SEPTIC TANK

TYPE OF WORK L W H N VOLUME RATE COST


BRICK WALL 6 0.21 2 2 5.04
BRICK WALL 3 0.21 2 2 2.52
BAFFLE WALL 3 0.21 1.5 1 0.945
BRICKWORK 8.505 3000 25515

CONCRETE 1:2:4) 6 3 0.75 1 13.5 3400 45900

EXCAVATION 6.5 3.5 2 1 45.5 100 4550

PVC PIPE 8 0.05 34 272

TOTAL COST IN Rs = 76237

SOAK PIT

RADIUS OF SEPTIC TANK , r = 1.5 m


DEPTH OF SEPTIC TANK ,h = 3m
AREA OF SEPTIC TANK , A = 7.065 m²

EXCAVATION = 21.195 m³
RATE OF EXCAVATION = 100 Rs
COST OF EXCAVATION = 2119.5 Rs
AMOUNT OF BRICK BATS TO BE USED = 5404.725

RATE OF LOW CLASS BRICK = 2 Rs PER BRICK


COST OF BRICK LAYING (INCLUDING SUPPLY AT SITE)
= 10809.45 Rs

PIPEWORK = 204 Rs

LABOUR HEAD = 4000 Rs


TOTAL COST IN Rs = 17132.95 Rs

GI SHEET SHED

LENGTH OF ROOF = 11 m
WIDTH OF ROOF = 15 m

AREA OF ROOF = 165 m²


AREA OF GI SHEET = 4.8 m²

NO. OF SHEETS TO BE USED = 34.375


= 35

RATE PER SHEET = 200 Rs PER m²

TOTAL COST = 33000 Rs

RATE OF BRICK PILLAR OF SIZE 300X300 mm = 3500 Rs

COST OF 10 PILLARS = 9450 Rs

TOTAL COST OF GI SHEET SHED = 42450 Rs