Sei sulla pagina 1di 4

2017 International Conference on High Voltage Engineering and Power System

October 2-5, 2017, Bali, Indonesia

Criteria for Integration of Intermittent Renewable


Energy to the Java Bali Grid
Eko Yudo Pramono1, Suroso Isnandar 2

PT. PLN (Persero) Pusat Pengatur Beban (Load Dispatching Centre)


Gandul, Cinere, Indonesia
1
ekoyudopramono@gmail.com
2
suroso.isnandar@pln.co.id

Abstract— Java Bali Grid has now reached the highest peak new renewable power plants, it will consist of dispatchable and
load ever at 25,325 MW on 15th September 2017, and the trend is intermittent generators.
going higher in the future. The fuel mix is dominated by fossil The maturity level of technology of renewable energy
fuel such as coal and gas, and about 8.8% comes from power plants has been reaching the commercial level of
dispatchable renewable energy of hydro and geothermal.
application and will be much reliable, cheaper technology
Government has set a progressive target of 23% renewable
energy in 2025 which may come from dispatchable and available in the coming years. It even has been reported that
intermittent renewable energy. In order to maintain the smooth some solar farm has reached a significant low cost of
operation of Java Bali Grid, criteria for integrating the generation and comparable to those of coal power plants [2].
intermittent renewable energy must be set and stipulated through Apart on that, government has also set a target for PLN
Grid Code. This criteria based on three basic pillars of system Pusat Pengatur Beban (Load Dispatching Centre) as the Java
operation principle, which to fulfill the reliability and security of Bali System Operator, to bring down the cost of electricity
supply, the quality of supply and economic operation of the generation as low as practically possible, in order to be able to
power system. This paper discuss the required criterias for give attractive tariff for industries and business in a such way
integrating intermittent renewable energy to the Java Bali. The
to sustain and maintain the economic growth of Indonesia. The
novely of this paper is as currently there is no standar has been
set for integration of intermittent renewable energy to the Java tariff subsidy which has been given in the past is gradually
Bali Grid, this paper proposes an approach to set criterias and withdrawn by government so the tariff must reflects the
requirements for the grid integration of renewable energy economic and real cost of generating electricity. This will add
sources. more complication in running and operating the Java Bali Grid.
As there is currently no standar has been set for integration
Keywords : renewable energy, fuel mix, dispatchable and of intermittent renewable energy to the Java Bali Grid, this
intermittent generation, power system reliability, system operation paper proposes an approach to set criterias and requirements
criteria for the grid integration in Java Bali interconnected system.

I. INTRODUCTION
II. POWER SYSTEM OPERATION CRITERIA
Currently the Java Bali Grid has reached its peak load at
25,325 MW on the 15th September 2017 at 18.00, and this Java Bali Grid as the same as other electricity network is
trend will continue to rise in the future, following the economic operated by adhering the three basic pillar of system operation,
development of Indonesia which has been growing consistently which are reliability and security of supply, quality of supply
at the level of more than 5% annually. To sustain this economic and economic operation of the system as depicted in Figure 1.
development, Government of Indonesia has launched a Reliability and security dictates that a power system should
capacity development program in electricity sector, and aim to have an ability to maintain its stability when there are some
build 35.000 MW of new generation plants, more than 46.000 disturbances occurred in the system without losing its ability
kms of transmission line 500 kV and 150 kV, and addition of to supply electricity and preventing any interuption, partial
new transformer up to 120.000 MVA, all should accomplished black out or total collapse of the system. Meanwhile quality
within the next 5 years [1]. must be adhered to in term of there is no violation of service
In doing so, government has also set a target of improving quality boundaries, such as voltage level remaining in certain
fuel mix by introducing more of renewable energy into the range, frequency does not vary wildly, and there is limited and
system. It is envisaged that by 2025 renewable energy must be controllabe harmonic distortion and irregularities. The third
accounted for 25% of all electricity generated in Indonesia [1]. principle is economic operation of power system, meaning a
For Java Bali Grid system, to achive this much portion of grid must be operated to achieve cost of generation as low as
renewable contribution, it must be installed at least 15.000 MW possible.
renewable power plant on top of currently around 3.500 MW
of hydro and geothermal power plant. From those 15.000 MW

978-1-5386-0945-3/17/$31.00 ©2017 IEEE

91
- Remedial Action Scheme (RAS) or Defense Scheme
The system keeps stable in
steady state and able to avoid Protection
the load shedding/blackout
during the system disturbance Manual Load Shedding (f<49,5 Hz)
The system operates with
Reliable UFR (48,4 < f < 49,0 Hz, in 7 steps)
Islanding Mode (48,1 < f < 48,3 Hz)
minimum cost

Over Generation Shedding


Over Load Shedding
- Grid Limitation / Constraint
Economic Quality This network congestion occured when there are
imperfect network configuration due to the lack
progress of new lines or because some major
The system operates with a
disturbance on the network.
good standard quality
b. Service Quality Criteria
The quality of supply can be seen from following criteria :
- Voltage Stability (Grid Code OC 4.0)
Figure 1. Three Basic Pillars of System Operation Principle
The voltage range in customer end for 150 kV and
66 kV system must fall between ranfe of +5% and -
10%, for 500 kV system must be kept in the range
III. CRITERIAS FOR INTERMITTENT RENEWABLE ENERGY of +/- 5%.
INTEGRATION INTO JAVA BALI GRID This voltage stability is maintained through
procedure of reactive power management either
The system operation criteria is achieved by dispatching from generation side or compensation techniques,
and regulating all the power plants connected to the Java Bali and transmission operation management.
system. For dispatchable power generators either fossil-fuel or - Frequency Stability (Grid Code OC 3.0)
renewable energy such as geothermal and hydro, those basic Frequency range which still can be accepted and as
principles could be achieved quite straightforward without governed by Jawa Bali Grid Code is 49.80 – 50.20
much difficulties. However this might not the case for Hz, and during 2016 a record of 97,7% was
intermittent renewable energy sources, as the nature of achieved in one year.
intermittent power generator is vary widely depending on the To maintain the frequency within this range, P2B
characteristic of local wind and solar insolation. These type of (Load Dispatching Centre) uses two methods, using
power plants are not dispatchable, so they must be taken as Load Frequency Control with participating
they are available and can not be dispatched at will. generators approximately 559 MW and Governor
Therefore they will add difficulties in operating the grid Free Mode with participat about less than 30% from
especially if their amount is quite significant to have adverse total 252 units power plants in Jawa Bali Grid.
impacts on the grid. In this case a set of criteria to be fulfilled
by these type of power plants must be stipulated in order to c. Economic Operation Criteria for Java Bali Grid
mitigate and manage the adverse impact it could have on grid Java Bali Grid is a growing and expanding electricity
operation. network and until now still experience some serious
a. System Reliability Criteria congestion due to the slipping finishing date of
transmission and substation project. Therefore in operating
PLN P2B (Load Dispatching Centre) sets an Reliability the grid P2B (Load Dispatching Centre) needs to consider
Criteria for running the Java Bali Grid as follows : following aspects :
- Maintaining reserve margin at minimum of 30% - System Constraint :
Reserve Margin (RM) on 15th September 2017 was 1. Stability
= (Nett Capacity - Peak Load)/Peak Load 2. Primary energy Take or Pay Contract and
= (33.439 – 25.225)/ 25.225 = 32,7% Pipe Line Pack limitation (gas, geothermal)
- Normal System Operation Criteria 3. Transmission congestion
Normal Criteria is Spinning Reserve fulfilled at least 4. Long distance power transfer (voltage
as same as the biggest unit size of power plant in Java stability)
Bali system. (Grid Code OC 2.2). Current minimum 5. Losses
spinning reserve in Java Bali is 815 MW. - Power Plant Constraint :
- Alert Condition Criteria 1. Power plant mode of operation (base load,
During the alert condition, System Reserve will be load follower or peaker)
maintande at least as twice as the biggest unit size. 2. Availibility condition of power plant (FOR,
(1630 MW) derating)
3. Minimum technical loading
- Economic Dispatch :

92
1. Hydro thermal coordination
2. Merit order

60 MW

60 MW
TML
SolarPLTS
/ Wind Farm Unit Back Up
Figure 3. Technical Minimum Load (TML) and Back-up Unit

Figure 3 shows the characteristics of the back-up units,


when they have to reduce output due to the production of the
renewable power plant. However there are limitation on how
Figure 2. Load Profile of Java Bali System much it should be reduced, as there is constraint of Technical
Minimum Load (TML) of the back-up power plant at certain
Figure 2 shows the load profile of Java Bali System with level. If the generation fall below TML, then unit will be
average load factor is more than 80%. This short of pattern tripped and can not immediately started again.
will likely to change if the penetration of renewable energy For aspect of maximum capacity allowable at one site, some
reaching the capacity as targeted. In other country whereas consideration must be given for the following item :
penetration level of renewable energy has reached significant - Ramping up / down capability of thermal units
amount, the load profile will change to a new pattern. - TML and regulation capabilty of thermal units
- Response time fo starting up / down of thermal units
and time needed in between
IV. ASPECTS AND IMPACTS OF INTERMITTENCY TO THE Power Plant Type Ramp Rate
JAVA BALI GRID Coal-fired 1 – 5 MW/min

There are some aspects and impacts of intermittency needs Gas Combined Cycle 5 - 8 MW/min

to be considered to keep the grid operating as intended. These Gas Open Cycle 5 – 8 MW/min
Hydro 20 MW/min
include variable output, back-up unit needed, maximum unit
capacity allowable at one location for solar and wind farm,
stability, power balance, defect to frequency, defect to voltage, Figure 4. Ramping Characteristic of Thermal Unit in Java Bali Grid
voltage regulation and economic aspect.
The variable output of renewable power plant is entirely Figure 4 shows characteristic of ramping up/down of the
depended on the availibility of solar and wind, which are given thermal unit in Java Bali Grid. Coal-fired has the slowest
by nature and can not be controlled. The potential for solar and response of 1-5 MW/minute, the gas power plants are between
wind farm in Java Bali Grid still need to be verified and studied 5–8 MW/minute, and the quickest is hydro unit of 20 MW/min.
further. Although there are some proposal has been put forward Therefore considering the current condition of the thermal
by developer, the feasibility study still need to be confirmed. ramping characteristic and its effect on frequency, the
However PLN has signed a power purchase agreeement with maximum renewable intermittent Java Bali Grid can absorb
a 70 MW wind farm in Yogyakarta, Central Java, although currently at maximum of 300 MW.
later is terminated due to some difficulties in project execution. Hz
This shows some potential exists and commercially attractive. 52,00

The intermittency nature call for some mitigation, including 50,20


Normal operation, frequency 50 + 0,2 Hz
some back up units to be ready to run any moment for
50,00
49,80
Excursion, + 0,5 Hz, brown-out
compensating the loss generation and prevent further frequency 49,50 Manual load shedding scheme A and B (625 MW + 625MW)

drop in the system. 49,00

Load shedding stage 1 s.d 7 (5.760 MW), frequency 49,00 s.d. 48,4 Hz
48,40
48,30
Islanding Operation, 48,30 - 48,10 Hz
48,00

47,50 Host-load operation of power plants

Figure 5. Frequency Excursion Range for Java Bali Grid

93
PLN P2B (Load Dispatching Centre) has set the operation
Figure 5 depicts the range of frequency tolerance in Java Bali parameters that should not be violated when integrating the
system.The normal range of frequency is between 49,8 – 50,2 new intermittent generation. This will be refelected in the
Hz and P2B (Load Dispatching Centre) will always try to coming revision of Java Bali Grid Code and should be adhered
achieve this range all the time. Any variation in renewable by any parties to connect the new plants to the grid, in order to
energy output should not bring the frequency out of this range, achieve the main objective of system operation by bring down
and this is become one of the grid primary concern in the cost of electricity, at the same time fulfilling the standard of
accommodating the intermittent renewable energy. service : reliability and security, quality and economic of
The other conern is the characteristic of inertia-less of supply.
intermittent renewable energy power plant. This will bring The approach to set criterias and requirements for
down overall system inertia as the intermittent will be the intermittent connection the grid has been proposed based on
quickest unit to disconnect from the grid if not regulated the basic principles of power system operation. Such criterias
specifically, the overall of the trip of units will affect and must be adhered in order to fulfil the system reliability criteria
compromise overall stability. and service level criteria.
The higher level of renewable energy penetration will also
push down the capacity of existing power plant in a such way,
creating new pattern of loading of thermal stations, with lower REFERENCES
capacity running during the day and back to normal loading [1] PT PLN (Persero), “Development Plan of Electricity Infrastructure
during evening, creating the steep increase on loading to 2017-2026”, Jakarta, PLN Head Office, 2017
thermal units in a very narrow time. Currently in Java Bali the [2] Website : http://www.independent.co.uk/environment/solar-and-wind-
power-cheaper-than-fossil-fuels-for-the-first-time-a7509251.html, as
difference of coal fired unit loading during the day and accessed on 02nd October 2017
compared to evening time can be as much high as 4.000 MW. [3] PT PLN (Persero) Pusat Pengatur Beban (PLN Load Dispatch Center),
This number will be even more with the penetration of “Evaluation Report of 2016 Annual Operation 2016”, Depok, Indonesia,
renewable energy in the future. 2017
Voltage and and frequency quality will also be affected [4] PT PLN (Persero) Pusat Pengatur Beban (PLN Load Dispatch Center),
substantially, including the reactive power regulation. As the “2017 Annual Operation Plan”, Depok, Indonesia, 2016
reactive power regulation from the intermittent plants are [5] Wood, A.J., et.al, “Power Generation, Operation and Control”, John
Wiley & Sons, USA, 2014
somewhat limited and not as wide as the conventional plants,
[6] Yadav, M., Saini, D.K., Pal, N., “Review and Compliances of Grid Code
this issue needs also to be dealt with and reflected on the Grid with Renewable Energy Integration”, Indian School of Mines, India,
Code in order to accommodate the connection of the units. 2015
[7] Hammons, T.J., “Integrating Renewable Energy Sources into European
Grids”, University of Glasgow, UK, 2010
V. CONCLUSION [8] Crabtree, G., et.al, “Integrating Renewable Energy on the Grid : A
It is unavoidable that intermittent renewable energy will be Report by the APS Panel on Public Affairs”, APS, Washington DC,
USA, 2014
one of the dominant sources of electricity and will contribute
[9] Jessen, L., Fuchs, F.W., “Investigation of Renewable Energy Generation
significantly to the fuel-mix. Government policy has enabled and Load Impact on the Grid Impedance at Different Points of
the proliferation of the renewable energy sources, and this will Connection in Public Low Voltage Grids to Support Grid Integration of
have an adverse impact to the grid if not mitigated properly. Renewable Energies”, Kiel University, Germany, 2017
There are some aspects and impacts of intermittency needs [10] IRENA, “Renewable Energy Integration in Power Grids : Technology
Brief”, USA, 2015
to be considered to keep the grid operating as intended. These
[11] Central Electricity Authority, “Large Scale Grid Integration of
include variable output, back-up unit needed, maximum unit Renewable Energy Sources : Way Forward”, India, 203
capacity allowable at one location for solar and wind farm,
system stability, power balance, defect to frequency, defect to
voltage, voltage regulation and economic aspect.

94

Potrebbero piacerti anche