Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Equipment
Group 4:
Nastia Siti D. W.
Sulthan Ridansyah A.
Dian Ratri Cahyani
Rayhan Mustofa K.
Rizky Rahardi Pramono
Chapter 11: Finishing
Equipment
Outline 03
Finishing operations follow closely behind
excavation operations or compation of
embankments.
Chapter 2: Fundamental
Concept of Equipment
Economics
A correct and complete understanding of
the costs that result from equipment
ownership and operation.
01 02
Chapter 9: Excavator
Hydraulic power is the key to versatility of
many excavators.
Chapter 2
Fundamental Concept of
Equipment Economics
Important Questions
1. How much does it cost to operate a machine on a project?
2. What is the optimum economic life and the optimum manner to secure a machine?
3. How much is the productivity of the machine?
Equipment Requirements in a Project
General conditions in equipment selection:
A = annual cost
The present worth is discounted at a predetermined rate of interest, often termed the minimum
attractive rate of return (MARR)
Example
Answer
*Contractor’s MARR is 8% Alternative A :
1. Purchase expense
2. Salvage value
3. Tax saving from depreciation
4. Major repairs and overhauls
5. Property taxes
6. Insurance
7. Storage and miscellanous
Elements of ● The cash outflow the firm experiences
in acquiring ownership of a machine
Ownership Cost ● It is the total delivered cost, including
amounts for all options, shipping, and
taxes.
● The firm has exchanged money, a
liquid asset, for a machine, a fixed
asset with which the company hopes
Purchase Expense to generate profit.
Elements of ● The cash inflow a firm receives if a
machine still has value at the time of
Ownership Cost its disposal. The revenue will occur at
a future date.
● Machine condition, the movement of
new machine prices, and the
machine’s possible secondary service
applications affect the amount an
Salvage Value owner can expect to receive.
Elements of ● The tax savings from depreciation are
a phenomenon of the tax system in
Ownership Cost ●
the US.
Under the current tax laws, tax
depreciation accounting no longer
requires the assumption of a
machine’s future salvage value and
useful life.
Tax Savings from Depreciation
Elements of ● Major repairs and overhauls are
included under ownership cost
Ownership Cost because they result in an extension of
a machine’s service life.
● Can be considered as an investment in
a new machine.
Taxes
Elements of ● Includes the cost to cover fire, theft,
and damage to the equipment.
Ownership Cost ● This cost can be actual premium
payments to insurance companies, or
it can represent allocations to a
self-insurance fund maintained by the
equipment owner.
Insurance
Elements of ● A company will require storage
facilities for its equipment. The cost of
Ownership Cost maintaining storage yards and
facilities should be prorated to those
machines that require such
harborage.
● Typical expenses include space rental,
utilities, and the wages for laborers or
Storage and Miscellaneous watchmen.
Elements of Operating Cost
Operating cost is the sum of those expenses an owner experiences by working a machine on a project.
Typical expenses include:
1. Fuel
2. Lubricants, filters, and grease
3. Repairs
4. Tires
5. Replacement of high-wear items
Elements of ● Fuel expense is best determined by
measurement on the job. Accurate
Operating Cost service records tell the owner how
many gallons of fuel a machine
consume over what period of time and
under what job conditions.
Fuel
● The cost of lube oils, filters, and
grease will depend on the
maintenance practices of the
● On the other hand, when an asset is rented; the responsibility of maintenance lies on
Production rate
Production rate
● Being struck by the moving machine, swinging booms, or other machine components
● Being struck by quick-disconnect excavator buckets that unexpectedly detach from the stick
● Rollovers, electrocutions, and machined sliding into trenched after cave-ins
Safe Practices:
● Operators keep machine attachments at a safe distance from workers at all times
● Workers are trained regarding safe practices when working in close proximity to heavy equipment
● Supervisors consider alternative working methods that eliminate the need to place workers in
close proximity to heavy equipment.
Front Shovels
● Used predominantly for hard digging above track level and for loading haul units
● Shovels are capable of developing high breakout force with their buckets but the material being
excavated should be such that it will stand as a vertical bank
● The size of a shovel is indicated by the size of the bucket
● Fill factors for front shovel buckets
● Struck capacity: volume actually enclosed by the bucket with no allowance for the bucket teeth
● Heaped capacity: angle of repose for heaped bucket capacity
Selecting a Front Shovel
2 fundamental factors that should be taken into account:
Selecting a Front
a. A job involving a large quantity of material
may justify the higher O&O and
mobilization costs of a larger shovel
Shovel 2. The cost of mobilizing/transporting
the machine to the project
3. The combined cost of drilling, blasting,
and excavating
Elements in the Production Cycle of a Shovel
Production 2.
3.
Swing with load 4-6 sec
Dump load 2-4 sec
4. Return swing 4-5 sec
Production 1.
2.
Class of material
Height of cut
3. Angle of swing
4. Operator skill
5. Condition of the shovel
6. Haul-unit exchange
7. Size of hauling units
8. Handling of oversize material
9. Cleanup of loading area
● A loose, flowing material will fill a
Effect of Shovel ●
material
If the face against which a shovel is
Production excavating material does not have
sufficient height, it will be difficult of
impossible to fill the bucket in one
pass up the face.
Height of Cut
Effect of Shovel
Production
Example question
Height of Cut
Effect of Shovel
Production
Example question
Hoes
● Primarily used to excavate below the natural surface of the ground on which the machine rests
● Other names: backhoe or back shovel
● Adept at excavating trenches and pits for basements and the smaller machines can handle general
grading work
Basic parts and
operating ranges of
hydraulic hoe
A: dumping height
B: digging reach
Formula
Excavation cycle times for
hydraulic crawler hoes under
average conditions
Calculating Hoe
Production
Example Question
Loaders
Are used in construction work to handle and transport bulk material, such as earth and rock. Also to load
trucks, excavate earth, and to change aggregate bins
Types and Sizes
1. The type of material 1. Fixed cycle time required to load the bucket
2. The volume of material to be handled 2. Time required to travel from the loading to
dumping
3. Time required to return to the loading position
4. Volume of material
Fixed cycle times for loaders
Chapter 11
Finishing Equipment
Graders
Are multipurpose machines used for: The primary purpose of grader’s is cutting and
moving material with moldboard. A grader can
1. Finishing move small amounts of material but cannot
2. Shaping perform dozer type work.
3. Bank sloping
4. Ditching Graders are capable of progressively cutting
5. Mixing ditches to a depth of 3ft .
6. Spreading
7. Leveling
Components of Grader
There are:
1. Moldboard
2. Rotating circle
3. Scarifier
Moldboard
Commonly referred to as the blade. A rotating circle carries the moldboard. Moldboard can be placed
into many positions.
Moldboard Angle
Moldboard can be positioned at almost any angle to the line of travel.
Scarifier
Used to cut material that is too hard. It is an attachment hung between the front axle and the moldboard.
It is composed of a scarifier log with removable teeth.
Grader Operations
Planing Surfaces
A grader is often used to plane or smooth off fill or cut surfaces. To do this the moldboard is set an angle to
surface with high material being scrapped off and used to fill low spots.
Moving Windrows
When a grader makes a cut, a windrow will form between the heel of the moldboard and rear wheel. This
widrow will impart a side draft force.
Spreading
Graders are often used to spread and mix dumped loads. Because of their mechanical structure and
operating characteristics, graders can only be effective spreading and mixing free flowing materials. The
general formula for figuring grader spreading and mixing production is:
Proper Working Speeds
Graders should be operated at full throttle in each gear. If less speed is required, it is better to use a lower
gear.
Turns
When making a number of passes over short distance (less than 1000 ft), backing the grader to the starting
point is normally more efficient than turning it around and continuing the work from the far end.
Number of Passes
Grader efficiency is in direct proportion to the number of passes made. For example, if 4 passes will complete a
job, every additional pass increases the time and cost of the job
Tire Inflation
Overinflated tires cause less contact between the tires and road surfaces. To achieve good results it is
necessary to always keep tires properly inflated.
Time Estimates
Example
Fine Grading Production
Example
Grader Safety
In order to keep workers and construction equipment safe. Cause by many fatalities are happened inside
the working project area by the machines that are moving in reverse
Sight Lines Adjoining Activities
Operators of heavy vehicle are not Many projects involves work along or
able to see directly behind them. work that crosses railroad tracks