CRONOGRAMA DE EJECUCION DE OBRA

mes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7


15 jun '08 22 jun '08 29 jun '08 06 jul '08 13 jul '08 20 jul '08 27 jul '08 03 ago '08 10 ago '08 17 ago '08 24 ago '08 31 ago '08 07 sep '08 14 sep '08 21 sep '08 28 sep '08 05 oct '08 12 oct '08 19 oct '08 26 oct '08 02 nov '08 09 nov '08 16 nov '08 23 nov '08 30 nov '08 07 dic '08
Id Descripción Partida D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1 OBRAS PROVISIONALES
2 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40X3.60 M.

3 CASETA DE ALMACEN Y GUARDIANIA

4 MOVILIZACION Y DESMOVILIZACION DE HERRAMIENTAS Y EQUIPO

5 MANTENIMIENTO DEL TRANSITO (DESVIO DE TRANSITO)

6 COLOCACION DE CINTAS DE PRECAUCION

7 ELIMINACION DE DESMONTE EN VIA C/EQUIPO

8 CONSTRUCCION DE VEREDAS Y RAMPAS

9 TRABAJOS PRELIMINARES
10 DEMOLICION DE VEREDAS EXISTENTES EN FORMA MANUAL E=0.10 M.

11 ELIMINACION DE DESMONTE PROVENIENTE DE LAS DEMOLICIONES

12 TRAZO NIVELES Y REPLANTEO VEREDAS

13 TRAZO NIVELES Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO

14 MOVIMIENTO DE TIERRAS
15 CORTE Y EXCAVACION EN TERRENO SUELTO MANUAL (VEREDA Y SARDINEL)
16 PERFILADO Y COMPACTADO DE LA SUBRASANTE

17 BASE GRANULAR E=0.15 M.


18 OBRAS DE CONCRETO SIMPLE
19 VEREDA DE PIEDRA LAVADA F'C=175 KG/CM2 E=4" C/DETALLES EN CEMENTO
PULIDO COLOREADO

20 CEMENTO PULIDO COLOR EN MARTILLOS Y RAMPAS

21 SARDINEL SUMERGIDO: CONCRETO F'C=140 KG/CM2


22 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDAS
23 ENCOFRADO Y DESENCOFRADO NORMAL SARDINELES
24 JUNTAS DE DILATACION RELLENAS CON MEZCLA ASFALTICA E=1"
25 SOLAQUEADO DE VEREDAS
26 CURADO DE VEREDAS CON ARENA
27 VARIOS VEREDAS
28 RETIRO Y REPOSICION DE CAJA DE MEDIDORES
29 RETIRO Y REPOSICION DE CAJA DE REGISTRO
30 PINTURA ESMALTE EN BORDE DE VEREDAS
31 ASFALTADO DE BERMAS
32 TRABAJOS PRELIMINARES
33 LIMPIEZA DEL TERRENO EN FORMA MANUAL
34 DEMOLICION DE BERMAS EXISTENTES EN FORMA MANUAL
35 ELIMINACION DE DESMONTE PROVENIENTE DE LAS DEMOLICIONES
36 TRAZO NIVELES Y REPLANTEO BERMAS
37 MOVIMIENTO DE TIERRAS
38 CORTE Y EXCAVACION EN TERRENO SUELTO C/MAQUINARIA
39 PERFILADO Y COMPACTACION SUB RASANTE
40 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO
41 PAVIMENTOS
42 BASE GRANULAR E=0.25 M.
43 IMPRIMACION ASFALTICA EN FORMA MANUAL
44 CARPETA ASFALTICA EN FRIO E=11/2 "
45 JARDINERAS
46 TRAZO NIVELES Y REPLANTEO
47 EXCAVACION DE ZANJAS EN TERRENO SUELTO
48 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO
49 SUMINISTRO E INSTALACION DE JARDINERAS PRE FABRICADA HEXAGONAL

Tarea Progreso resumido Hito externo Sólo duración Progreso


Hito Tareas externas Tarea inactiva Informe de resumen manual Fecha límite
Proyecto: Cronograma
Resumen Resumen del proyecto Hito inactivo Resumen manual
Fecha: sáb 26/11/11
Tarea resumida División Resumen inactivo Sólo el comienzo
Hito resumido División resumida Tarea manual Sólo fin

Página 1