.1.2.2 Housekeeping

 Unwanted materials/ supplies shall be removed from site to


ensure clear access and assigned roads for equipment
traffic.

 Proper barricading and signage shall be implemented.

 Maintain proper access and egress for workers and


equipment.

 Keep all work areas clean and free of trash.

Copies with no seal are Uncontrolled copies. Page 5 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

7.1.2.3 Work Environment

 Portable toilets provided.

 Drinking water provided in 2CHtter coolers.

 Replacement drink (juice with salt, sugar and glucose)


provided to all workers twice during morning and afternoon
to minimize impact d heat exposure.

 Rest shelters provided near the working area.

 During high wind where visibility will hamper the operation,


Construction and Safety will advise the workers on
approved action to take.

7.1.2.4 Tools and Equipment

 All tools shall be inspected color coded prior to use replace


damage tools from store.

 Electrical tools/ equipment must be properly checked color


coded before using (project standard is 110 volts supply).

 Operate the tools according to the operations manual.

7.1.2.5 Permit to Work

 All permits to work required must be valid and approved


before the start of the job.

 Permit original copies must be in the site inside the permit


box.

 All conditions provided in the permit must be compiled and


maintained form the start up to completion of the works.

 For night work, workers list shall be attached on all permits.

7.1.2.6 Electricity

 Lighting facility (tower fights & flashing lights) for night work
are provided.

 All energized equipment shall be properly grounded.

Copies with no seal are Uncontrolled copies. Page 6 of 7


NASSER S AL HAJRI CORPORATION
SAUDI ARAMCO ONSHORE MAINTAIN POTENTIAL PROGRAM- NA1A
CONTRACT # 6600033948
NSH-SAOMPP-CMS-CI-005 METHOD STATEMENT FOR REPAIR OF CONCRETE
Rev-00 Date: 15 Feb 2015

 Qualified mechanic/ electrician shall be deployed during the


operation to respond the need for lighting relocation etc.
and also to act as fire watchers.

 Panel boards or extension cords used in site shalt be


properly checked and color coded.

 To mitigate tripping hazard, power/ electrical cables shall be


either installed in between scaffold planks or elevated in
access/ egress portions.

7.1.2.7 Other Specific Safety Requirements

 MSDS: To be provided in the site. MSDS box, site clinic and


work site area.

 For medical team/facility: Provide certified nurse certified


first aider, ambulance driver, ambulance (to be parked
near the work area during night time).

 Working in pair (“buddy-system”) is strictly required


especially during night works.

 A prescribed cheek time (CT) schedule must be observed.


Check times are Intervals between working times and rest
times. Construction and Safety will check the workers
conditions before re-starting the work. For day shift check
time shall depend on the heat index level.

 Provide scaffold planks as required to walk while working


on rebars

END OF THE DOCUMENT

Copies with no seal are Uncontrolled copies. Page 7 of 7

Potrebbero piacerti anche