Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Alan McSweeney
Core Dimensions Of Projects
Project Stages/Timeline
March 2, 2014 2
Integrated Project Business Engagement Model
March 2, 2014 3
Components Of Integrated Project Delivery And
Business Engagement Model
Stages
S
Artefacts A A Activities
G
Gates
March 2, 2014 4
Extended Dimensions Of Project Delivery
Project Review and Decision Gates
IT And
Business Artefacts
Functions/
Roles/
Activities
Project Stages/Timeline
March 2, 2014 5
Extended Dimensions Of Project Delivery
Function
Organisation
Readiness
Service
Management
Infrastructure
and
Communications
March 2, 2014 7
Integrated Project Delivery Process And Business
Engagement Model
• Take an artefacts- and results/deliverables-based
integrated approach with review gates where go/no-go
decisions are made
• Across all project phases and project delivery roles
• Focus on getting the project right at the start will yield
benefits
• Provides a complete view of what has to be achieved
• Allows project status to be assessed
• Allows effort to be quantified across all stages and
resources
• Designed to reduce risk of project failures
March 2, 2014 8
Integrated Project Delivery Process
Functionality
More Expensive Delivered Does not
to Operate Than Meet Business
Planned Requirements
Solution Largely
Unused And/Or
Unusable
Complete Project
Success: Increasing Frequency/
On-time, On-budget Complete Project
and Delivering
Probability of Failure: Cancelled,
Specified Benefits Occurrence Unused, Rejected
March 2, 2014 10
Project Failures
March 2, 2014 11
Reasons For Project Failures
March 2, 2014 12
Artefacts/Deliverables Define Across Project
Delivery Process
Time
Function
March 2, 2014 13
Artefacts/Deliverables
March 2, 2014 14
Artefact View Of Integrated Project Delivery Process
Concept Initiate Plan Design Build Test Deploy Operate
Project Charter Project Plan Project Management – Planning, Resource, Scheduling
Project Risk, Actions, Issues and Dependencies Management
Project Initiation Project Resource Plan Reporting and Communications Management
Management Document Change Management
Solution Concept/ Business Case Benefits Schedule and User Acceptance Test Benefits Realisation
Business Requirements Benefits Realisation Results Review
Function Document Plan Lessons Learned
Functional To Be Process User Acceptance Test Documentation Library
Business Requirements Definition Design and Plan
Analysis As Is Process Definition Standard Operating
Procedures
Rough Order of Solution Architecture Non Functional
Solution Magnitude Estimate High Level Design Requirements
Detailed Solution
Architecture Design/ Functional
Specification
Data Audit Confirmed Estimates Data Migration Results Data Migration Test Data Migration to Live Go Live Support
Data Design and Data Build Documentation Results
Configuration System Test Plan
Management Approach Migration Plan Unit Test Results Results Deploy to Production
Delivery and Plan Technical/Build UAT Changes and
Results
Integration Test Results Support and Operations
Detailed Estimates Specification Rework
Documentation
Test Strategy Functional Test Design Functional Test Results Operational Readiness
and Plan Non-Functional Test Review
Non-Functional Test Results
Design and Plan
Test and Quality Integration Test
Integration Test Design Results
and Plan System Test Results
System Test Design
and Plan
Management Team Change Impact Change Action Plan Role Definition Organisation and
Briefing Assessment Staffing
Organisation Detailed
Organisation Design Training Schedule Implementation
Communications Develop Training
Readiness Strategy and Plan Communications Plan
Material
Training Delivery
Training Needs Analysis
Service Impact Service Level Operations Acceptance Operations Acceptance Service and
Assessment Requirements Testing Design and Plan Testing Results Operational Level
Service Agreement(s)
Access and Security Service Definition
Management Definition Transfer to Production
Plan
Infrastructure Plan Infrastructure Design Build Test Environment Build Training Build Production Decommission Unused
Infrastructure Technical Build UAT Environment Environment Environment Environments
Infrastructure Specification Build OAT Environment
Build Development
Environment
March 2, 2014 15
Artefact View Of Integrated Project Delivery Process
March 2, 2014 16
Artefact View Integrates Different Activity Lifecycles
Strategy, Business Planning and Business Analysis
Plan Close
Implement
Setup and
Manage Evolve
Prepare
Develop Test Deploy
March 2, 2014 17
Initial Focus Area – Business Engagement And
Solution Definition
Time
Getting This
Right … Project Stages/ Timeline
Manage
Concept Initiate Plan Design Build Test Deploy and
Operate
Project
Management
Business
Focus on these project stages
Project Activity/ Function
Organisation
Readiness
Service
Management … Means Problems
Infrastructure Will Be Avoided At
and
Communications Later Stages
March 2, 2014 18
Artefact View Of Initial Focus Area – Business
Engagement And Solution Definition
Concept Initiate Plan Design
Functional To Be Process
Requirements Definition
Business Analysis Non Functional
As Is Process
Definition Requirements
March 2, 2014 20
Initial Focus Area – Business Engagement And
Solution Definition And Validation
• Have a defined solution to meet a defined and articulated
business need that will deliver a realisable and achievable
set of business benefits
• Understand the complexity of what has to be delivered
March 2, 2014 21
Initial Focus Area – Business Engagement And
Solution Definition And Validation
• Ensures there is a strong and solid foundation for solution
implementation, delivery and management and operation
March 2, 2014 22
Initial Focus Area – Business Engagement And
Solution Definition And Validation
Getting Time
These Wrong
… Project Stages/ Timeline
Manage
Concept Initiate Plan Design Build Test Deploy and
Operate
Project Solution Concept/ Requirements
Management
Business
Business Case
Project Activity/ Function
Organisation
Readiness
Service
Management
… Means Problems
Infrastructure
and
Communications
Will Occur During
The Project
March 2, 2014 23
Initial Focus Area – Business Engagement And
Solution Definition And Validation
• Where there are gaps in the foundation on which solution
implementation is being based, the project is at significant
risk of failure
March 2, 2014 24
Weaknesses In Business Analysis And Solution Design
Capabilities At The Root of Many Project Failures
Poor Size/Capacity/ Poor Strategic
Requirements Complexity Alignment
Poor Analysis Large Project, Inadequate Business
Practices Complex, Difficult Case, Undefined
Changes and Processes Problem/Need
Business Requirements Large Project Team and Business Benefits Business Needs
Not Captured Multiple Stakeholders Not Measured Not Met
Opportunities
Lost
Investment
Inadequate Resource Unproven Technology Inadequately Explored Wasted
Allocation and Solution Options
Prioritisation
Business Requirements Large Project Team and Business Benefits Business Needs
Not Captured Multiple Stakeholders Not Measured Not Met
Opportunities
Lost
Investment
Inadequate Resource Unproven Technology Inadequately Explored Wasted
Allocation and Solution Options
Prioritisation
Function
Gate 3
Gate 6
Gate 1
Gate 2
Gate 4
Gate 5
Gate 7
Implementation
and Delivery
Organisation
Readiness
Service
Management
Infrastructure
and
Communications
March 2, 2014 27
Project Gates
Phase Phase
Project
Stopped
Sent Back for
Rework
STOP
March 2, 2014 29
Project Process Gates
Gate 0 Gate 1
Gate 4 Gate 3
Gate 6 Gate 7
Deploy Operate
March 2, 2014 30
Project Process Gates
Gate 0 Gate 1
Gate 4 Gate 3
Business Solution Concept/ Business Case Benefits Schedule and User Acceptance Test Benefits Realisation
Requirements Benefits Realisation Results Review
Function Document Plan Lessons Learned
Functional To Be Process User Acceptance Test Documentation Library
Business Requirements Definition Design and Plan
Analysis As Is Process Definition Standard Operating
Procedures
Rough Order of Solution Architecture Non Functional
Solution Magnitude Estimate High Level Design Requirements
Architecture Detailed Solution
Design/ Functional
Specification
Data Audit Confirmed Estimates Data Migration Results Data Migration Test Data Migration to Live Go Live Support
Data Design and Data Build Documentation Results
Configuration System Test Plan
Management Approach Migration Plan Unit Test Results Results Deploy to Production
Delivery and Plan` UAT Changes and
Results
Technical/Build Integration Test Results
Specification Rework Support and Operations
Detailed Estimates Documentation
Test Strategy Functional Test Design Functional Test Results Operational Readiness
and Plan Non-Functional Test Review
Non-Functional Test Results
Design and Plan
Test and Quality Integration Test Design
Integration Test
Results
and Plan System Test Results
System Test Design
and Plan
Management Team Change Impact Change Action Plan Role Definition Organisation and
Briefing Assessment Staffing
Organisation Detailed
Organisation Design Training Schedule Implementation
Communications
Readiness Strategy and Plan Communications Plan Develop Training Training Delivery
Material
Training Needs Analysis
Service Impact Service Level Operations Acceptance Operations Acceptance Service and
Service Assessment Requirements Testing Design and Plan Testing Results Operational Level
Access and Security Agreement(s)
Management Service Definition
Definition Transfer to Production
Plan
Infrastructure Plan Infrastructure Design Build Test Environment Build Training Build Production Decommission Unused
Infrastructure Technical Build UAT Environment Environment Environment Environments
Infrastructure Specification Build OAT Environment
Build Development
Environment
March 2, 2014 33
Consistent View Of Projects
March 2, 2014 34
Artefact-Based Status View Of Project
March 2, 2014 35
Summary
March 2, 2014 36
More Information
Alan McSweeney
http://ie.linkedin.com/in/alanmcsweeney
March 2, 2014 37