Sei sulla pagina 1di 15

SPE 39023

A Successful Short Radius Re-Entry with Aerated Mud in Venezuela


Charles Ingold, SPE, Anadrill Schlumberger, Julio Salazar, SPE, Anadrill Schlumberger, Jose Carrasquel, Lagoven, Jose
Vidal, Lagoven, Francisco Ramirez, Lagoven, Bernard Gourgues, Air Drilling S.A, Juan Beltran Paredes, Air Drilling S.A

Copyright 1997, Society of Petroleum Engineers, Inc.


(Eocene Sand of Lake Maracaibo) - has been quite
This paper was prepared for presentation at the Fifth Latin American and Caribbean successful. A water zone overlying the targeted pay zone
Petroleum Engineering Conference and Exhibition held in Rio de Janeiro, Brazil, 30 August–3
September 1997. has to be isolated. They are separated by an unstable shale
This paper was selected for presentation by an SPE Program Committee following review of stringer. On medium or long radius wells profiles a casing
information contained in an abstract submitted by the author(s). Contents of the paper, as would be set at 60 degrees inclination or higher in the
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any shale. Due to the proximity of the target, medium radius
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at
SPE meetings are subject to publication review by Editorial Committees of the Society of cannot be used starting from vertical.
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the Society of Petroleum Engineers is The top of the pay zone was less than 77 ft from the
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous
bottom of the shale (discordancia) in the first well.
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. (Payzones are about 20 foot thick).
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
Drilling in Tia Juana has three major problems:
1- Setting intermediate casing restricts the number of
options to complete reentry wells, especially when the main
Abstract casing is 7 in.
New horizontal wells drilled with aerated mud have 2- The additional intermediate casing increases the well
proven to be a cost-effective way for drilling and enhancing cost.
well productivity. Reentry drilling operations using aerated 3- Lost circulation is always present, independent of the
mud have been used for over a year in Western Venezuela. casing program or the build up rate.
A major operator considered for a long time to combine Under this scenario, how could an operator get the
short radius technique and aerated mud to reduce cost per benefit of short radius reentry drilling at a reasonable cost ?
produced barrel. Several re-entry candidates appeared to be The problems were addressed by planning a
perfect for such an application. borehole trajectory where the well is drilled 100 % inside
A short radius drilling system, including articulated the pay zone. The unstable shale was avoided by cutting a
downhole mud motor and modified measurement while section below it, at the top of the Misoa sand. A short
drilling (MWD) tools, combined with careful drilling radius well profile brings additional benefits, like: single
engineering program has enabled a successful completion hole size, or using nearby well logs data for correlation
of the first two short-radius wells with aerated mud drilled purposes.
in Latin America. The second of which resulted in a six-
fold production increase over the average well in the area. Aerated mud
The first short-radius well was drilled in 13 days with 500 Aerated mud drilling has been recognized as having
feet of displacement. The second well was drilled in 12 days many advantages over conventional mud drilling, such as
and had 880 feet of horizontal drain (fig. 1 & 7). higher ROP, less formation damage and less risks of lost
This paper describes the operational aspects, and circulation or differential sticking. Avoiding differential
procedures followed. It emphasizes the equipment and rig sticking and lost circulation have a great impact on costs.
selection, the training requirements, and the environmental In some areas, aerated mud as a circulating medium, is the
and safety concerns. It also includes a comparison with only option to drill oil or gas wells.
other techniques. The overbalance pressure is often defined as the
pressure differential between the bottom hole pressure
The Problem: An Overlying shale Bed and a Water (caused by hydrostatic and friction) and the formation fluid
Zone pressure. A formation pressure lower than the hydrostatic
Drilling new horizontal wells (medium radius) in pressure of a column of fresh water requires the use of a
“Tia Juana” field at the Misoa formation - interval B5 lighter fluid. Air injected with mud will result in a lower
2 C. INGOLD, J. SALAZAR, J. CARRASQUEL, J. VIDAL, F. RAMIREZ, B. GOURGUES, J. PAREDES SPE 39023

overbalance pressure. Aerated mud is defined as a fluid problem, because pressure fluctuations are common with
consisting of liquid (water or mud), air and drilling aerated mud due to connection, air / mud ratio etc.)
cuttings. With the right surface equipment (mud pumps The basic short-radius BHA has the following
and air compressors) the required liquid and air flow rates components: bit, articulated downhole motor, customized
depend on the desired carrying capacity of the aerated mud flexible non-magnetic drill collar with MWD, and S-135
and flowing BHP during drilling. If a lower BHP is drill pipe (3 1/2 in. or 2 7/8 in.). In the upper straight
desired, a higher air/liquid ratio should be used (Fig. 3). section of the hole standard 5 in. or 3 1/2 in. drill pipe is
used depending on casing size. Drilling a short radius
curve required an articulated downhole mud motor
An infinite number of combinations of mud and air equipped with a special air drilling power section, where an
flow rate exists that meet the hole requirements. The bore orientation sub for the MWD tool is located at the top of it.
hole stability, the carrying capacity of fluid, pipe sticking A field-replaceable rotating stabilizer located close to the
and formation damage prevention are taken into account. bit reduces hanging-up and improves overall drilling
An optimum air flow rate exists from an energy performance. The steering and measurement functions
consumption point of view. This combination was were performed by a modified retrievable MWD tool. The
determined and used on both jobs. tool was hardwired to operate in air drilling conditions (fig
6.) It provides azimuth, drift, magnetic toolface, gravity
In this particular case the reasons to select aerated mud toolface, gamma ray, and downhole drilling shocks
drilling techniques were: measurements. It is battery-powered even though it is
- Avoid the circulation losses linked to surface by a cable. It can be retrieved, or run in
- Reduce formation damage the hole, with a wire-line. The drill string needs to be
- Improve the rate of penetration pulled to the wet connect to allow, if required, replacement
of the MWD without having to trip the BHA all the way out
Planning the Job of the hole. This is a reliable alternative to the
Drilling these wells required a careful preparation. electromagnetic data transmission system. The changes to
The selection of personnel and BHA design, the the standard MWD system can be made in a few hours.
environmental and safety considerations and specially a The directional sensor package is located at the bottom of
teamwork approach were crucial to the success of this the tool, bringing the measurement point 17 ft above the
operation. bit. Such a short distance allows to have an effective
The operation benefited from local experience of control of trajectory in short radius drilling operations.
team members, particularly in aerated mud drilling Most steering tools do not allow measurements as close as
practices. Several modifications to the standard drilling the MWD.
program were implemented; like: NMDCs have been specially designed to provide the
• Flopro mud to improve borehole stability. flexibility to easily trip in and out of the hole, through the
• The rig was not equipped with top drive which at curve, without problems.
the end was considered regrettable (see conclusions) A tricone bit is normally preferred because of its
• Pumping power, rotary and hook load capabilities lower drilling torque and easier toolface orientation while
were more than adequate for the depth. drilling the curved section of the well. In the lateral
• A zero discharge system was also in place. section, tricone bits were also used even though PDC’s
• The rig was equipped for air drilling and is utilized could have been considered.
most of the time for “aerated mud” operations. The
compressors had enough power even with a full LL 1070 first job The first Reentry Operation
string of 3 1/2 in. drill pipe. The well profile was designed to use the short
radius system and available drill string components at its
The drilling crew had good experience in the area maximum limits, i.e. 70 ft radii. These constraints made it
with aerated mud. The quality of the technical support necessary to land the drain hole at the lower part of the pay
provided by operator, drilling fluid companies, wireline and zone. The presence of a positive 2 degree formation dip
gyro companies and recognized experts in the field of air made it necessary to build angle to 95 deg. to get higher in
drilling were in tune with the situation. the best part of the reservoir.
The rigs used on the lake are floating barges. A single 6 1/8 in. was planned from 9 5/8 in.
Generally waves are one foot high, but they may reach up to casing. A cement plug was set next to a section milled
four feet. This can be a problem with aerated mud system window and drilled off within a foot of the top of window.
and slow rate of penetration; for example, if the downhole The curve was drilled in two steps. The sidetrack was
motor stalls, it takes time a long time to identify the initiated with a double bend motor assembly oriented with
SPE 39023 A SUCCESSFUL SHORT RADIUS RE-ENTRY WITH AERATED MUD IN VENEZUELA 3

gyroscopic survey, followed by an articulated positive important reduction of drilling time could be achieved by
displacement (PDM) motor. The well was drilled very slightly modifying the operating procedure.
close to the planned azimuth making build rate more Reservoir conditions at LL 1084: i.e. formation dip
effective, which combined with the good performance of the very close to 0 degrees, permeability of 25 - 30 md, porosity
double bend assembly permitted landing the drain hole 16 of 20 % and of 15 Ohms; required a 56 deg. / 100 ft. build
feet above the plan in the better section of sand, resulting in up rate.
a lower final hole inclination. Geosteering techniques The BHA was virtually identical to the first job
using MWD gamma ray measurements were used to keep except that new 2 7/8 in. S-135 drill pipe was used in the
the drain hole in the pay zone throughout its entire length. curve. The rest of the string was 3 1/2 in. grade G. Rig up
During the planning phase, there was a concern and rig down time was reduced by making small
about the effect of aerated mud, i.e type of fluid, corrosion, improvements to the cable system; like quick connects and
and difficulty of sealing-off with a 4.5 ppg equivalent fluid; an integral float valve / wet connect assembly. The cable
on the downhole motor articulations and power section. only had to be cut to make a connection through the pack
Early articulation designs showed leakage problems when off at the kelly. The connection time to sting in and out of
rotary drilling. Even though the motor was equipped with the wet connect were reduced.
redesigned articulations, potential leaking problems were A 6 1/8 in. drainhole was planned out of a 7 in.
anticipated. casing. This time a whipstock was preferred to open the
On the first run, the short radius system was pulled window and sidetrack, because there was ample space
out of the hole after 24 hrs drilling time and 54 deg. at the available for such type of operation. It was located and set
bit, to verify its condition. No failure was experienced and with a combination of casing collar locator (CCL), a
the motor power section did not suffer any damage. 20 “ gamma ray and a radioactive trace. Even if the distance
drilling hours” later the curve was completed to 84 deg. from the top to bottom of the whipstock was 10 ft, a total of
The same articulated motor was reconfigured to the 21 ft of formation are exposed to the opened window (3 ft
lateral configuration. The articulated motor is designed to above due to the string mill, 8 ft below due to the rathole)
drill the straight section of the hole but has limited power (fig 2). An additional cleaning run with a bit and junk
thus affecting the drilling performance. Therefore, basket was made to drill two feet and recover any steel.
following the first bit run after the curve, the lateral was An articulated down hole motor was used to finalize
drilled using “hybrid motors”, which are almost standard the side track and drill the curve. The initial orientation
downhole motor assemblies. The lateral section was was done with gyroscope. The plan called for a continuous
completed more efficiently with better ROP. build and turn curve, where 60 degrees turn to the left was
The hybrid motor was connected to the rest of the necessary to land the drain hole in the proper position in
BHA with a special flex joint. Several crossovers were the reservoir. The maximum observed build rate was 64
eliminated, including the dump valve (not used with deg/100 ft. It is interesting to note that the build rate
aerated mud) and float valve. This simple modification increased from 5291 ft MD (about 10 %) and the rate of
made it possible to more than double the rate of penetration penetration from 4 ft./hr. to 7.4 ft./hr. At 5300 ft MD a
(from 10 ft/hr to 20 ft/hr) with tricone bits in rotary mode. good quality sand was drilled. The BHA was pulled out of
Throughout the horizontal section, the ROP was up to three the hole to reconfigure the articulated motor for drilling the
times higher than in the curve. During this phase, the lateral section. Reconfiguring the motor took 20 minutes
values of torque and drag were lower than the predicted and it was done on the rig floor. (Changing a motor and
values. Sliding was kept to a minimum with an effective orienting it takes longer).
ROP at around 25% of that of rotary drilling ROP. Drilling The well was relogged using gamma ray (GR)
was stopped after a bad joint of drill pipe broke 3 ft above readings from MWD. It was decided to land five feet lower
the bottom connection. The BHA was fished without any than planned. The short radius articulated motor was
problem. pulled out of the hole as soon as the build up rate required
On this well, 84-ft is the distance from the top of to land was less than 8 deg./100. The hybrid motor was run
window to the landing point. (A system that produces 70 to increase the power output and improve drilling
feet radius will use up more than 70 ft tvd in a re-entry performance. The articulated motor reached a maximum
application) (fig 2.) 6.5 ft/hr in rotary mode. The hybrid motor drilled at up to
21 ft./hr. The bit was pulled after drilling for 32.25 drilling
LL 1084 second job The Reentry Operation hours. The weight on bit was deliberately limited to 8000
The drilling program for LL 1084 was modified pounds in rotary mode, to reduce the risk of buckling the 2
after extensive analysis of LL 1070 recorded drilling data 7/8 in. drill pipe in the vertical part of the hole. A new bit
and operational experience, to improve performance. For was run and additional 2 7/8 drill pipe were added in the
example, the selected equipment was found adequate but BHA.
4 C. INGOLD, J. SALAZAR, J. CARRASQUEL, J. VIDAL, F. RAMIREZ, B. GOURGUES, J. PAREDES SPE 39023

ROPs from 10 ft/hr to 21 ft/hr. were also obtained showed that the B5 formation could be drilled with an ECD
on this bit run. 516 feet were drilled with 5% sliding only. as low as 4 ppg.
The 5% sliding took 14 % of the overall drilling time. The carrying capacity of the aerated mud for a
When the drain hole had almost reached 900 ft it was given liquid flow rate is directly linked to the air injection
decided to call it TD. The bit drilled for 42 hours at an volume. In the range of low liquid and air flow rate (for a
average of 12.3 ft per hour with very low torque and drag fixed air injection rate) increasing mud flow will decrease
values. Bit came out of the hole 1/4 inch undergauge with the carrying capacity. The increase in mud flow will
three loose cones. The BHA had a very light natural elevate mixture density, resulting in a larger drop in
tendency to gain inclination in rotary mode which mixture velocity than in cutting slip velocity.
contributed to improve the drilling performance, as it was The difference between the mixture velocity and the
necessary to direct the drain hole into the higher section of slip velocity reflects the cuttings carrying capacity of the
sand. Losses were experienced at the end of the job. aerated mud.
An estimate of production potential of an horizontal Lack of returns upon resuming drilling, for example
wells can easily be done with a Nodal analysis. The after a connection, does not mean that circulation is lost.
average well in Tia Juana field produces around 200 bopd. Returns have to be established as a new circuit. Pressure
The well LL 1084 produces 1300 bopd. This confirmed the will go up first and will decrease as annulus is lightened up.
economics of short radius aerated mud drilling operations Aerated mud has the drawback of causing corrosion
in this field. caused by oxygen and fluid. Drill pipe corrosion can be
reduced by using organic ester corrosion inhibitor. The
Operating Conditions corrosion inhibitor should be oil soluble and water
Both wells were drilled under overbalance condition dispersible to protect the drill string and casing when in
using an aerated mud system. Air was injected through the contact with hydrocarbons.
stand pipe with the drilling mud to lower the equivalent
circulating density (ECD) to match formation conditions. On the second well, LL 1084, with 185 gpm and
The wellbore support and stability were the same as that of 1000 cu-ft/min of air, the pressure drop never exceeded
a conventional drilling fluid yet minimizing reservoir skin 1800 psi at surface when resuming circulation after trip.
damage and lost circulation. The most frequent question is:
- What is the equivalent amount of fluid as it goes through
Oil, water or gas influx could have been controlled the motor and jets?
by applying a back pressure at the air mud separator control A large volume of air is pumped on surface and is
manifold. Generally the bottom hole pressure did not subject to the following changes (these are approximations
exceed 200 psi over the normal ECD pressure gradient. that pertain to this job):
The mud properties before the injection of air were • The injection pressure (typically 100 psi above the
as follow: pump pressure)
Mud density, ppg 8.6 • Friction pressure which is reduced as fluid goes
Plastic Viscosity, cp 6 to 8 downhole.
Yield Point, lb/100 sq-ft 12 to 16 • Hydrostatic pressure gradient increases as the fluid
Filtrate API, cc 6 to 8 goes downhole
MBT, lb / Bl 5 The increase in hydrostatic pressure is slightly
PH 10 superior to the decrease in friction pressure (except in the
The mud weight was lowered from 8.6 to 4.6 PPG on well lateral). On the average, the actual amount of fluid at the
LL 1084. The aerated mud properties were as follow: stator is around 220 gpm (185 gpm of mud and 35
equivalent gpm of air). Higher volumes would have caused
Air volume, Cu-ft/min: 900 to 1050 over spinning which would have been identified. Note also
Mud volume, gpm: 180 / 185 that the efficiency of an air compressor is reduced with
Injection pressure, (off bottom) psi: 1300 to 1450 altitude and temperature.
Bottom Hole Pressure, psi: 1300 *
Equivalent Circulating Density, ppg 4.7 Other items to watch out for, especially with aerated
Average weight on bit, Klbs: 6 to 8 mud, are as follow:
Average Rotary Speed on surface, RPM: 25 • Are the pumps primed and working?
• Are there returns?
* Annular pressure profile (Fig. 4) • Are we loosing or gaining fluid?
• Is the rotary head properly latched?
The experience obtained in these drilling operations
SPE 39023 A SUCCESSFUL SHORT RADIUS RE-ENTRY WITH AERATED MUD IN VENEZUELA 5

• Is the rotary head leaking? • The drilling efficiency in the lateral section is
• Are we loosing or gaining pressure? negatively affected by the lower power output of
the short radius. Improvements can be achieved by
Any fluctuation of pressure has to be accounted for. customizing the BHA with Hybrid motors to
The motor could be stalled. The wave effect makes it more increase the power available downhole
difficult to read the weight indicator (especially at slow • Natural Corrosiveness of aerated mud system can
ROP). The driller’s console indicates the pit level but with be controlled, but is always present.
another limitation: the pit level changes with the wave • Drilling from floater with aerated mud can be
effect: a wash out could be developing. A change in complex especially at slow ROP, when the wave
compressor or mud efficiency could also change effect creates fluctuation on weight on bit.
substantially pressure drop. After each connection, • Planning a short radius reentry well requires
pressure starts off higher and takes as much as one hour to additional distance for the window opening and
stabilize to the previous value. If for any reason the mud initial rat hole. A 70 ft. radius system may require
pump is cut down or reduced, the well can “unload” with as much as 90 ft. in a reentry application to
little notice. go from 0 to 90 degrees.
As depth increases the air injection rate has to be • In case of reduced TVD to reach horizontal, a
increased to stay close to balance. Pressure on bottom will section milled window is preferred over the
be increased if air injection is reduced (keeping mud flow whipstock. A whipstock creates a 15 deg./100 dog
rate constant). Pressure on bottom will be decreased if air leg severity over a 20 ft interval, while with the
injection is increased. A jet sub can be installed in the section milled window it is possible to reach 40
string to increase hole cleaning and help returns. It would deg./ 100
be placed at about twice the depth of the static level of the Modern one trip whipstock systems have an
well. When a trip is made, metal displacement has to be additional drawback. They expose more
accounted for. Once the bit reaches the static level no more formation as the whipstock is longer and the
fluid needs to be added. A sonolog can help determine rathole is deeper
whether fluid needs to be added. Normally one sonolog is • Section milled window results in a smoother curve
taken once the bit is at the window. The static level on LL- profile.
1084 was around 2750 ft below rotary. A survey taken An additional benefit is that the number of
shortly after drilling may indicate much less. gyroscope orientation surveys can be reduced. A clean
reading of the azimuth without magnetic interference is
Summary obtained when MWD directional sensor package is across
Both of these wells, LL 1070 and LL 1084 were the section. (Fig. 5).
operational successes. Benefits and advantages of On the average job this is what happens:
whipstock versus section milling were identified. Lateral
sections were drilled very effectively with minimum sliding a- With a Whipstock:
time, especially on the second well. The MWD / gamma ray - The first 60 feet (below whipstock) are drilled without a
measurements were adequate to navigate inside the pay reliable azimuth data.
zone. These wells have demonstrated the technical - When the first valid azimuth appears, there is 45 deg of
competitiveness of short radius technique. Overall drilling drift at the bit.
performance and rate of penetration in the curve and in
laterals improved on the second job, specially due to the b- With Section milling (45 ft. section):
ability to control the BHA behavior. The operating - The first 25 ft. (below top of section) are drilled without
procedures with the cable were improved, leading to a 30 % reliable azimuth data.
time saving (connection time, the rig up time, wet connect - The next 29 ft. -from 25 to 54 ft- are drilled with valid
operation.) information.
The success of this project will lead to more short- - The next 10 ft may be drilled without a valid azimuth
radius wells drilled with aerated mud on lake Maracaibo, At that point the well should be lined up to the
where multilaterals are also considered but promise to be desired azimuth: the short blind interval is not critical as
more complex to design. gravity toolface may be used.

Conclusions • An improperly set whipstock has a negative impact in the


• Short radius drilling can save one casing final quality of the curve generating additional torque and
• The curve is drilled at a slower ROP but is drag till TD.
shorter (3 to 6 times)
6 C. INGOLD, J. SALAZAR, J. CARRASQUEL, J. VIDAL, F. RAMIREZ, B. GOURGUES, J. PAREDES SPE 39023

• Hexagonal kelly or drill pipe are easier to seal off than found close to each end of the non-magnetic element of the
square kelly. BHA. Even if anti-corrosion agents injected to the drilling
• Better quick connects with ready made float valve have fluid have reduced the corrosion effect, placement of
reduced rig up time. Quick connect that can be run through corrosion rings at each end are considered. Corrosion rings
pack offs will save extra time. are already used in the drill pipe to monitor corrosion.
• The use of a top drive would make a hard wired modified Another aspect of paramount importance in short-
retrievable MWD almost as fast and easy to use as an radius drilling is the quality of the curve in terms of
electromagnetic one. smoothness. A tortuous curve with inconsistent build up
• Drilling underbalance, probably with coiled tubing and rates, where the presence of higher than expected micro
nitrogen will also be considered for the future wells. It is doglegs creates points with stresses concentration resulting
advisable to gain more experience before doing so. in extremely high “true” forces acting on the string, far
above calculated values: as a consequence, there is an
Possibility of using Electromagnetic MWD system: accelerated fatigue process and early failure. In addition,
Electromagnetic MWD eliminates the need for a any tortuosity will add some extra drag and torque, limiting
cable -except for gyroscope surveying- and all associated the capability to reach long displacement. In other words
operations. One supplier was contacted but had two the curve is what takes place first. It will affect drilling the
problems: lateral until the end.
• The directional survey package could not be moved down
(the measurement point would be located 34 ft above the bit Nomenclature
instead of 17). As a consequence it would take around 44 DLS = dogleg severity (X / 100 ft)
feet to evaluate BHA response or 40 % of the curve length. BUR = Build up rate (X / 100 ft)
This could be too late for taking proper corrective action to DNI = MWD directional sensor package
land the well in target. In the case of a whipstock, a clean CFM = Cubic Foot per Minute
azimuth reading would require having 80% of the curve NMDC = Non Magnetic Drill Collar
drilled. PDM = Positive Displacement Motor
• Maximum operating conditions for the electromagnetic
MWD system were limited to 60 deg./100 ft dog leg Formula for equivalent gpm going through PDM
severity which is far below the project requirements. (This is for air drilling and has to be adapted for aerated
mud)
Possibility for Short Radius Multilateral wells: P1 = Atmospheric Pressure ( -14.7 psi)
To have successful multilateral wells, some of the V1 = Compressor Rated Output (CFM)
inherent problems associated with production mechanisms P2 = Standpipe Pressure
in these type of wells, i.e. cross flow, have to be solved. V2 = CFM delivered to downhole Motor
• Multilaterals through milled window or whipstock are
feasible with bare foot or drop-in liner completion Pick gpm from Motor Specifications.
• In the case of a section milled window, the circulation
losses through the first well are a risk. V2 = gpm : 7.48 gal/cu. ft = CFM (delivered to PDM)
• A retrievable whipstock is probably the better option for V2 = P1V1(0.455) : (P2)
multilateral drilling from a common cased trunk. V1 = P2V2 : (P1 x 0.455)
• Multilaterals in the same zone may require the
combination of short and ultra short radius technique. 0.455 = Assumed efficiency of the compressor and motor
combined
Avoiding fatigue and corrosion
Short radius drilling techniques are very particular. Acknowledgments
Many of the rules for classical rotary drilling do not apply. We thank Lagoven S.A for their assistance and technical
Short crossovers and tool joints are recommended to add support in preparation of this paper.
flexibility and reduce stress concentration in the drill string
and BHA components. Contributors: Jaime Bernardini, Ulf Remahl, Peter Ellice,
The connections should not be equipped with stress Duilio Olmo, Beltran Marin (Anadrill)
relief and bore-back grooves just like on ordinary drill pipe. Paul Neumann (Gyrodata)
The extra length required to recut the connection increases
rigidity and fatigue on tubes. References
Stress relief and bore back grooves can accelerate 1. Hill, D., Askew, W., Tracy, P., Koval, V.: “A Predictable
fatigue in a corrosive environment. Severe pitting was and Efficient Short Radius Drilling System.” Paper
SPE 39023 A SUCCESSFUL SHORT RADIUS RE-ENTRY WITH AERATED MUD IN VENEZUELA 7

IADC/SPE 35049 presented at the 1006 IADC/SPE


Drilling Conference held in New Orleans, Louisiana, 12-
15 March 1996.
2. Black Max Motor Manual
3. William J. Tank, Short-Radius Horizontal Drilling
System Optimization in Yates Field Unit Provides
Excellent Directional Control and Highly Economical
Completions. Paper published in March 1997 SPE
Drilling and Completion.

SI Metric Conversion Factors


ft. x 3.048* E -01 =m
in. x 2.54* E +00 = cm
* Conversion factor is exact
LL1084

ANNULAR PRESSURE PROFILE

1200

1000
Run #1
Run #2
800 Run #3
B.H.P. PSI

Run #4
Run #5
600 Run #6
Run #7

400

200

0
0

1000

2000

3000

4000

4414

4414

4774

4774

5000

5000

5180

5180

6000

6044

6044

6127

6127

6128
DEPTH FT

FIG 4

Potrebbero piacerti anche