4.

1Secuencia de actividades (Diagrama de red)

ACTIVIDAD PREDECESOR TIEMPO TIEMPO MAS TIEMPO DURACIÓN


OPTIMISTA PROBABLE PESIMO
A - 3 4 5 4

B A 2 3 4 3
C A 3 5 6 9.66

D B, C 3 5 6 9.66
E D 4 5 7 5.16
F E 3 5 6 9.66
G F 2 3 4 3
H G 2 4 5 4
I E 4 5 6 5
J I 5 6 7 6
K I 7 8 10 8.16
L I 5 6 7 6
M K 5 6 7 6
N J, L 20 22 25 22.16
Ñ M, N 4 5 6 5
O Ñ 8 9 10 9
P O 6 7 8 6.66
Q P 3 4 5 4
R Q 2 3 4 3
S R 3 4 5 4
Gráfico Nro. 2: Diagrama de Red 9 13
0 3 9 13 13 18
3 5
0 3 4 13 18
3 5 E
3 I 5
A B
2 18 26.16
3 6 13,83
6 5 K 18 26.16
4 11,83
3 3 F 9.66
INICIO 3 D
C L 8.16
9 12 9.66 22.66
J
6 9 7 9 18 23
11.66 20.66
0 0 4 7 16 21
0 0 3 6 6
1 4 4 G 6 M
22.66 28.66
23 28
20.66 24.66
N 21 28 26.16 32.16
4 6 26.16 32.16
28.66 28.66
83,32 83,32 H 24.66 28.66
83,32 83,32 5
54,32 63,32 Ñ
FIN 72,32 63,32
63.32 72,32
79,32 83,32 72,32 76,32 63.32 72,32 32.16 54,32
76,32 79,32
79,32 83,32 72,32 76,32 O 22.16 32.16 54,32
76,32 79,32
4 P
S Q
R 9
6.66
3 4