Table of Contents
OBJECTIVE ................................................................................................................................ 1
RESOURCES .................................................................................................................................5
Personnel .............................................................................................................................5.1
Equipment ........................................................................................................................5.2
Program of work……………………………………………………………………………………6
Preliminary site
investigation………………………………………………………………………………………….6.1
site clearance......................................................................................................................6.3
1. Objective
This document specifies methods and procedure accordance with
construction drawing and adhering to applicable specifications with
consideration to local rules and regulations.
2. SCOPE OF APPLICATION
The scope of this document is confined to civil construction pilling
works, which are listed below. These include material, machineries,
workforce, temporary activities & materials, mobilization and
demobilization of the team & stuff assigned to complete the pilling
scope. All the pilling activities to be performed in accordance with
relevant international codes & standards or recognized good
engineering practice
Method of statement
4. REFERENCE DOCUMENTS
5. RESOURCES
5.1 Personnel
Work will be carried out by qualifies personnel as
below
Civil Engineers.
Surveyor
QA QC civil engineer.
Skilled labors.
5.2 Equipment
6.PROGRAM OF WORK
As per the site condition all the earth works shall be limited to the area
inside the plot boundary.
The entire are required for construction of fire water tank will be
identified and marked with chalk powder (white) and will be barricaded
with a suitable hard barricading material with access
The surveyor should establish all the control point (through primary
datum line) in respect to lines/ grids, lines/cut lines, install and maintain
The reference marks, benchmarks, and maintain them as long as
required for setting out.
Method of statement
7.Sequence of works
The pile driving rig from Delmag company .
The length of pile is 13 m and two piles have to be driven for each
location = 26 m and the remaining above ground portion is 1 meter to
be demolished later on and tie rebar with foundation .
Pitching of the pile is carried out by looping the chain around the pile
approximately 1 m from the end and winching up into the helmet of the
hammer by rig operator
Set up piling rig with the pitched pile over the marked position then the
driver placed the pile onto the ground
Then the driver lowers service winch and proceeds to operate driving
hammer at low drop height until the pile has safely entered the ground
Pile is then driven to the required height which is one meter above the
ground for each phase of pitching process. and as the picture below
Method of statement
The pitched pile dose not satisfy the designated depth in the
drawing in our case. Then we have to pitch another pile, this pile
will be tied to the bottom of the pitched pile by welding plate to
the second plate for all four sides side as shown below.
Jointing is carried out by placing the pitched pile over the driven
pile, removing dirt that cover of the pitched pile by the assistance
And lowering of the pitched pile on the top of the driven pile by
the rig driver with direction from the assistant. Jointing in our
proposed tie connection
The pile is checked for the vertical plum again. Then the service
Method of statement
control measures
always check the manufacture handbook for instruction regarding
pilling rig
always carry out a walk through survey of the site before bringing the
rig into the operation zone
inspect all the site maps relating to the ground works to identify if there
are any underlying services present that need to be highlighted
all the driver will be trained and competent to operate the pile rig
when pitching a new pile, the assistant must ensure that the chain is
not twisted by using looping technique
The ground on which the rig has to operate must be inspected so as to
ensure its stability and that excavation don’t pose a threat of
overturning to the operatives
The joining of the pile must have done safely and the assistant to the
pilling rig operator must be wearing gloves and he does not tray to
align pile by feeling with his finger, he must remove the plastic dirt
covers and then he directed the rig operator to lower the pitch pile on
the top of driven pile and after joining process can proceed
Only the authorized person may operate in the vicinity of piling rig
Method of statement