0114 Beldar Day 0.1750 176.00 30.80 19.5300 3437.28
Mason (brick layer )2nd
0124 Day 0.1563 329.00 51.41 17.4375 5736.94
class
WOOD-Kail wood 2nd
MR6091 cum 0.0038 15825.60 59.35 0.4185 6623.01
class
Total Quantity 111.6000 sqm
Total Deducted Quantity 0.0000 sqm
Net Total Quantity 111.60 sqm
Say 111.6000 sqm @ Rs 161.653 / sqm 18040.47
Unskilled
3437.28 Unskilled Person-days 19.53
wage
Lump sum Type :
4 Quality control and Survey 8258.00
Admin
Heading / Description : 5 - EXCAVATION OF NALA
1 63.27.06.2 -- Earth work in rough excavation, filling excavated earth into depressions on
banking as directed, top surface to be levelled and neatly dressed.</br>(a) Dense or hard soil
Sl No Description No L B D CF Quantity Remark
-
1 - 1 60.000 5.000 0.750 1.0 225.0000 -
LIST
Total Total
Code Description Unit Quantity Rate(Rs) Amount(Rs)
Quantity Amount(Rs)
0114 Beldar Day 0.6700 176.00 117.92 150.7500 26532.00
Total Quantity 225.0000 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 225.00 cum
Say 225.0000 cum @ Rs 133.25 / cum 29981.25
Unskilled
26532.00 Unskilled Person-days 150.75
wage
Total Rs : 499999.95
Rounded Total Rs : 5,00,000.00
( Rupees Five Lakh Only)
Unskilled Manpower wages 84917.04
Materials (Includes Extra Charges) 395474.84
Carriage 0.00
Skilled 2200.93
SemiSkilled 9148.96
Lumpsum Admin 8258.00
Lumpsum Material 0.00
No of Person days 482