INSTALLTION OF LACT UNIT, GAS METERING SKID AND THEIR INTERCONNECTING PIPING.

ITEM ACTIVITY UNIT QTY


1 ENGINEERING VERIFICATION L/S 1
2 CONSTRUCTION PROCEDURES, SPECIFICATION AND RECORDS L/S 1
3 MOBILIZATION & DEMOBILIZATION OF PERSONNEL L/S 1
4 WELDER'S PRE-QUALIFICATION AND QUALIFICATION ACTIVITIES L/S 1
5 PROVISION OF PIPING MATERIALS TO WORK SHOP L/S 1
6 PROVISION OF PIPE SUPPORT MATERIALS TO WORK SHOP L/S 1
7 PROVISION OF TOOLS & EQUIPMENT RESOURCES(INCLUDING CRANE) L/S 1
8 PROVISION OF WELDING CONSUMABLES AND EQUIPMENTS L/S 1
9 PROVISION OF SAFETY & PPEs GADGETS L/S 1
PERSONNEL RESOURCES AND ENGAGEMENT ( Fabrication - Fit up
10 (Grinding / cutting & Welding )) L/S 1
11 NDT QUALITY TESTING & PWHT AND ACCEPTANCE L/S 1
12 HYDRO TEST AND NITROGEN PURGING L/S 1
PAINTING MATERIALS, QUALIFICATION, BLASTING AND PAINTING ACTIVITIES,
13 TESTING AND ACCEPTANCE L/S 1
14 TAGGING, STACKING, STORAGE AND PACKAGING L/S 1
15 SITE LOGISTICS. (Handling &Lifting) L/S 1
16 LACT UNIT AND GAS METERING SKID INSTALLATION ON SITE L/S 2
17 PIPING INSTALLATION ON SITE L/S 1
18 HOUSE KEEPING (Removal of waste materials ) L/S 1
SUB TOTAL
VAT 5%
NIGERIAN CONTENT DEVELOPMENT
TOTAL
ONNECTING PIPING.

RATE AMOUNT
500,000.00 500,000.00
200,000.00 200,000.00
300,000.00 300,000.00
285,151.00 285,151.00
3,425,860.00 3,425,860.00
800,000.00 800,000.00
1,286,750.00 1,286,750.00
290,750.00 290,750.00
250,000.00 250,000.00

4,720,630.00 4,720,630.00
1,280,000.00 1,280,000.00
450,000.00 450,000.00

1,400,000.00 1,400,000.00
60,000.00 60,000.00
250,000.00 250,000.00
250,000.00 500,000.00
560,000.00 560,000.00
125,000.00 125,000.00
16,684,141.00
834,207.05
166841.41
17,685,189.46