Sei sulla pagina 1di 12

Construction site

issues – hazards
and control 10
smaller. The use of sub-contractors is very common at all
10.1 Introduction levels of the industry.
Over many years, the construction industry has had
The construction industry covers a wide range of activities a poor health and safety record. In 1966, there were
ranging from large-scale civil engineering projects to very 292 fatalities in the industry and by 1995 this figure had
small house extensions. The construction industry has reduced to 62 but by 2000/01 the figure had increased to
approximately 200,000 firms of whom only 12,000 employ 106. Over the last 25 years, 2,800 people have died on
more than seven people – many of these firms are much

Figure 10.1 Typical construction site.

173
Introduction to Health and Safety in Construction

construction sites. These figures include deaths of mem-


bers of the public including children playing on construc-
tion sites. Although most of these fatalities (over 70%)
were caused by falls from height, there are other signifi-
cant causes. The Health and Safety Executive (HSE) has
listed the main causes of fatalities as:

➤ falling through fragile roofs and rooflights


➤ falling from ladders, scaffolds and other workplaces
➤ being struck by excavators, forklift trucks or dumper
trucks
➤ overturning vehicles
➤ being crushed by collapsing structures.

At a conference organized by the Health and Safety Figure 10.2 Secure site access gate.
Commission in February 2001 to address the problem,
it was noted that at least two construction workers were
being killed each week. Targets were set to reduce the 10.2.1 Safe place of work
number of fatalities and major injuries by 40% over a
4-year period. All these statistics, however, ignore the Safe access to and egress from the site and the individ-
large number of ‘near miss’ incidents, such as material ual places of work on the site are fundamental to a good
falling from a height but not coming into contact with health and safety environment. This clearly requires that
an employee, a machine overturning without causing all ladders, scaffolds, gangways, stairways and passenger
injury and a trench collapse at a time when no one was hoists are safe for use. It further requires that all excava-
working in it. A proper investigation of near miss inci- tions are fenced, the site is tidy and proper arrangements
dents and the identification of the causes allow preven- are in place for the storage of materials and the disposal
tive action to be taken before an accident occurs. It also of waste. The site needs to be adequately lit and secured
signals that all failures must be taken seriously whether against intruders, particularly children, when it is unoccu-
or not they lead to injury and may yield a greater under- pied. Such security will include:
standing of deficiencies within the health and safety
management system. Studies have shown that approxi- ➤ secure and locked gates with appropriate notices
mately ten ‘near miss’ similar incidents will be followed posted
by an accident if no remedial action is taken. ➤ a secure and undamaged perimeter fence with
Due to the fragmented nature of the industry and appropriate notices posted
its accident and ill-health record, the recent construc- ➤ all ladders either stored securely or boarded across
tion industry legal framework has concentrated on haz- their rungs
ards associated with the industry, welfare issues and ➤ all excavations covered
the need for management and control at all stages of a ➤ all mobile plant immobilized, fuel removed, where
construction project. practicable, and services isolated
Finally, it is important to note that the construction ➤ secure storage of all inflammable and hazardous
site may be inside a building (refurbishment work) as substances
well as an open air site. ➤ a programme of visits to local schools to explain the
dangers present on a construction site. This has been
shown to reduce the number of child trespassers
➤ security patrols and closed circuit television – may
10.2 General hazards and controls need to be considered if unauthorized entry persists.

The Construction (Design and Management) (CDM)


Regulations deal with the main hazards likely to be 10.2.2 Protection against falls
found on a construction site. In addition to these specific
hazards, there will be the more general hazards (manual Falls from a height are the most common cause of seri-
handling, electricity, noise, etc.), which are discussed in ous injury or death in the construction industry. These
more detail in other chapters. The hazards and controls falls are normally from a height (see Chapter 8) but
identified in the CDM 2007 are as follows. may also be on the same level. It is important that trip

174
Construction site issues – hazards and control

hazards, such as building and waste materials, are not must also be fenced and suitable notices posted so that
left on-site on walkways or roadways. neither people nor vehicles fall into them.

10.2.3 Fragile roofs 10.2.7 Prevention of drowning

Roof work, particularly work on pitched roofs, is hazard- Where construction work takes place over water, steps
ous and requires a specific risk assessment and method should be taken to prevent people falling into the water
statement prior to the commencement of work. Further and rescue equipment should be available at all times.
details are given in Chapter 18.

10.2.4 Protection against falling objects

Construction workers and members of the public need


to be protected from the hazards associated with fall-
ing objects. Both groups should be protected by the use
of covered walkways or suitable netting to catch fall-
ing debris. Waste material should be brought to ground
level by the use of chutes or hoists. Waste should not
be thrown from scaffolding and only minimal quantities
of building material should be stored on working plat-
forms. The Construction (Head Protection) Regulations
virtually mandate employers to supply head protection
(hard hats) to employees whenever there is a risk of
head injury from falling objects. (Sikhs wearing turbans
are exempted from this requirement.) The employer is
also responsible for ensuring that hard hats are properly
maintained and replaced when they are damaged in any
way. Self-employed workers must supply and maintain
their own head protection. Employees must wear head
protection when so directed, take good care of it and Figure 10.3 Prevention of drowning.
report any loss or defect. Visitors to construction sites
should always be supplied with head protection and
mandatory head protection signs should be displayed
around the site. 10.2.8 Vehicles and traffic routes
Injuries due to falling materials are not limited to
All vehicles used on site should be regularly maintained
materials falling from height. Many fatalities have been
and records kept. Only trained drivers should be allowed
caused by the collapse of walls, particularly retaining
to drive vehicles and the training should be relevant to
walls, and by the collapse of excavations.
the particular vehicle (forklift truck, dumper truck, etc.).
Vehicles should be fitted with reverse warning systems.
10.2.5 Demolition HSE investigations have shown that in over 30% of
dumper truck accidents, the drivers had little experience
Demolition is one of the most hazardous construction and no training. Common forms of accident include driv-
operations and is responsible for more deaths and major ing into excavations, overturning whilst driving up steep
injuries than any other activity. The management of dem- inclines and runaway vehicles which have been left
olition work is controlled by the CDM Regulations and unattended with the engine running. Many vehicles such
requires a planning supervisor and a health and safety as mobile cranes require regular inspection and test
plan (as covered in Chapter 3). A more detailed discus- certificates.
sion of demolition is given in Chapter 20. Traffic routes and loading and storage areas need
to be well designed with enforced speed limits (a maxi-
10.2.6 Excavations mum of 10 mph is the limit on most sites), good visibil-
ity and the separation of vehicles and pedestrians being
This topic is covered in more detail in Chapter 19. considered. The use of one-way systems and separate
Excavations must be constructed so that they are safe site access gates for vehicles and pedestrians may be
environments for construction work to take place. They required. Finally, the safety of members of the public

175
Introduction to Health and Safety in Construction

must be considered particularly where vehicles cross A manual handling assessment should also be made to
public footpaths. ensure that the lifting and handling of heavy objects is
kept to a minimum. Additional health hazards may also
be present when working near water whether the water
10.2.9 Fire and other emergencies
is stagnant or not.
Emergency procedures relevant to the site should be in
place to prevent or reduce injury arising from fire, explo-
sion, flooding or structural collapse. These procedures
should include the location of fire points and assembly 10.3 Initial site assessment
points, extinguisher provision, site evacuation, contact
with the emergency services, accident reporting and Before work commences, an initial site assessment
investigation and rescue from excavations and confined should be undertaken. This assessment should not only
spaces. There also needs to be training in these proce- consider hazards associated with the site itself but also
dures at the induction of new workers and ongoing train- the hazards which may well be present during the con-
ing for all workers. struction phase.
The previous and current use of the site will form
the basis of the assessment. A greenfield site is likely
10.2.10 Electricity to present fewer problems than a brownfield site, par-
ticularly when the site has been previously contaminated
Electrical hazards are covered in detail in Chapter 14,
by earlier activities. Chemical contamination is common
and all the control measures mentioned apply on a con-
when the site formerly housed industrial plant. It is not
struction site. However, due to the possibility of wet con-
uncommon in such situations for oils or other pollut-
ditions, it is recommended that only 110 V equipment is
ants to be stored in underground storage chambers; and
used on site. If mains electricity is used (perhaps dur-
although normally the bulk of such substances will have
ing the final fitting out of the building), residual current
been removed, residues will remain and present both
devices should be used with all electrical equipment.
environmental and cost problems to the construction
Where workers or tall vehicles are working near or under
developer who needs to understand the various reme-
overhead power lines, either the power should be turned
dial measures that may be used to prevent pollution of
off or ‘goal posts’ or taped markers should be used to
nearby streams. Remedial measures may involve the
prevent contact with the lines. Similarly, underground
capping of the chamber or its excavation and the com-
supply lines should be located and marked before dig-
plete disposal of the pollutants (possibly including soil
ging takes place.
washing and thermal treatment). In many parts of the
country, there are old mine workings, shafts and wells
10.2.11 Noise and in many cases there is no record of these on avail-
able public documents. A detailed site survey may well
Noisy machinery should be fitted with silencers. When discover that such old workings exist and indicate that
machinery is used in a workshop (such as woodworking sufficient funds must be allocated to ensure that they
machines), a noise survey should be undertaken and, if are safely capped.
the noise levels exceed the second action level, the use Knowledge of the history of the site is, therefore,
of ear defenders becomes mandatory. If it is necessary to important during the initial site assessment. Details will
shout when talking to a nearby colleague, then the noise also be needed of any other activities, including non-
level is excessive and ear defenders should be worn. construction ones, which are taking place at or near
the site.
10.2.12 Health hazards If the project involves demolition and refur-
bishment, then information on the occupancy of the
Health hazards are present on a construction site. These premises or nearby premises needs to be ascertained.
hazards include vibration, dust (including asbestos), A structural survey should be made of the building to
cement, solvents and paints, and cleaners. A Control of investigate the types of structural defect that may be
Substances Hazardous to Health Regulations (COSHH) apparent during a visual inspection and explain the
assessment is essential before work starts with regu- causes of those defects. Typical defects include cor-
lar updates as new substances are introduced. Copies rosion of steelwork, cracking due to fatigue in struc-
of the assessment and the related safety data sheets tural steel and welds, cracked brickwork and concrete,
should be kept in the site office for reference after acci- concrete degradation (flaking), dropped lintels and dis-
dents or fires. They will also be required to check that the torted doors or window frames, wood rot, evidence of
correct personal protective equipment (PPE) is available. timber infestation, dampness above the damp-proof

176
Construction site issues – hazards and control

course, cracks or dips in floors and ceilings, dips in


the roof line, deformed structural members and bulg- 10.4 Site controls
ing walls. Possible causes could include the quality of
the initial design, the age of the building, lack of mainte- Many of the site controls have been covered earlier in
nance, poor quality materials, poor construction stand- this chapter (Section 10.2 – General hazards and con-
ards, solar radiation, damage from extreme weather trols). Site controls can be conveniently subdivided
conditions, vibration from machinery or traffic, chemical under four headings – site planning, site preparation,
attack, overloading, accidental impact, ground settle- site security and the arrangements with the client and/or
ment or subsidence, leaking drains, unauthorized modi- occupier of the premises.
fications, fire damage, vandalism, the action of tree roots
and pest infestation. 10.4.1 Site planning
The provision of temporary supports where required,
suitable access equipment and barriers or covers to pre- An essential element of site planning is the layout of the
vent falls through floor openings and the need to carry site. Due to a lack of forethought or planning, many sites
out an assessment of the manual handling operations rapidly degenerate into a muddled or confused state.
are additional factors to be considered. Asbestos, ver- This leads to a corresponding reduction in health and
min infestation and exposure to lead from paintwork and safety standards and an increase in accidents.
pipes are possible health hazards and evidence of any During the site planning stage, arrangements will be
of these must also be included in any assessment. needed to ensure that there is safe access to and around
Also an emergency evacuation plan and the use the site for both pedestrians and vehicles. Care must be
of hot work permits may need to be considered at the taken during the planning of traffic routes so that pedestri-
initial site assessment stage. ans and vehicles are kept apart as much as possible. It will
A survey of the topography of the site, including also be necessary to provide suitable loading and unload-
the ground conditions, ground stability and type of ing areas, which may need to be moved as the construc-
ground or soil (e.g. gravel, sand or clay), is essential prior tion work progresses, and recognized parking areas.
to the commencement of any construction work. Method statements (see Chapter 6) should be
Access to the site, particularly for vehicles, is an developed at this stage. They will detail how a specific
important consideration especially if access is from a job or process is to be undertaken together with the
busy road or close to a school or hospital. associated hazards and the necessary control measures
Finally the nature of the surroundings of the that should be in place to ensure health and safety. If
site should be included in the assessment and should contractors are to be used, a pre-tender questionnaire
include the following considerations: should be submitted by them so that their competence
may be determined. The method statement should be
➤ the proximity of roads, footpaths, railways, rivers checked and approved by the employer or a respon-
and other waterways sible person, such as the site manager or supervisor,
➤ the details of any fencing or hedging and general before the work starts. When the work has started,
vegetation the employer is obliged, under section 3 of the Health
➤ the position and description of any trees which need and Safety at Work Act, to ensure adherence to the
to be felled and those that must be untouched (par- method statement and that a safe system of work is
ticularly if they are subject to a tree preservation being used while the work is being undertaken.
order) Adequate lighting must be provided in all parts of
➤ the proximity of residential, commercial or industrial the site especially along vehicle routes, although natural
properties and concerns light should be made available whenever possible. When
➤ the proximity of schools, colleges, hospitals and lighting failure could lead to serious risks of accidents,
playing fields such as working on a tower scaffold, secondary light-
➤ the presence of overhead power lines and details of ing should be provided, perhaps in the form of torches.
the responsible authority Suitable signs will be required on the site – these may
➤ the presence of buried services including sewers be health and safety, warning or directional signs.
and disused wells Areas on the site will also need to be designated for
➤ the availability of services, such as electricity, tele- site offices, materials and on-site machinery (fixed and
phone lines and water, and drainage systems mobile) storage and welfare facilities for the workforce.
➤ any evidence of fly tipping or other unauthorized Arrangements for the day-to-day management and con-
activity trol of the site, monitoring, review and inspection of pro-
➤ measures required to prevent unauthorized access cedures and equipment and workforce supervision must
by vehicles. be made during the planning stage.

177
Introduction to Health and Safety in Construction

If demolition or refurbishment is to be undertaken, ➤ a reasonable uniform load distribution within the


then hazards associated with structural collapse, fire, skip at all times
working at height, lifting and carrying and electricity must ➤ the immediate removal of any damaged skip from
be considered together with health hazards from lead, service and the skip inspected after repair before it
asbestos, vermin and insects. As mentioned in Chapter 20, is used again
a structural survey before work commences should ➤ sufficient space around the skip to work safely at all
reduce the risk of unintentional structural collapse. The times
issue of hot work permits, provision of firefighting equip- ➤ the skip should be resting on firm level ground
ment and suitable storage facilities for flammable sub- ➤ the skip should never be overloaded or overfilled,
stances should control the fire risk. Health risks can be and
controlled, for example, by the use of licensed contrac- ➤ there must be sufficient headroom for the safe
tors for the removal of asbestos, specialist contractors to removal of the skip when it is filled.
eradicate vermin and the provision of suitable PPE.
Emergency arrangements need to be in place before Finally the HSE should be notified before work begins
work begins. These arrangements should deal with fire (using F10 (rev) or the details required by F10) when the
precautions, accident reporting and investigation and project construction phase involves more than 30 days
the provision of an accident book together with RIDDOR of work or involves more than 500 person-days of con-
reporting forms. struction work. The CDM co-ordinator is responsible for
Whatever the type of construction project, the dis- this notification to the HSE. See Chapter 21 for details of
posal of any waste produced must be planned. There the information required.
are four requirements for the transfer of waste from the
site to final treatment or disposal: 10.4.2 Site preparation

1. The waste must be clearly identified. This will It is quite possible that specialist activities, such as lift-
involve the determination of the chemical and physi- ing, piling or steelwork, will be carried out on site dur-
cal properties of the material, the identification of ing the construction phase and controls will need to be in
any special problems associated with the waste, place to address associated risks. Only workers who are
and ensuring that it is properly labelled with a written competent in the specialist activity should be employed
description. or contracted. One of the ways of assessing competence
2. The waste must be securely stored with procedures is to check on relevant method statements supplied by
to deal with spillages and prevent access, particu- the workers. When the activity involves working at height,
larly by scavengers or children. then the safeguards outlined in Chapter 18 must be
3. The waste must be transferred only to an authorized made available. Care must also be taken to ensure that
person. Classes of authorized person include regis- other major hazards are addressed, such as noise and
tered waste carriers, holders of waste management vibration hazards associated with piling work and crane
licences or exempt parties such as charities or waste hazards during lifting operations. Site rules for site work-
collection authorities. Waste transfer notes must be ers should be formulated during the planning stage and a
transferred from one duty holder to the next along specimen set of such rules is given in Appendix 10.1.
the waste chain. Checks are advised to ensure that The preparation of the site may well involve the
prospective waste contractors are competent to deal removal or de-branching of trees using chainsaws and
with waste. a wheeled excavator to remove the roots. These are par-
4. The adequate records of waste consignments must ticularly hazardous operations when there are overhead
be kept for at least 2 years in the case of controlled or buried power lines at the site.
waste, and 3 years for any hazardous waste. (These Chainsaws must only be used by trained and com-
categories of waste are defined in Chapter 16 which petent operators using a safe system of work which
includes additional possible legal requirements for fully describes the hazards involved and the measures
waste disposal on construction sites.) required to reduce the risks. Such measures include the
necessary PPE, for example goggles, hearing protection,
Waste skip selection should be made during the site and ballistic trousers or overalls; the provision of safe and
planning process. The selected skip must be suitable secure access to higher branches such as ladders or
for the particular job. The following points should be cherry pickers; and the provision of fall arrest equipment
considered: such as harnesses. There must be a high level of super-
vision at all times. There is much more information on
➤ sufficient strength to cope with its load chainsaws and the necessary precautions when used, in
➤ stability while being filled Chapter 13 (13.9.4).

178
Construction site issues – hazards and control

Figure 10.4 Precautions for overhead lines: ‘goalpost’ crossing points beneath lines to avoid contact by plant.

When site preparation requires the removal of con- of access ladders, providing trench supports, covering
taminated topsoil, it is important to ensure that appropri- holes where possible, immobilizing plant, safe stacking
ate PPE, including respirators, is issued to the workforce of materials, locking away dangerous chemicals, isolat-
and the suitable welfare facilities, including a decon- ing electrical supplies and locking off fuel storage tanks.
tamination unit, are available. A decontamination unit Many of these problems may be avoided by visiting local
will have a dirty chamber where contaminated cloth- schools to inform children of construction site dangers.
ing can be left, a shower facility and a clean chamber Accidents to children on construction sites are a national
where clean clothes will be kept. Arrangements will also concern and a widespread problem everywhere.
be needed to ensure that eating, rest and first-aid areas The provision of warning signs at the perimeter
are free from contamination and that emergency decon- fence and suitable viewing points for the public to
tamination facilities are available. observe the construction work safely has been shown
Finally, high-voltage overhead power lines should to reduce the incidents of site trespass.
always be made dead to prevent contact with the ener- Whilst storage is an important factor for site security,
gized cable. If this is not possible, other control meas- it is also needed for health and safety reasons. Cement,
ures should be used such as height restrictions for site which is a hazardous substance, must be securely
vehicles, signs, goalpost barriers and the use of banks- stored in a dry store. Gas cylinders, fuel and other flam-
men. It is also necessary to locate and identify any mable substances must be stored in a separate flame-
underground services. It is essential that the electrical proof store (more details of these requirements are given
supply company is informed of the construction work in Chapter 15).
and that sound emergency procedures are in place.
10.4.4 Environmental considerations
10.4.3 Site security
The public must also be protected from environmen-
Site security is required to ensure that construction tal hazards resulting from the work, such as excessive
materials, equipment and accessories are protected dust, noise and mud on the public highway. Excessive
and this is usually achieved by the erection of a strong dust may be controlled by damping down haul roads
perimeter fence and a lockable gate. However, it is also regularly, the sheeting of lorry loads and imposing speed
important to protect members of the public includ- limits on roads close to the site. During road repair oper-
ing trespass by children. This is particularly relevant ations, dust should be prevented from entering surface
for a refurbishment project when strong hoardings or drains and precautions taken to prevent or restrict the
secure fencing must be provided. There is also a need effects of fuel spillage.
to ensure that the site itself is safe should children man- Noise levels may be reduced by the regular mainte-
age to trespass onto the site. This involves the removal nance of equipment and the erection of noise barriers.

179
Introduction to Health and Safety in Construction

Other controls include the use of quieter equipment and ➤ those site method statements which are relevant to
restricting the use of noisy machinery to late morning or the workers at the induction
early afternoon. ➤ the findings of any relevant risk assessments
Regular road sweeping will reduce mud on sur- ➤ details of any hazardous operations, such as work at
rounding roads. The problem will also be alleviated by height, site vehicular movement and confined space
washing vehicle wheels before they leave the site. working
For any of these measures to be successful, the site ➤ control measures on the site, including:
workforce must be informed of the procedures at induc- ➤ any site rules
tion and by posters and signs around the site. ➤ any permit-to-work systems
➤ traffic routes
10.4.5 Arrangements with the client and/or ➤ security arrangements
occupier of the premises ➤ hearing protection zones
➤ arrangements for PPE, including what is needed,
Such arrangements will include site rules (see Appendix where to find it and how to use it
10.1 for an example) for the protection of members of ➤ manual handling procedures and precautions
the public, visitors and other employees. They should ➤ arrangements for housekeeping and materials
also cover issues such as shared facilities (e.g. first-aid storage
arrangements and the use of catering facilities) and the ➤ facilities available, including welfare facilities
need for full co-operation from the occupier and his staff ➤ emergency procedures, including fire precau-
in the observation of health and safety rules. tions, the action to take in the event of a fire,
When the construction work involves a public high- escape routes, assembly points, responsible
way, measures should be introduced to ensure the safe people and the safe use of any firefighting
passage of vehicles and pedestrians. This will involve equipment.
the erection of warning signs, the use of cones with ➤ arrangements for first aid
lead-in and exit tapers and an indication of a safety zone ➤ arrangements for reporting accidents and other
between the cones and the work area. Pedestrian safety incidents
will require the use of barriers and lighting and traffic ➤ details of any planned training, such as ‘toolbox’
may need to be controlled using traffic lights or stop/go talks
boards. Certain neighbours, such as schools, hospitals ➤ arrangements for consulting and involving workers
or factories, may also need to be informed of the timing in health and safety, including the identity and role
of some aspects of the work. of any:
➤ appointed trade union representatives
10.4.6 Arrangements for site induction ➤ representatives of employee safety
➤ safety committees.
Properly organized and prepared site inductions for ➤ information about the individual’s responsibilities for
all site workers are very important. As mentioned in health and safety.
Chapter 9, site induction training is seen by the HSE
The quality of the information presented at the site meet-
as an essential element in the drive to reduce accidents
ing will determine the effectiveness of the induction train-
on construction sites. Induction training in general was
ing. Some use should be made of videos or DVDs in the
covered in Chapter 4 (4.8.1) and the issues raised there
presentation and the opportunity for interactive discus-
should be included in an induction event on a construc-
sion given. A copy of the site rules, health and safety pol-
tion site. However, the following additional topics should
icy and a simple organizational chart should be issued to
also be covered:
each worker at the induction meeting.
➤ senior management commitment to health and
safety
➤ site health and safety policy 10.5 Provision of welfare facilities
➤ the outline of the project
➤ the managerial and consultation arrangements on The HSE have been concerned for some time at the
site including the identity of their supervisor poor standard of welfare facilities on many construction
➤ site health and safety plans sites. Welfare arrangements include the provision of san-
➤ site welfare facilities itary conveniences and washing facilities, drinking water,
➤ any site-specific health and safety risks, for example accommodation for clothing, facilities for changing
in relation to access, transport, site contamination, clothing and facilities for rest and eating meals. First-aid
hazardous substances and manual handling provision is also a welfare issue and is covered in

180
Construction site issues – hazards and control

Chapter 6. However, the scale of first-aid provision will each for every 25 employees). Special provision should be
be related to the size and complexity of the project, the made for disabled workers and there should normally
number of workers on site at any given time and the be separate facilities for men and women. There should
proximity of emergency hospital facilities. be adequate protection from the weather and only as
Sanitary and washing facilities (including show- a last resort should public conveniences be used. A
ers if necessary) with an adequate supply of drinking good supply of warm water, soap and towels must be
water should be provided for everybody working on the provided as close to the sanitary facilities as possible.
site. Accommodation will be required for the chang- Hand dryers are permitted but there are concerns about
ing and storage of clothes and rest facilities for break their effectiveness in drying hands completely and thus
times. There should be adequate first-aid provision (an removing all bacteria. In the case of temporary or remote
accident book) and protective clothing against adverse work sites, sufficient chemical closets and sufficient
weather conditions. Welfare issues are covered by the washing water in containers must be provided.
CDM 2007 and its AC.P. All such facilities should be well ventilated and lit
Detailed guidance is also available in HSG 150 and cleaned regularly.
Health and Safety in Construction. Welfare requirements Drinking water must be readily accessible to all
are also covered in the work place (Health Safety and the workforce. The supply of drinking water must be
Welfare) Regulations and its AC.P. adequate and wholesome. Normally mains water is used
and should be marked as ‘drinking water’ if water not
fit for drinking is also available. On some sites, particu-
larly during the early stages of construction, it may be
necessary to provide bottled water or water in tanks. In
this event, the water should be changed regularly and
protected from contamination. Cups or mugs should
be available near the tap unless a drinking fountain is
provided.
Accommodation for clothing and facilities for
changing clothing must be provided which is clean,
warm, dry, well ventilated and secure. Where workers are
required to wear special or protective clothing, arrange-
ments should be such that the workers’ own clothing
is not contaminated by any hazardous substances. On
smaller sites, the site office may be suitable for the stor-
age of clothing, provided that it can be kept secure and
used as a rest facility.
Facilities for rest and eating meals must be pro-
vided so that workers may sit down during break times
in areas where they do not need to wear PPE. It should
be possible for workers to make hot drinks and prepare
food. Separate rooms should be provided for smok-
ers and non-smokers. Facilities should also be pro-
vided for pregnant women and nursing mothers to rest.
Arrangements must be in place to ensure that food is
not contaminated by hazardous substances. Many fires
have been caused by placing clothes on an electric
heater. Damp clothes should not be positioned in con-
Figure 10.5 Welfare – washing facilities: washbasin large tact with the heater. There should be adequate ventila-
enough for people to wash their forearms. tion around the heater. If possible, the heater should be
fitted with a high temperature cut-out device.
Sanitary conveniences and washing facili- The location of the welfare facilities on the site is
ties must be provided together and in proportion important. They should be located adjacent to each other
to the size of the workforce. The Approved Code of and as close to the main working area as possible. It is
Practice of the Workplace (Health, Safety and Welfare) likely that as the work progresses, the welfare facilities
Regulations provides two tables offering guidance on the will need to be moved. It may be appropriate to use facili-
requisite number of water closets, wash stations and uri- ties in neighbouring premises. However, all such arrange-
nals for varying sizes of workforce (approximately one of ments must be agreed in advance with the relevant

181
Introduction to Health and Safety in Construction

Figure 10.6 A wide range of portable welfare facilities like these are available. It may be possible when refurbishing
buildings to use the facilities already on site.

neighbour. Reliance on public conveniences should be Identify the main hazards that may be
avoided due to their unreliability and lack of hot water encountered in carrying out this work and outline the
for washing (normally). precautions that should be taken to control them.
Welfare arrangements for transient sites will be dif-
ferent to those for fixed sites. Transient sites include 4. Extensive maintenance work is to be carried out
sites where the construction work is of short dura- on a piecemeal basis in a working warehouse. List
tion (up to 1 week in many cases), such as road works SIXTEEN items that should be covered in a site
and emergency work. In these cases, welfare facilities induction briefing for the maintenance contractor’s
(toilets, hand-washing basins, rest and eating arrange- employees.
ments) may be provided by a suitably equipped vehi-
cle or by siting fixed installations at intervals along the 5. Site preparation work involves the removal of topsoil
length of the job. from land known to be contaminated with heavy
HSE have produced two useful information leaflets metals. Outline the precautions required in relation
on the provision of welfare facilities at fixed construction to the transportation from site and disposal of the
sites (CIS No. 18 (rev 1)) and transient construction sites contaminated soil.
(CIS No. 46).
6. The preparation of a site requires the complete
removal of some trees and the de-branching of
others. An overhead power line crosses the site and
10.6 Practice NEBOSH questions for buried cables may be present.
Chapter 10 Describe a safe system of work for:
(a) cutting the timber using chainsaws
1. (a) Describe how a person new to a construction (b) removing tree roots by means of a wheeled
site could be made aware of the requirements to excavator.
wear head protection.
(b) Outline the requirements of the Construction 7. Site preparation work involves the removal of topsoil
(Head Protection) Regulations 1989. from land known to be contaminated with heavy
metals. Outline the specific requirements for this
2. Outline a system for the management and disposal work in relation to:
of waste from a construction site. (a) Personal protective equipment and practices
(b) welfare facilities.
3. Major refurbishment work, including the installation
of new supports and joists for the first floor, is to be 8. Residents living close to a large construction site
carried out on a two-storey Victorian building. have complained about excessive noise levels

182
Construction site issues – hazards and control

from the site, dust on their property and mud on 13. Outline the requirements of the Construction
residential streets. (Design and Management) Regulations relating to
(a) Outline the actions that could be taken to sanitary and washing facilities on construction sites.
mitigate such nuisances.
(b) Describe the means by which site management 14. Outline the requirements of the Workplace (Health,
could make contractors and operatives aware Safety and Welfare) Regulations relating to the
of any new procedures adopted. provision of welfare facilities.

9. Outline EIGHT precautions that should be considered 15. A project involves the construction of an in situ
to prevent accidents to children who might be concrete structure, including the installation of
tempted to gain access to a construction site. drains, on a brownfield site. Up to 60 people are
likely to be involved in the work at any one time.
10. Identify ways of minimizing the risk of accidents to Identify the welfare facilities that should be
children who might be tempted to gain access to a provided for such work.
construction site.
16. A project involves shallow excavations in land
11. Outline the issues that should be considered to previously used as a landfill site.
ensure the health and safety of security personnel Outline the welfare facilities that should be
used on a construction site out of normal working provided for such work.
hours.

12. Explain, with reference to practical examples,


the legal requirements relating to the provision of
welfare and first-aid facilities on construction sites.

183
Introduction to Health and Safety in Construction

Appendix 10.1 – A typical set of site rules

1. All contractors are required to comply with the 10. All plant and equipment brought onto site must
guidance contained in the publication HSG150 be in good condition and properly maintained.
Health and Safety in Construction as the basis 11. Operators of plant and equipment must
upon which their construction activities are produce ‘certificates of competence or training
organized, planned and implemented. A copy will achievement’ when requested or a letter from
be provided on site for reference by contractors their employer confirming competence and
and employees. authorization to operate the plant/equipment.
2. Contractors must ensure that their employees are 12. Plant and machinery must be immobilized and
made aware of these site rules and fire, first-aid secured when the site is unattended.
and emergency procedures. 13. The site manager must be advised before any
3. Any person who is in doubt about safe working ‘hot work’ is undertaken and an appropriate hot
practices and procedures must contact their work permit form completed.
supervisor. 14. Entrance gates/fencing must be secured and
4. Any person becoming aware of any unsafe act, locked when the site is unattended.
condition or faulty piece of equipment which they 15. Contractors must supply details of risk
cannot put right themselves, must where possible assessment and method statements as required
warn others, isolate the hazard and immediately by the site manager.
inform the person in charge. Where necessary, 16. Only 110 V electrical tools and equipment are to
work should be stopped and, if appropriate the be used on site.
area evacuated. 17. Hard hats must be worn in the designated areas.
5. All persons must report to the site manager when 18. Safety footwear must be worn at all times.
initially arriving on site. 19. Debris and waste must be cleared away regularly,
6. Sub-contractors must advise the site manager of and dust (and noise) kept to a minimum. There
any employees under the age of 18 and provide a must be no burning on site.
copy of their assessment of the risks specific to 20. All accidents and incidents must be reported
young persons. immediately to the site manager and entered in
7. Young persons on ‘work experience’ will not be the accident book.
permitted on site without the prior agreement of 21. The statutory reporting of injuries is the
the site manager. responsibility of the individual employer of
8. No person who is known to be under the contracted workers. The site manager is to be
influence of alcohol or illegal substances will be provided with a copy of Form F2508.
permitted to work. 22. Sub-contractors and employees must co-operate
9. The site manager has the authority to stop with the site manager in the investigation of any
work if he is not satisfied with the provisions or incident or accident.
arrangements made for health and safety whether
in respect of unsafe practices, faulty plant and
equipment or the conduct of employees.

184

Potrebbero piacerti anche