Sei sulla pagina 1di 1

GANT CHART DECOMMISSIONING

Project : Decomissioning Ø 12''


Contractor : PT. Wijaya Karya
Sub Contractor : PT. Farrel Internusa Pratama
Location : KM 138 - 127 & TBBM Padalarang - Bandung

PERHITUNGAN SIMULASI WAKTU


Pembulatan
Truk Tangki (LPM) 16,000.00 (jam)
KM.127 Kapasitas Pompa max. 610 LPM (610 610
x 75%) 457.50
KM.127 Loading di KM. 127 (menit) 34.97 35
KM.127 Conec & Disconect Hose 15.00 15
Waktu tempuh KM. 127 - TBBM Padalarang 90.00 90
TBBM PDL Kapasitas Pompa max. 909 LPM (909 x 75%) 681.75
TBBM PDL Unloading di TBBM Padalarang (menit) 23.47 23
TBBM PDL Conec & Disconect Hose 15.00 15
Waktu tempuh KM. 127 - TBBM Padalarang 90.00 90
268
4.47