Document No.

:- CIL /
CAPACIT’E INFRAPROJECT LTD.
HSE / 20
HEALTH, SAFETY & ENVIRONMENT Revision :- 00
ELCB INSPECTION REPORT Date :- 05/09/2019

OBJECTIVES
To determine the effectiveness of EARTH LEAKAGE CIRCUIT BREAKERS safety at the project
management level & ensure that all the ELCB are in safe condition.

INSPECTION PHOTOGRAPHS

Observation and findings


Location @f2
DB N0-4
Not showing proper earthing need to replace
DB N0-11
Earthing is not provided provide earthing
DB N0-16
Elcb is notworking properly
DB near tower crane no 4 –not working propely need to replace
DB N0-16
No earthing provided
Location @ f1
DB N0-9
Not showing proper earthing provide proper earthing
Location @ new labour camp
As per inspection out of 7 ELCB 3,of them are not working properly need to replace.the elcb
Document No. :- CIL /
CAPACIT’E INFRAPROJECT LTD.
HSE / 20
HEALTH, SAFETY & ENVIRONMENT Revision :- 00
ELCB INSPECTION REPORT Date :- 05/09/2019

CONCLUSION

 Most of our ELCB Is safe and ready to use for activity


 In f2 & New labour camp required extra precaution & monitering .

Prepared by verified by

Name: Name :

Sign : Sign :