CUADRO DE CANTIDADES Y PRECIOS Pag.

1 de 3
INFRAESTRUCTURA FISICA PARA EL ACOPIO Y COMERCIALIZACION DE CAFÉ DEPARTAMENTO DEL HUILA
ASOCIACION DE PRODUCTORES PRIMAVERAL - ACEVEDO HUILA

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


1 PRELIMINARES
1.1 LOCALIZACION Y REPLANTEO MANUAL M2 183.28 3,425 627,734
1.2 DESCAPOTE MANUAL E=0.20m, INCLUYE RETIRO DE MATERIALES M3 36.66 14,689 538,499
1.3 CERRAMIENTO EN LONA H=2.0m ML 64.2 22,430 1,440,006
1.4 CONSTRUCCION Y/O ALQUILER DE CAMPAMENTO GL 1 1,000,000 1,000,000
SUBTOTAL PRELIMINARES 3,606,239
2 CIMENTACION
2.1 EXCAVACION MANUAL EN MATERIAL COMUN (INCLUYE RETIRO) M3 86.84 23,692 2,057,413
2.2 RELLENO EN SUELO CEMENTO COMPACTADO 95%PM E=0.45m M3 20.33 76,903 1,563,438
2.3 SOLADO DE LIMPIEZA EN CONCRETO 2500PSI E=0.05m M3 3.18 381,973 1,214,674
2.4 CONCRETO CICLOPEO (40% PIEDRA MEDIA ZONGA Y 60% CONCRETO DE M3 3.65 399,378 1,457,730
2500 PSI) PARA BASES
2.5 CONCRETO DE 3000 PSI PARA ZAPATAS M3 18.46 571,254 10,545,349
2.6 VIGA DE CIMENTACION EN CONCRETO DE 3000 PSI M3 9.28 612,259 5,681,764
2.7 ACERO DE REFUERZO 60000 PSI PARA CIMENTACION KG 3,109.15 4,349 13,521,693
2.8 VIGUETA DE SOBRECIMIENTO EN CONCRETO DE 3000 PSI 0.15X0.20 ML 24.9 51,738 1,288,276
INCLUYE ACERO
SUBTOTAL CIMENTACION 37,330,337
3 ESTRUCTURA
3.1 COLUMNAS EN CONCRETO DE 3000 PSI M3 24.28 669,335 16,251,454
3.2 VIGA DE AMARRE EN CONCRETO DE 3000 PSI M3 49.95 668,748 33,403,963
3.3 ACERO DE REFUERZO 60000 PSI PARA ESTRUCTURA KG 9,048.43 4,349 39,351,622
3.4 PLACA EN METALDECK 2" CAL 22 PERFILPHR 220X80X20 (1.50MM) M2 310.22 210,009 65,148,992
CAJON
3.5 COLUMNETA 0,20 X 0,15 EN CONCRETO DE 3000 PSI, INCLUYE REFUERZ ML 45 64,806 2,916,270
3.6 VIGUETA DE CONFINAMIENTO EN CONCRETO DE 3000 PSI 0.15X0.20 ML 27.41 51,738 1,418,139
INCLUYE ACERO
3.7 LOSA MACIZA PARA ASCENSOR SEGÚN DISEÑO, INCLUYE ACERO M2 11.1 286,113 3,175,854
3.8 VIGA CANAL EN CONCRETO 3000 PSI SEGÚN DISEÑO, INCUYE ACERO ML 22.8 88,914 2,027,239
3.9 ESCALERA MACIZA EN CONCRETO DE 3000 PSI, INCLUYE ACERO M3 3.7 1,263,885 4,676,375
3.10 PANTALLA EN CONCRETO REFORZADO DE 3000 PSI PARA ASCENSOR, M3 12.99 1,146,622 14,894,620
SEGÚN DISEÑO, INCLUYE ACERO
3.11 PLACA MACIZA EN CONCRETO DE 3000 PSI PARA TANQUES, INCLUYE M2 12.6 197,296 2,485,930
ACERO
3.12 VIGA DE CORONA EN CONCRETO DE 3000 PSI, SECCION DE 0,12 X 0,10 M ML 54.6 55,613 3,036,470
INCLUYE ACERO DE REFUERZ
SUBTOTAL ESTRUCTURA 188,786,928
4 MAMPOSTERIA
4.1 MURO EN LADRILLO BLOQUE N°5 M2 664.44 25,466 16,920,629
4.2 MESONES EN CONCRETO TERMINADOS EN GRANITO PULIDO ML 11.57 160,125 1,852,646
SUBTOTAL MAMPOSTERIA 18,773,275
5 CARPINTERIA METALICA
5.1 PORTON METALICO PARA FACHADA SEGÚN DISEÑO, INCLUYE M2 11.48 260,973 2,995,970
MATERIALES, MANO DE OBRA, HERRAMIENTA Y
5.2 PUERTA METALICA SEGÚN DISEÑO, INCLUYE MATERIALES, MANO DE M2 3.04 185,553 564,081
OBRA, HERRAMIENTA Y EQUIPO
5.3 VENTANA EN ALUMINIO TIPO PESADA SEGÚN DISEÑO M2 53.22 268,684 14,299,362
5.4 PUERTA VENTANA EN ALUMINIO TIPO PESADA SEGÚN DISEÑO M2 22.94 388,684 8,916,411
5.5 DIVISIONES EN ALUMINIO SEGÚN DISEÑO M2 60.92 176,362 10,743,973
5.6 PUERTAS EN ALUMINIO SEGÚN DISEÑO M2 17.2 258,862 4,452,426
5.7 BARANDA EN ALUMINIO PARA BALCON, SEGÚN DISEÑO ML 6.05 199,431 1,206,558
SUBTOTAL CARPINTERIA METALICA 43,178,781
6 CARPINTERIA MADERA
6.1 PUERTAS EN MADERA ENTAMBORADA SEGÚN DISEÑO INCLUYE MARCO M2 17.2 160,000 2,752,000
SUBTOTAL CARPINTERIA MADERA 2,752,000

OBRAS 1.8, www.master-soft.net


Pag. 2 de 3

7 CUBIERTA Y ESTRUCTURA DE CUBIERTA


7.1 SUMINISTRO E INSTALACION DE CUBIERTA EN TEJA MASTERMIL M2 151.69 61,971 9,400,381
7.2 CORREA METALICA PHR 160X60X20 (1.20mm) ML 134.9 22,657 3,056,429
7.3 CIELORASO EN DRYWALL M2 416.76 47,980 19,996,145
SUBTOTAL CUBIERTA Y ESTRUCTURA DE CUBIERTA 32,452,955
8 PAÑETES
8.1 PAÑETE LISO MUROS 1:4 INCLUYE FILOS Y DILATACIONES M2 1,328.88 27,076 35,980,755
SUBTOTAL PAÑETES 35,980,755
9 PISOS Y ENCHAPES
9.1 RELLENO EN RECEBO COMPACTADO E=0.25m M3 45.82 35,737 1,637,469
9.2 PLACA BASE EN CONCRETO 2500 PSI E=0.07m M2 183.28 35,929 6,585,067
9.3 ALISTADO PISOS E=0.04m M2 45.72 15,474 707,471
9.4 PISO EN CERAMICA TRAFICO PESADO M2 479.57 48,999 23,498,450
9.5 GUARDAESCOBA EN CERAMICA ML 401.29 6,106 2,450,277
9.6 ENCHAPE PARA BAÑOS M2 110 52,533 5,778,630
9.7 SUMINISTRO E INSTALACION DE FACHALETA, SEGÚN DISEÑO M2 15 55,154 827,310
SUBTOTAL PISOS Y ENCHAPES 41,484,674
10 INSTALACIONES HIDRAULICAS
10.1 ACOMETIDA ACUEDUCTO 1" UND 1 296,436 296,436
10.2 TUBERIA PVC PRESION 1" ML 71.4 8,128 580,339
10.3 TUBERIA PVC PRESION 3/4" ML 11.5 6,980 80,270
10.4 PUNTO DE AGUA FRIA PVC 1/2" UND 21 37,315 783,615
10.5 TANQUE DE ALMACENAMIENTO SUBTERRANEO (2.0X2.0X1.50m) INCLUYE UND 1 2,992,781 2,992,781
MATERIALES, EQUIPO Y MANO DE
10.6 SUMINISTRO E INSTALACION DE ELECTROBOMBA 1HP UND 1 881,809 881,809
10.7 TUBERIA PVC PRESION 1 1/2" ML 42.9 13,436 576,404
10.8 SUMINISTRO E INSTALACION DE TANQUE DE ALMACENAMIENTO UND 4 550,894 2,203,576
ELEVADOS CAP 1000 LTS
10.9 SUMINISTRO E INSTALACION DE RED CONTRAINCENDIO EN TUBERIA HG ML 23.43 192,929 4,520,326
1/2", INCLUYE: MATERIALES,
10.10 SUMINISTRO E INSTALACION DE GABINETE TIPO III, INCLUYE: MATERIALE UND 3 1,700,000 5,100,000
EQUIPO, MANO DE OBRA Y
SUBTOTAL INSTALACIONES HIDRAULICAS 18,015,556
11 INSTALACIONES SANITARIAS Y PLUVIALES
11.1 CAJAS DE INSPECCION DE 1.0X1.0 UND 7 228,962 1,602,734
11.2 CAJAS DE INSPECCION DE 0.80X0.80 UND 1 182,480 182,480
11.3 TUBERIA PVC 4" SANITARIA Y A.LL ML 79.4 30,954 2,457,748
11.4 TUBERIA PVC 3" SANITARIA Y A.LL ML 79.4 21,609 1,715,755
11.5 TUBERIA PVC 2" SANITARIA ML 16.5 17,092 282,018
11.6 PUNTO DESAGUE 2", 3", 4" UND 31 45,000 1,395,000
SUBTOTAL INSTALACIONES SANITARIAS Y PLUVIALES 7,635,735
12 INSTALACIONES ELECTRICAS
12.1 INSTALACIONES ELECTRICAS (SEGUN PRESUPUESTO ELECTRICO GL 1 12,762,721 12,762,721
ADJUNTO)
SUMINISTRO E INSTALACION DE RED DE VOZ Y DATOS GL 1 17,646,737 17,646,737
SUBTOTAL INSTALACIONES ELECTRICAS 30,409,458
13 EQUIPO Y ACCESORIOS
13.1 COMBO SANITARIO BLANCO (SANITARIO Y LAVAMANOS) UND 6 418,941 2,513,646
13.2 ORINAL UND 3 443,718 1,331,154
13.3 LAVAPLATOS EN ACERO INOXIDABL UND 2 200,576 401,152
13.4 SUMINISTRO E INSTALACION DE ASCENSOR MAQUINA GEARLESS, UND 1 120,000,000 120,000,000
INCLUYE EQUIPOS,ACCESORIOS, INSTALA
SUBTOTAL EQUIPO Y ACCESORIOS 124,245,952
14 ESTUCOS Y PINTURAS
14.1 ESTUCO Y VINILO TIPO I TRES MANOS M2 921.07 10,691 9,847,159
SUBTOTAL ESTUCOS Y PINTURAS 9,847,159
15 ASEO GENERAL
15.1 ASEO GENERAL ENTREGA M2 183.28 3,725 682,718

OBRAS 1.8, www.master-soft.net


Pag. 3 de 3

SUBTOTAL ASEO GENERAL 682,718

COSTO DIRECTO 595,182,522


COSTO INDIRECTO (21.52%) 128,083,279
COSTO TOTAL 723,265,801

DETALLE DEL COSTO INDIRECTO


Administración 10% 59,518,252
Imprevistos 2% 11,903,650
Utilidad 8% 47,614,602
IVA sobre Utilidad 19% 9,046,774

OBRAS 1.8, www.master-soft.net