Sei sulla pagina 1di 29

CERTIFICADO DE PAGO No.

02

"SUMINISTRO, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y


OBRA : PUESTA EN SERVICIO PARA "AMPLIACION DE REDES DE MT Y BT
UU.NN. HUANUCO PARTE II"
VALORIZACION No. : 02
MES DE VALORIZACION : FEBRERO
AÑO DE VALORIZACION : 2008
CONTRATO : GR-126-2007/ELECTROCENTRO

ITEM DESCRIPCION UND

1 SUMINISTRO DE EQUIPOS Y MATERIALES 129,810.00

2 MONTAJE ELECTROMECANICO 13,974.51

3 DESMONTAJE

4 TRANSPORTE 14279.10

5 COSTO DIRECTO (C.D.) 158,063.61

6 GASTOS GENERALES 36,486.28

7 UTILIDADES 15,806.36

8 TOTAL GENERAL SIN IGV 210,356.25

9 AMORTIZACION DE ADELANTO 42,071.25

10 COSTO NETO A CANCELAR 168,285.00

11 IGV (19%) 31,974.15

12 MONTO TOTAL A CANCELAR 200,259.15


CUADRO RESUMEN GENERAL

OBRA : "SUMINISTRO, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA AMPLIACION DE REDES DE MT Y BT UU.NN. HUANUCO PARTE II"

MES DE VALORIZACION : FEBRERO

AÑO DE VALORIZACION : 2008

CONTRATO : GR-126-2007/ELECTROCENTRO

METRADO BASE ACUMULADO MES ANTERIOR VALORIZACION No. 02 ACUMULADO TOTAL


ITEM DESCRIPCION %
BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL

I SUMINISTRO DE EQUIPOS Y MATERIALES 717,255.06 718,003.27 1,435,258.33 0.00 0.00 123,978.00 5,832.00 129,810.00 123,978.00 5,832.00 129,810.00

II MONTAJE ELECTROMECANICO 372,614.18 260,287.13 632,901.31 10,274.46 1,903.48 12,177.94 2,643.90 11,330.61 13,974.51 12,918.36 13,234.09 26,152.45

III DESMONTAJE 9,187.11 2,898.81 12,085.92 0.00 0.00 0.00 0.00 0.00 0.00

IV TRANSPORTE 11% 78,898.06 78,980.36 157,878.42 0.00 0.00 0.00 13,637.58 641.52 14,279.10 13,637.58 641.52 14,279.10

V COSTO DIRECTO (C.D.) 1,177,954.41 1,060,169.57 2,238,123.98 10,274.46 1,903.48 12,177.94 140,259.48 17,804.13 158,063.61 150,533.94 19,707.61 170,241.55

VI GASTOS GENERALES 23.08% 271,910.58 244,721.97 516,632.55 2,371.68 439.39 2,811.07 32,376.50 4,109.78 36,486.28 34,748.18 4,549.16 39,297.34

VII UTILIDADES 10% 117,795.44 106,016.96 223,812.40 1,027.45 190.35 1,217.79 14,025.95 1,780.41 15,806.36 15,053.39 1,970.76 17,024.16

VIII TOTAL GENERAL SIN IGV 1,567,660.43 1,410,908.50 2,978,568.93 13,673.59 2,533.21 16,206.80 186,661.92 23,694.32 210,356.25 200,335.51 26,227.54 226,563.05
CUADRO RESUMEN MENSUAL

"SUMINISTRO, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA


OBRA :
"AMPLIACION DE REDES DE MT Y BT UU.NN. HUANUCO PARTE II"

VALORIZACION No. : 02
MES DE VALORIZACION : FEBRERO
AÑO DE VALORIZACION : 2008
CONTRATO : GR-126-2007/ELCTO

METRADO BASE VALORIZACION No. 02


ITEM DESCRIPCION %
BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL

1 SUMINISTRO DE EQUIPOS Y MATERIALES 717,255.06 718,003.27 1,435,258.33 123,978.00 5,832.00 129,810.00

2 MONTAJE ELECTROMECANICO 372,614.18 260,287.13 632,901.31 2,643.90 11,330.61 13,974.51

3 DESMONTAJE 9,187.11 2,898.81 12,085.92 0.00

4 TRANSPORTE 11% 78,898.06 78,980.36 157,878.42 13,637.58 641.52 14,279.10

5 COSTO DIRECTO (C.D.) 1,177,954.41 1,060,169.57 2,238,123.98 140,259.48 17,804.13 158,063.61

6 GASTOS GENERALES 23.08% 271,910.58 244,721.97 516,632.55 32,376.50 4,109.78 36,486.28

7 UTILIDADES 10% 117,795.44 106,016.96 223,812.40 14,025.95 1,780.41 15,806.36

8 TOTAL GENERAL SIN IGV 1,567,660.43 1,410,908.50 2,978,568.93 186,661.92 23,694.32 210,356.25
CALCULO DE LA AMORTIZACION

"SUMINISTRO, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA


OBRA :
"AMPLIACION DE REDES DE MT Y BT UU.NN. HUANUCO PARTE II"

ADELANTO 595,713.79

IGV 113,185.62

TOTAL ADELANTO 708,899.41

CONTRATO GR-126-2007/ELCTO

VALORIZACION MONTO S/. (SIN IGV) AMORTIZACION PORCENTAJE

No. 01 ENERO 2008 16,206.80 6,482.72 1.09%

0.000%

No. 02 FEBRERO 2008 (20%) 210,356.25 42,071.25 7.062%

0.00

MONTO TOTAL 226,563.05 48,553.97 8.151%


CUADRO DE RESUMEN PORCENTUAL

"SUMINISTRO, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA "AMPLIACION DE REDES DE MT Y BT
OBRA :
UU.NN. HUANUCO PARTE II"

VALORIZACION No. : 02

MES DE VALORIZACION : FEBRERO


AÑO DE VALORIZACION : 2008
CONTRATO : GR-126-2007/ELCTO

VALOR PORCENTUAL DE
ITEM DESCRIPCION CONTRACTUAL S/. AVANCE ACTUAL S/.
AVANCE

1 SUMINISTRO DE EQUIPOS Y MATERIALES 1,435,258.33 129,810.00 9.04%

2 MONTAJE ELECTROMECANICO 632,901.31 26,152.45 4.13%

3 DESMONTAJE 12,085.92 0.00 0.00%

4 TRANSPORTE 157,878.42 14,279.10 9.04%

5 COSTO DIRECTO (C.D.) 2,238,123.98 170,241.55 7.61%

6 GASTOS GENERALES 516,632.55 39,297.34 7.61%

7 UTILIDADES 223,812.40 17,024.16 7.61%

8 TOTAL GENERAL SIN IGV 2,978,568.93 226,563.05 7.61%


VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE BAJA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
PRECIO
METRADO TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTUAL
METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO %
CONTRACTUAL
S/.

SUMINISTRO DE MATERIALES
1.00 POSTES,CRUCETAS Y MENSULAS
1.01 POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 9/300/2/150/285, FABRICADO CON CEMENTO PORTLAND TIPO V,UND 367.50 772.00 283710.00 324.00 41.97% 119,070.00 324.00 41.97% 119,070.00 448.00 58.03%
1.02 POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 8/300/2/120/240 INC. PERILLA PARA POSTE UND 308.00 6.00 1848.00 6.00 ### 1,848.00 6.00 ### 1,848.00 0.00 0.00%
1.03 BASTIDOR DE F° G° DE 1.10 m DE LONGITUD KIT COMPLETO UND 185.96 24.00 4463.04 0.00% 0.00 0.00 0.00% 0.00 24.00 ###
SUB TOTAL 0.00 290,021.04 0.00 120,918.00 120,918.00

2.00 CONDUCTORES 0.00


2.01 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x25+1x16 + P/25 m 8.30 1430.00 11869.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,430.00 ###
2.02 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x16+1x16 + P/25 m 6.76 1090.00 7368.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,090.00 ###
2.03 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x35+2x16 + P/25 m 10.94 870.00 9517.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 870.00 ###
2.04 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x25+2x16 + P/25 m 9.37 9410.00 88171.70 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 9,410.00 ###
2.05 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x16+2x16 + P/25 m 7.89 370.00 2919.30 0.00 0.00% 0.00 0.00 0.00% 0.00 370.00 ###
2.06 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x35+1x16 + P/25 m 7.30 3030.00 22119.00 0.00 0.00% 0.00 0.00 0.00% 0.00 3,030.00 ###
2.07 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x25+1x16 + P/25 m 6.29 6010.00 37802.90 0.00 0.00% 0.00 0.00 0.00% 0.00 6,010.00 ###
2.08 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x16+1x16 + P/25 m 5.24 5800.00 30392.00 0.00 0.00% 0.00 0.00 0.00% 0.00 5,800.00 ###
2.09 CABLE N2XY TETRAPOLAR 4 x 10mm2 m 16.76 310.00 5195.60 0.00 0.00% 0.00 0.00 0.00% 0.00 310.00 ###
2,10 CORDON PORTATIL DE Cu (NLT) 2 x 2.5 mm2 m 2.37 920.00 2180.40 0.00 0.00% 0.00 0.00 0.00% 0.00 920.00 ###
SUB TOTAL 217,536.10 0.00 0.00 0.00
3.00 AISLADORES 0.00
3.01 AISLADOR DE PORCELANA TRACCION, CLASE ANSI 54-1 (RETENIDA BT) UND 2.44 485.00 1182.19 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 485.00 ###
SUB TOTAL 1,182.19 0.00 0.00 0.00
4.00 FERRRETERIA 0.00
4.01 PERNO MAQ. AºGº 16mmØ x 254mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 4.19 260.00 1089.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 260.00 ###
4.02 PERNO OJO AºGº 16mmØ x 203mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 6.60 518.00 3418.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 518.00 ###
4.03 PERNO OJO AºGº 16mmØ x 305mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 7.57 75.00 567.75 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 75.00 ###
4.04 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 152mm DE LONGITUD UND 4.35 3.00 13.05 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 3.00 ###
4.05 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 203mm DE LONGITUD UND 4.99 367.00 1831.33 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 367.00 ###
4.06 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 305mm DE LONGITUD UND 8.86 19.00 168.34 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 19.00 ###
4.07 TUERCA OJO DE A°G° PARA PERNO DE 16mm2 UND 4.67 154.00 719.18 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 154.00 ###
4.08 PORTALINEA UNIPOLAR DE A°G°, PARA AISLADOR CLASE ANSI 53-1 UND 3.22 520.00 1674.40 0.00 0.00% 0.00 0.00 0.00% 0.00 520.00 ###
4.09 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.84 1552.00 1303.68 0.00 0.00% 0.00 0.00 0.00% 0.00 1,552.00 ###
4.10 ARANDELA CUADRADA PLANA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.81 26.00 21.06 0.00 0.00% 0.00 0.00 0.00% 0.00 26.00 ###
4.11 CONECTOR TIPO CUÑA Al-Al 35/35 - 16 mm². UND 4.19 224.00 938.56 0.00 0.00% 0.00 0.00 0.00% 0.00 224.00 ###
4.12 CONECTOR TIPO CUÑA Al-Al 25/25 - 16 mm². UND 4.19 1454.00 6092.26 0.00 0.00% 0.00 0.00 0.00% 0.00 1,454.00 ###
4.13 CONECTOR TIPO CUÑA Al-Al 16/16 - 16 mm². UND 3.22 1162.00 3741.64 0.00 0.00% 0.00 0.00 0.00% 0.00 1,162.00 ###
4.14 CONECTOR BIMETALICO TIPO CUÑA Al/Cu, 16 mm²/16mm² UND 9.98 52.00 518.96 0.00 0.00% 0.00 0.00 0.00% 0.00 52.00 ###
4.15 CONECTOR BIMETALICO TIPO CUÑA Al/Cu, 25 mm²/25 mm² UND 9.98 18.00 179.64 0.00 0.00% 0.00 0.00 0.00% 0.00 18.00 ###
4.16 HEBILLA DE ACERO INOXIDABLE P' FLEJE 19 mm UND 1.25 260.00 325.00 0.00 0.00% 0.00 0.00 0.00% 0.00 260.00 ###
4.17 FLEJE DE ACERO INOXIDABLE (CINTA BAND IT), DE 19 mm m 5.02 208.00 1044.16 0.00 0.00% 0.00 0.00 0.00% 0.00 208.00 ###
4.18 CAJA DE DERIVACION POLIMERICA 10 SALIDAS - 03 BARRAS UND 122.36 193.00 23615.48 0.00 0.00% 0.00 0.00 0.00% 0.00 193.00 ###
4.19 CAJA DE DERIVACION POLIMERICA 10 SALIDAS - 04 BARRAS UND 122.36 67.00 8198.12 0.00 0.00% 0.00 0.00 0.00% 0.00 67.00 ###
4.20 GRAPA DE SUSPENSION ANGULAR DE ALEACION DE ALUMINIO UND 8.53 388.00 3309.64 0.00 0.00% 0.00 0.00 0.00% 0.00 388.00 ###
4.21 GRAPA DE ANCLAJE CONICA DE ALEACION DE ALUMINIO UND 13.85 748.00 10359.80 0.00 0.00% 0.00 0.00 0.00% 0.00 748.00 ###
SUB TOTAL 69,130.25 0.00 0.00 0.00

Página 6 PLANILLA AVANCE BT


VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE BAJA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
PRECIO
METRADO TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTUAL
METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO %
CONTRACTUAL
S/.

5.00 RETENIDAS
5,01 CABLE A°G° DE 10 mm Ø GRADO SIEMENS MARTIN, 7 HILOS m 2.51 4850.00 12173.50 0.00 0.00% 0.00 0.00 0.00% 0.00 4,850.00 ###
5,02 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx203mm, TUERCA Y CONTRATUERCA UND 6.60 454.00 2996.40 0.00 0.00% 0.00 0.00 0.00% 0.00 454.00 ###
5,03 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx406mm, TUERCA Y CONTRATUERCA UND 9.82 31.00 304.42 0.00 0.00% 0.00 0.00 0.00% 0.00 31.00 ###
5,04 GRAPA PARALELA DOBLE VIA AºGº 3 PERNOS, 152mm LONG, PARA CABLE DE ACERO 10 mm2 UND 7.89 1940.00 15306.60 0.00 0.00% 0.00 0.00 0.00% 0.00 1,940.00 ###
5,05 VARILLA DE ANCLAJE DE A° G° PROVISTO DE OJAL Y GUARDACABO 16mmØx1.80m, Tuerca y Contrat. UND 18.19 485.00 8822.15 0.00 0.00% 0.00 0.00 0.00% 0.00 485.00 ###
5,06 BLOQUE DE CONCRETO ARMADO DE 0.40 x 0.40 x 0.15m UND 15.30 485.00 7420.50 0.00 200.00 41.24% 3,060.00 200.00 41.24% 3,060.00 285.00 58.76%
5,07 ARANDELA DE ANCLAJE DE A°G° 102 x 102 x 5 mm, AGUJERO CENTRAL DE 18mmØ UND 2.74 485.00 1328.90 0.00 0.00% 0.00 0.00 0.00% 0.00 485.00 ###
5,08 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.84 970.00 814.80 0.00 0.00% 0.00 0.00 0.00% 0.00 970.00 ###
5,09 JUEGO DE CONTRAPUNTA DE TUBO DE AºGº DE 2"Ø x1.00m CON ABRAZADERA PARTIDA Y PERNO DE AJUSTE UND 60.86 83.00 5051.38 0.00 0.00% 0.00 0.00 0.00% 0.00 83.00 ###
5,10 CANALETA GUARDACBLE DE F° G° DE 2.4 m DE LONG. CON PERNO Y TUERCA EN UN EXTREMO. UND 24.47 485.00 11867.95 0.00 0.00% 0.00 0.00 0.00% 0.00 485.00 ###
5,11 ALAMBRE DE F°G° N° 12 AWG, PARA ENTORCHADO m 0.32 1455.00 465.60 0.00 0.00% 0.00 0.00 0.00% 0.00 1,455.00 ###
SUB TOTAL 0.00 66,552.20 3,060.00 3,060.00
6.00 PUESTA A TIERRA 0.00 0.00
6,01 CONDUCTOR DE COBRE DESNUDO CABLE TEMPLE BLANDO 16mm2, 7 HILOS m 4.54 2048.00 9297.92 0.00 0.00% 0.00 0.00 0.00% 0.00 2,048.00 ###
6,02 CONECTOR DE ALEACION DE COBRE PARA ELECTRODO DE 16mm∅ UND 3.86 256.00 988.16 0.00 0.00% 0.00 0.00 0.00% 0.00 256.00 ###
6,03 ELECTRODO DE COPPERWELD DE 16mm∅ x 2400mm DE LONGITUD (MAQUINADO) UND 40.25 128.00 5152.00 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
6,04 CONECTOR BIMETALICO TIPO CUÑA Al-Cu SEGÚN REQUERIMIENTO UND 12.24 128.00 1566.72 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
6,05 CAJA DE REGISTRO DE CONCRETO ARMADO DE 400 x 400 x 300mm CON TAPA UND 23.35 128.00 2988.80 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
6,06 SAL INDUSTRIAL (SACO 25 KG) SACO 8.05 256.00 2060.80 0.00 0.00% 0.00 0.00 0.00% 0.00 256.00 ###
6,07 TUBO PVC SAP DE 20mmØ x 1.5m UND 5.53 128.00 707.84 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
6,08 BENTONITA SODICA SACO DE 30 KG. SACO 13.42 384.00 5153.28 0.00 0.00% 0.00 0.00 0.00% 0.00 384.00 ###
6,09 TIERRA VEGETAL CERNIDA PREPARADA PARA PUESTA A TIERRA M3 65.41 285.00 18641.85 0.00 0.00% 0.00 0.00 0.00% 0.00 285.00 ###
6,10 ARANDELA DE ANCLAJE CUADRADA PLANA DE COBRE 152 x 152 x 6.35 mm, HUECO 18mmØ UND 6.43 128.00 823.04 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
6,11 TUERCA DE COBRE PARA MAQUINADO DE 16 mmØ UND 7.98 128.00 1021.44 0.00 0.00% 0.00 0.00 0.00% 0.00 128.00 ###
SUB TOTAL 0.00 48,401.85
7.00 EQUIPOS DE ALUMBRADO PUBLICO 0.00
7.01 CONECTOR BIMETALICO TIPO CUÑA Al-Cu 16 mm²/2.5 mm² UND 2.28 556.00 1267.68 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 556.00 ###
7.02 PASTORAL PARABOLICO DE FºGº PP/1.10m/1.5m/38.1mmØ/15º TIPO UNIFIX UND 48.14 278.00 13382.92 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 278.00 ###
7.03 ABRAZADERA DE AºGº PARA PASTORAL 39mmx125mmØ(POSTE)x25.4mmØ(PASTORAL), 5mm ESP. UND 10.14 486.00 4928.04 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 486.00 ###
7.04 ABRAZADERA DE AºGº PARA PASTORAL 39mmx220mmØ(POSTE)x25.4mmØ(PASTORAL), 5mm ESP. UND 12.56 70.00 879.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 70.00 ###
SUB TOTAL 20,457.84 0.00 0.00 0.00

8.00 OTROS 0.00


8.01 CORREA PLASTICA DE AMARRE DE 363 mm long. x 54.4 kg resistente a la tracción COLOR NEGRO UND 0.59 2287.00 1349.33 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2,287.00 ###
8.02 CINTA AISLANTE m 7.03 1.60 11.25 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.60 ###
8.03 CINTA DE GOMA AUTOFUNDENTE HASTA 1000V m 1.69 1267.00 2141.23 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,267.00 ###
8.04 SEPARADOR DE VIAS PVC UND 78.63 6.00 471.78 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 6.00 ###
SUB TOTAL 3,973.59 0.00 0.00 0.00
TOTAL SUMINISTRO DE MATERIALES 717,255.06 0.00 123,978.00 123,978.00

Página 7 PLANILLA AVANCE BT


VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE BAJA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
PRECIO
METRADO TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTUAL
METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO %
CONTRACTUAL
S/.

MONTAJE ELECTROMECANICO BT

1.00 OBRAS PRELIMINARES 0.00


1.01 REPLANTEO TOPOGRAFICO Y UBICACION DE ESTRUCTURAS km 489.26 26.16 12800.35 21.00 80.27% 10,274.46 0.00% 0.00 21.00 80.27% 10,274.46 5.16 19.73%
1.02 INGENIERIA DE DETALLE (Incluye cálculos justificativos, diseño, elaboración de expediente y otros) LOC. 881.30 12.00 10575.60 0.00 0.00% 0.00 3.00 25.00% 2,643.90 3.00 25.00% 2,643.90 9.00 75.00%
SUB TOTAL 23,375.95 10,274.46 2,643.90 12,918.36

2.00 INSTALACION DE POSTES 0.00


2.01 TRANSPORTE POSTES DE C.A.C. 8 m y 9 m DE ALMACEN A PUNTO DE IZAJE UND 778.00 65.19 50717.82 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 65.19 ###
2.02 EXCAVACION EN TERRENO NORMAL (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) m3 132.00 46.91 6192.12 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.91 ###
2.03 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 8 m y 9 m. m3 778.00 46.02 35803.56 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.02 ###
2.04 PINTADO, SEÑALIZACION Y NUMERACIÓN DE ESTRUCTURAS (Incluye materiales, mano de obra y otros) UND 778.00 16.64 12945.92 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 16.64 ###
2.05 CIMENTACION DE POSTES DE CONCRETO ARMADO CENTRIFUGADO DE 8, 9 y 11 m Fc=140 Kg/cm2 (Inc solado,) UND 187.00 108.82 20349.34 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 108.82 ###
2.06 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 7.00 153.04 1071.28 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 153.04 ###
2.07 EXCAVACION EN TERRENO ROCOSO (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) m3 44.00 153.40 6749.60 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 153.40 ###
EXCAVACION EN TERRENO CON PAVIMENTO (Inc. Limpieza y/o Eliminacion de desmonte
2.08 a verdederos en zonas urbanas) m3 22.00 119.70 2633.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 119.70 ###
SUB TOTAL 136,463.04 0.00 0.00 0.00

3.00 INSTALACION DE RETENIDAS 0.00


3.01 EXCAVACION EN TERRENO NORMAL (Inc. Limpieza, elimin.desmonte a vertederos en zonas urbanas) m3 228.00 61.52 14026.56 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 61.52 ###
3.02 INSTALACION DE RETENIDA R1 m3 379.00 46.20 17509.80 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 46.20 ###
3.03 INSTALACION DE RETENIDA R2 JGO 75.00 46.20 3465.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 46.20 ###
3.04 INSTALACION DE RETENIDA R1P JGO 23.00 59.38 1365.74 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 59.38 ###
3.05 INSTALACION DE RETENIDA R2P JGO 8.00 59.38 475.04 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 59.38 ###
3.06 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) JGO 4.00 153.04 612.16 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 153.04 ###
3.07 RELLENO Y COMPACTACION PARA EL BLOQUE DE ANCLAJE JGO 228.00 45.09 10280.52 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 45.09 ###
3.08 EXCAVACION EN TERRENO ROCOSO (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) JGO 114.00 153.40 17487.60 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 153.40 ###
EXCAVACION EN TERRENO CON PAVIMENTO (Inc. Limpieza y/o Eliminacion de desmonte a
3.09 verdederos en zonas urbanas) m3 38.02 119.70 4551.47 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 119.70 ###
SUB TOTAL 0.00 69,773.89
4.00 MONTAJE DE ARMADOS 0.00
4.01 MONTAJE DE ARMADO TIPO E1 JGO 353.00 19.88 7017.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 19.88 ###
4.02 MONTAJE DE ARMADO TIPO E2 JGO 2.00 27.82 55.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 27.82 ###
4.03 MONTAJE DE ARMADO TIPO E3 JGO 232.00 23.20 5382.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 23.20 ###
4.04 MONTAJE DE ARMADO TIPO E4 JGO 129.00 27.82 3588.78 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 27.82 ###
4.05 MONTAJE DE ARMADO TIPO E5 JGO 14.00 30.91 432.74 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 30.91 ###
4.06 MONTAJE DE ARMADO TIPO E6 JGO 5.00 34.78 173.90 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 34.78 ###
4.07 MONTAJE DE ARMADO TIPO E7 JGO 46.00 23.20 1067.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 23.20 ###
4.08 MONTAJE DE ARMADO TIPO E9 JGO 11.00 27.82 306.02 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 27.82 ###
4.09 MONTAJE DE ARMADO TIPO A1 JGO 2.00 39.72 79.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 39.72 ###
4.1 MONTAJE DE ARMADO TIPO A3 JGO 6.00 39.72 238.32 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 39.72 ###
4.11 MONTAJE DE ARMADO TIPO A4 JGO 4.00 39.72 158.88 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 39.72 ###
4.12 MONTAJE DE ARMADO TIPO E1P JGO 19.00 21.41 406.79 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 21.41 ###
4.13 MONTAJE DE ARMADO TIPO E2P JGO 5.00 30.91 154.55 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 30.91 ###
4.14 MONTAJE DE ARMADO TIPO E3P JGO 43.00 25.27 1086.61 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 25.27 ###
4,15 MONTAJE DE ARMADO TIPO E7P JGO 4.00 25.27 101.08 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 25.27 ###
4,16 MONTAJE DE ARMADO TIPO E9P JGO 11.00 30.91 340.01 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 30.91 ###
4,17 MONTAJE DE ARMADO TIPO EMPALME EN "+" JGO 27.00 46.35 1251.45 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.35 ###
4,18 MONTAJE DE ARMADO TIPO EMPALME EN "T" JGO 53.00 46.35 2456.55 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.35 ###
4,19 MONTAJE DE CAJA DE DERIVACION TIPO TIPO CA10 220 V JGO 67.00 46.35 3105.45 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.35 ###

Página 8 PLANILLA AVANCE BT


VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE BAJA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
PRECIO
METRADO TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTUAL
METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO %
CONTRACTUAL
S/.

4,20 MONTAJE DE CAJA DE DERIVACION TIPO TIPO CA10 220 V 3Ø JGO 193.00 46.35 8945.55 0.00 0.00 0.00 46.35 ###
4,21 MONTAJE DE ARMADO TIPO E10 JGO 18.00 19.88 357.84 0.00 0.00 0.00 19.88 ###
4,22 MONTAJE DE ARMADO TIPO A4P JGO 1.00 46.35 46.35 0.00 0.00 0.00 46.35 ###
4,23 MONTAJE DE ARMADO TIPO E4P JGO 8.00 34.78 278.24 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 34.78 ###
4,24 MONTAJE DE ARMADO TIPO EMPALME EN "ET1" JGO 6.00 55.63 333.78 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 55.63 ###
SUB TOTAL 37,365.21 0.00 0.00 0.00

5.00 MONTAJE DE CONDUCTORES


5.01 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x25+1x16 + P/25 km 1.43 1245.42 1780.95 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5.02 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x16+1x16 + P/25 km 1.09 1245.42 1357.51 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5.03 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x35+2x16 + P/25 km 0.87 1245.42 1083.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5.04 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x25+2x16 + P/25 km 9.41 1245.42 11719.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5.05 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x16+2x16 + P/25 km 0.37 1245.42 460.81 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5.06 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x35+1x16 + P/25 km 3.03 1245.42 3773.62 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5,07 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x25+1x16 + P/25 km 6.01 1245.42 7484.97 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
5,08 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x16+1x16 + P/25 km 5.80 1245.42 7223.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1,245.42 ###
SUB TOTAL 0.00 34,884.22 0.00 0.00 0.00
0.00 0.00 0.00
6.00 INSTALACION DE PUESTA A TIERRA 0.00 0.00 0.00
EXCAVACION DE TERRENO NORMAL PARA PUESTA A TIERRA (Incluye Limpieza y/o
6.01 Eliminacion de desmonte a vertederos en zonas urbanas) m3 104.00 61.52 6398.08 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 61.52 ###
6.02 INSTALACION DE PUESTA A TIERRA TIPO PATB-1 JGO 128.00 83.16 10644.48 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 83.16 ###
6.03 SISTEMA DE PROTECCION ANTIRROBO DE LAS VARILLAS DE COBRE (Incluye materiales) UND 128.00 94.20 12057.60 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 94.20 ###
6.04 RELLENO Y COMPACTACION DE PUESTA A TIERRA (Incluye caja de registro, ) m3 104.00 56.43 5868.72 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 56.43 ###
6.05 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 3.00 153.04 459.12 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 153.04 ###
EXCAVACION DE TERRENO ROCOSO PARA PUESTA A TIERRA (Incluye Limpieza y/o
6,06 Eliminacion de desmonte a vertederos en zonas urbanas) m3 35.00 153.40 5369.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 153.40 ###
6,07 EXCAVACION DE TERRENO CON PAVIMENTO PARA PUESTA A TIERRA (Incluye Limpieza y/o Eliminacion de desmonte m3 17.00 119.70 2034.90 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 119.70 ###
SUB TOTAL 0.00 42,831.90 0.00 0.00
5.00 INSTALACION DE EQUIPOS DE ALUMBRADO PUBLICO 0.00 0.00
7.01 MONTAJE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP1 (postes B.T.) JGO 243.00 61.79 15014.97 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 61.79 ###
7.02 MONTAJE DE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP1P (postes MT) JGO 2.00 74.14 148.28 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 74.14 ###
7,02 MONTAJE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP2 JGO 33.00 52.95 1747.35 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 52.95 ###
SUB TOTAL 16,910.60 0.00 0.00 0.00

6.00 PRUEBAS Y PUESTA EN SERVICIO 0.00


6.01 PRUEBA Y PUESTA EN SERVICIO DE LAS REDES LOC 12.00 652.36 7828.32 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 652.36 ###
SUB TOTAL 7,828.32 0.00 0.00 0.00

7.00 INSTALACION DE ACOMETIDAS 0.00


9.01 REINSTALACION DE ACOMETIDAS (Incluye materiales y demas accesorios) LOC 45.00 70.69 3181.05 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 70.69 ###
SUB TOTAL 3,181.05 0.00 0.00 0.00

TOTAL MONTAJE ELECTROMECANICO 372,614.18 10,274.46 2,643.90 12,918.36

DESMONTAJE ELECTROMECANICO

1.00 DESMONTAJE ELECTROMECANICO 0.00

1.01 DESMONTAJE DE LINEA EXISTENTE (Incluye postes, redes, ferreteria, anclajes, y otros, asimismo incluye traslado a km 7785.69 1.18 9187.11 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.18 ###
0.00 0.00 0.00 0.00 0.00
SUB TOTAL 0.00 9,187.11 0.00 0.00 0.00

TOTAL DESMONTAJE ELECTROMECANICO 9,187.11 0.00 0.00 0.00

TOTAL 1,099,056.35 10,274.46 126,621.90 136,896.36

Página 9 PLANILLA AVANCE BT


VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

SUMINISTRO DE MATERIALES
1.00 POSTES, BASTIDORES Y MENSULAS 0.00 0.00
1.01 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 13/300/2/180/375 INC. PERILLA UND 804.50 25.00 20,112.50 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 25.00 ###
1.02 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 13/400/2/180/375 INC. PERILLA UND 874.50 82.00 71,709.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 82.00 ###
1.03 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 15/400/2/225/450 INC. PERILLA UND 1301.50 12.00 15,618.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 12.00 ###
1.04 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 15/500/2/225/450 INC. PERILLA UND 1371.50 10.00 13,715.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 10.00 ###
1.05 PERFIL DE F° G° TIPO "U" DE 60 x 50 x 6 mm DE ESPESOR x 2.40 m DE LONGITUD UND 233.45 9.00 2,101.05 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 9.00 ###
1.06 PERFIL DE F° G° TIPO "U" DE 75 x 60 x 6 mm DE ESPESOR x 2.40 m DE LONGITUD UND 239.41 12.00 2,872.92 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 12.00 ###
1.07 PERFIL DE F° G° TIPO "U" DE 75 x 50 x 9.5 mm DE ESPESOR x 2.80 m DE LONGITUD UND 466.58 14.00 6,532.12 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 14.00 ###
1.08 BRAZO SOPORTE RIOSTRA DE PERFIL ANGULAR DE AoGo DE 38x38x5 mm, SECCION 0.71 LONG UND 13.20 20.00 264.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 20.00 ###
1.09 PERFIL DE F° G° TIPO "U" DE 64 x 64 x 6 .4mm DE ESPESOR x 1.50 m LONG. C/PERNO UND 229.91 2.00 459.82 0.00 0.00 0.00 2.00 ###
1.10 MEDIA LOZA DE C.A. 1.30/750. PARA SOPORTE DE TRANSFORMADOR UND 213.50 29.00 6,191.50 0.00 0.00 0.00 29.00 ###
1.11 CRUCETA SIMETRICA DE CONCRETO ARMADO VIBRADO DE Z/2.00/500 UND 133.00 2.00 266.00 0.00 0.00 0.00 2.00 ###
1.12 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 1 . Ver detalles. UND 165.67 122.00 20,211.74 0.00 0.00 0.00 122.00 ###
1.13 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 2 . Ver detalles. UND 270.48 75.00 20,286.00 0.00 0.00 0.00 75.00 ###
1.14 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 3 . Ver detalles. UND 201.25 3.00 603.75 0.00 0.00 0.00 3.00 ###
1.15 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 5 PARA SECCIONADOR. Ver detalles. UND 256.96 2.00 513.92 0.00 0.00 0.00 2.00 ###
1.16 PALOMILLA DE CONCRETO ARMADO DE 1.50 / 100 UND 73.50 18.00 1,323.00 0.00 0.00 0.00 18.00 ###
1.17 CRUCETA SIMETRICA DE CONCRETO ARMADO VIBRADO DE Z/1.50/300 UND 63.00 2.00 126.00 0.00 0.00 0.00 2.00 ###
1.18 CRUCETA ASIMETRICA DE C.A.V. DE ZA/1.50/0.90/250 UND 63.00 2.00 126.00 0.00 0.00 0.00 2.00 ###
1.19 MENSULA DE CONCRETO ARMADO VIBRADO DE M/1.00/250 UND 52.50 92.00 4,830.00 0.00 0.00 0.00 92.00 ###
1.20 MENSULA DE CONCRETO ARMADO VIBRADO DE M/0.60/250 UND 42.00 10.00 420.00 0.00 0.00 0.00 10.00 ###
1.21 MENSULA DE CONCRETO ARMADO VIBRADO DE M/1.50/250 UND 73.50 6.00 441.00 0.00 6.00 ###
SUB TOTAL 188,723.32 0.00 0.00 0.00
2.00 CONDUCTORES 0.00
2.01 CONDUCTOR DE ALEACION DE ALUMINIO 6201-T81 AAAC CABLEADO 25mm2, 7HILOS m 0.90 11590.00 10,431.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 11,590.00 ###
2.02 CONDUCTOR DE ALEACION DE ALUMINIO 6201-T81 AAAC CABLEADO 35mm2, 7HILOS m 1.24 7420.00 9,200.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 7,420.00 ###
2.03 CABLE DE CONTROL DEL TIPO CCT-B DE 12 x 14 AWG m 15.96 20.00 319.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 20.00 ###
2.04 ALAMBRE DE AMARRE DE ALUMINIO SOLIDO RECOCIDO TEMPLE BLANDO DE 16 mm2 m 0.97 520.00 504.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 520.00 ###
2.05 CABLE DE CONTROL DEL TIPO CCT-B DE 7 x 2.5 mm2 440 - 220 V m 9.74 40.00 389.60 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 40.00 ###
2.06 CABLE DE CONTROL DEL TIPO CCT-B DE 7 x 2.5 mm2 380 - 220 V m 9.74 15.00 146.10 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 15.00 ###
2.07 CONDUCTOR TIPO NA2XSA2Y-S 15 kV de 3 X 1X35 mm2 m 39.20 30.00 1,176.00 0.00 0.00% 0.00 0.00 0.00% 0.00 30.00 ###
2.08 CONDUCTOR TIPO NA2XSA2Y-S 30 kV de 3 X 1X35 mm2 m 60.47 130.00 7,861.10 0.00 0.00% 0.00 0.00 0.00% 0.00 130.00 ###
2.09 CABLE NYY EN FORMACION TRIPLE SECCION 3 x 1 x 25 mm2 m 28.59 80.00 2,287.20 0.00 0.00% 0.00 0.00 0.00% 0.00 80.00 ###
2.10 CABLE NYY EN FORMACION TRIPLE SECCION 3 x 1 x 10 mm2 m 11.99 110.00 1,318.90 0.00 0.00% 0.00 0.00 0.00% 0.00 110.00 ###
2.11 CABLE NYY CON FORMACION UNIPOLAR SECCION 1 x 35 mm2 m 12.69 75.00 951.75 0.00 0.00% 0.00 0.00 0.00% 0.00 75.00 ###
2.12 CABLE NYY EN FORMACION PARALELA SECCION 3 x1x 50 mm2 m 52.07 120.00 6,248.40 0.00 0.00% 0.00 0.00 0.00% 0.00 120.00 ###
2.13 CABLE NYY EN FORMACION PARALELA SECCION 2 x 1 x 35 mm2 m 39.05 70.00 2,733.50 70.00 ###
SUB TOTAL 43,567.95 0.00 0.00 0.00

Página 10 METRADO MT
VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

3.00 TRANSFORMADORES DE DISTRIBUCION 0.00


3.01 TRANSFORMADOR 3Ø, MT, 3500 msnm, 10±2x2.5% / 0.23 kV DE 25 kVA UND 6964.86 1.00 6,964.86 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
3.02 TRANSFORMADOR 3Ø, MT, 3500 msnm, 10±2x2.5% / 0.23 kV DE 50 kVA UND 8970.82 2.00 17,941.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
3.03 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9.2±2x2.5% /0.40 - 0.23 kV DE 25 kVA UND 8621.55 1.00 8,621.55 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
3,04 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9.2±2x2.5% / 0.400-0.230 kV DE 75 kVA UND 12567.18 3.00 37,701.54 0.00 0.00% 0.00 0.00 0.00% 0.00 3.00 ###
3,05 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.400-0.23 kV DE 100 kVA UND 16113.85 2.00 32,227.70 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
3,06 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9.2±2x2.5% / 0.46-0.23 kV 37.5 kVA UND 7018.96 2.00 14,037.92 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
3,07 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.46-0.23 kV 25 kVA UND 6332.61 2.00 12,665.22 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
3,08 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.46-0.23 kV 15 kVA UND 5362.27 9.00 48,260.43 0.00 0.00% 0.00 0.00 0.00% 0.00 9.00 ###
SUB TOTAL 178,420.86 0.00 0.00 0.00
4.00 EQUIPOS DE PROTECCION Y SECCIONAMIENTO 0.00
4.01 SECCIONADOR CUT-OUT 15 KV, 95 kV BIL, INOM 100 A. (Para tensión de servicio 10 kV) UND 151.68 12.00 1,820.16 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 12.00 ###
4.02 SECCIONADOR TIPO CUT OUT DE 27 kV, 125 kV BIL, 100 A (Para tensión de servicio22.9/ 13.2 kV) UND 183.28 63.00 11,546.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 63.00 ###
4.03 FUSIBLE DE EXPULSION TIPO K, UND 8.78 63.00 553.14 0.00 0.00% 0.00 0.00 0.00% 0.00 63.00 ###
4.04 PARARRAYO POLIMÉRICO DE OXIDO DE METAL, TIPO DISTRIBUCION 15 kV, 10 kA (Para tensión de servicio 10 kV) UND 158.00 12.00 1,896.00 0.00 0.00% 0.00 0.00 0.00% 0.00 12.00 ###
4.05 PARARRAYO POLIMÉRICO DE OXIDO DE METAL, TIPO DISTRIBUCION 21 kV, 10 kA UND 183.28 63.00 11,546.64 0.00 0.00% 0.00 0.00 0.00% 0.00 63.00 ###
SUB TOTAL 27,362.58 0.00 0.00 0.00
5.00 AISLADORES Err:522 0.00
5.01 AISLADOR POLIMERICO TIPO PIN DE 15 Kv(Vmin) CON ESPIGA A°G° PARA CRUCETA CAV DE POSTE (Tension servicio 10 k UND 66.39 30.00 1,991.70 30.00 ###
5.02 AISLADOR POLIMERICO TIPO PIN DE 35 Kv(Vmin) CON ESPIGA A°G° PARA CRUCETA CAV DE POSTE (Tension servicio 22.9 UND 135.88 164.00 22,284.32 164.00 ###
5.03 AISLADOR POLIMERICO TIPO SUSPENSION DE 17.5 Kv CON HERRAJE DE FºGº (tensión de servicio 10 kV) UND 48.30 24.00 1,159.20 24.00 ###
5.04 AISLADOR POLIMERICO TIPO SUSPENSION DE 36 Kv CON HERRAJE DE FºGº (tensión de servicio 22.9 kV) UND 74.06 253.00 18,737.18 253.00 ###
5.05 TERMINAL EXTERIOR TERMORESTRINGER PARA CABLE NA2XSA2Y-S, 15/8.7 KV PARA 35 mm² UND 583.37 10.00 5,833.70 10.00 ###
5.06 TERMINAL EXTERIOR TERMORESTRINGER PARA CABLE NA2XSA2Y-S, 30 KV PARA 35 mm² UND 1236.48 22.00 27,202.56 22.00 ###
5.07 CAPUCHON POLIMERICO DE GOMA 10 KV , RELLENO CON GRASA SILICONADA UND 323.40 6.00 1,940.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 6.00 ###
5.08 CAPUCHON POLIMERICO DE GOMA 25 KV , RELLENO CON GRASA SILICONADA UND 316.80 18.00 5,702.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 18.00 ###
SUB TOTAL 84,851.46 0.00 0.00 0.00
6.00 FERRRETERIA Err:522 0.00 Err:522
6.01 PERNO OJO AºGº DE 16mmØ x 152 LONG. 76mm, CON TUERCA Y CONTRATUERCA UND 5.94 76.00 451.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 76.00 ###
6.02 PERNO OJO AºGº DE 16mmØ x 203mm, CON TUERCA Y CONTRATUERCA UND 5.96 56.00 333.76 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 56.00 ###
6.03 PERNO OJO AºGº DE 16mmØ x 305mm, CON TUERCA Y CONTRATUERCA UND 6.60 88.00 580.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 88.00 ###
6.04 PERNO AºGº DE 9.5 mmØ x 38mm, CON TUERCA Y CONTRATUERCA UND 7.57 4.00 30.28 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 4.00 ###
6.05 PERNO MAQ. AºGº 16mmØ x 203mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 1.45 92.00 133.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 92.00 ###
6.06 PERNO MAQ. AºGº 13mmØ x 406mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 2.74 51.00 139.74 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 51.00 ###
6.07 PERNO MAQ. AºGº 16mmØ x 152mm LONG., CON TUERCA Y CONTRATUERCA UND 6.12 19.00 116.28 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 19.00 ###
6.08 PERNO MAQ. AºGº 16mmØ x 305mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 3.54 304.00 1,076.16 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 304.00 ###
6.09 PERNO MAQ. AºGº 16mmØ x 356mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 4.99 10.00 49.90 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 10.00 ###
6.10 PERNO MAQ. AºGº 16mmØ x 458mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 5.47 89.00 486.83 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 89.00 ###
6.11 PERNO MAQ. AºGº 16mmØ x 508mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 7.08 47.00 332.76 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 47.00 ###
6.12 PERNO DOBLE ARMADO DE AºGº 16mmØ x 406mm LONGITUD CON ARANDELAS, TUERCA Y CONT. UND 7.57 29.00 219.53 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 29.00 ###

Página 11 METRADO MT
VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

6.13 PERNO DOBLE ARMADO DE AºGº 16mmØ x 305mm LONGITUD CON ARANDELAS, TUERCA Y CONT. UND 8.05 18.00 144.90 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 18.00 ###
6.14 TUERCA OJO DE AoGo PARA PERNO DE 16mmØ UND 6.76 89.00 601.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 89.00 ###
6.15 HEBILLA DE ACERO INOXIDABLE PARA FLEJE DE 19 mm UND 6.05 43.00 260.15 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 43.00 ###
6.16 GRAPA ANCLAJE TIPO PISTOLA DE A° G° PARA CONDUCTOR DE 25 mm2. de 2 pernos UND 4.67 122.00 569.74 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 122.00 ###
6.17 CONECTOR DE ALUMINIO TIPO CUÑA DE 25 - 50 mm² SEGÚN REQUERIMIENTO UND 30.43 51.00 1,551.93 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 51.00 ###
6.18 ARANDELA CUADRADA CURVA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.86 730.00 627.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 730.00 ###
6.19 ARANDELA CUADRADA PLANA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.84 628.00 527.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 628.00 ###
6.2 ADAPTADOR TIPO LIRA DE ACERO FORJADO GALVANIZADO DE 16 mmØ x 78 mm LONG. UND 0.81 42.00 34.02 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 42.00 ###
6.21 GRAPA ANCLAJE TIPO PISTOLA DE A° G° PARA CONDUCTOR DE 35 mm2. de 2 pernos (3 pernos paravano > a 150 m) UND 8.05 113.00 909.65 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 113.00 ###
6.22 GRAPA DE SUSPENSION ANGULAR DE ALEACION DE Al. PARA CONDUCTOR DE ACUERDO REQ. UND 30.43 36.00 1,095.48 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 36.00 ###
6.23 GRAPA DE ALUMINIO TIPO DOBLE VIA PARA CONDUCTOR DE 25 mm2. UND 15.46 38.00 587.48 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 38.00 ###
6.24 GRAPA DE ALUMINIO TIPO DOBLE VIA PARA CONDUCTOR DE 35 mm2. UND 2.25 68.00 153.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 68.00 ###
6.25 TERMINAL DE COMPRESION BIMETALICO CON OREJA DE 9,5 mm Ø INC. PERNO Y ARAND. PRESION UND 2.25 26.00 58.50 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 26.00 ###
6.26 VARILLA DE ARMAR SIMPLE DE AL-AL, PARA CONDUCTOR DE 25 mm2 UND 6.77 26.00 176.02 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 26.00 ###
6.27 VARILLA DE ARMAR SIMPLE DE AL-AL, PARA CONDUCTOR DE 35mm2 UND 5.15 74.00 381.10 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 74.00 ###
6.28 PLATINA DE A°G° 652 LONG. x 50 mm ANCHO x 5 mm ESPESOR. CON DOS PERNOS SEGÚN DETALLE. UND 6.12 46.00 281.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 46.00 ###
6.29 VARILLA DE ARMAR DOBLE DE AL-AL, PARA CONDUCTOR DE 25 mm2 UND 10.30 16.00 164.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 16.00 ###
6.3 CINTA PLANA DE ARMAR 1.3x7.6 mm x 0.70 m DE LONGITUD. m 5.96 242.20 1,443.51 0.00 0.00% 0.00 0.00 0.00% 0.00 242.20 ###
6.31 FLEJE DE ACERO INOXIDABLE (CINTA BAND IT), DE 3/4" m 0.97 73.20 71.00 0.00 0.00% 0.00 0.00 0.00% 0.00 73.20 ###
6.32 PERNO DE A°G° 16 mm Ø x 51 mm LONG. CON ARANDELA, TUERCA Y CONTRATUERCA UND 5.02 20.00 100.40 0.00 0.00% 0.00 0.00 0.00% 0.00 20.00 ###
SUB TOTAL 13,691.04 0.00 0.00 0.00
7.00 RETENIDAS Err:522 0.00 Err:522 0.00 Err:522 Err:522
7.01 CABLE A°G° SIEMENS MARTIN 10mm Ø, 7 HILOS m 2.51 1880.00 4,718.80 0.00% 0.00 0.00% 0.00 0.00 0.00 1,880.00 ###
7.02 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx254mm, TUERCA Y CONTRATUERCA UND 7.41 116.00 859.56 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 116.00 ###
7.03 GUARDACABO DE F° G° PARA CABLE DE 10 mm Ø UND 0.81 152.00 123.12 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 152.00 ###
7.04 GRAPA DOBLE VIA AºGº 3 PERNOS, 152mm LONG, PARA CABLE S.M. DE 10 mm2 UND 7.89 500.00 3,945.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 500.00 ###
7.05 VARILLA DE ANCLAJE CON GUARDACABO AoGo 16mmØx2.40m, TUERCA Y CONTRATUERCA UND 25.28 116.00 2,932.48 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 116.00 ###
7.06 BLOQUE DE CONCRETO ARMADO DE 0.50 x 0.50 x 0.20m UND 30.00 116.00 3,480.00 0.00% 0.00 81.00 69.83% 2,430.00 81.00 69.83% 2,430.00 35.00 30.17%
7.07 ARANDELA DE ANCLAJE CUADRADA PLANA DE A°G° 102 x 102 x 6.35 mm, HUECO 18mmØ UND 3.22 116.00 373.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 116.00 ###
7.08 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 0.84 232.00 194.88 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 232.00 ###
7.09 AISLADOR DE PORCELANA TRACCION, CLASE ANSI 54-2 (RETENIDA MT) UND 0.67 116.00 77.72 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 116.00 ###
7.10 CANALETA GUARDACABLE DE F°G°, DE 2.4m DE LONG. CON PERNO Y TUERCA EN UN EXTREMO SACO 24.47 116.00 2,838.52 0.00 0.00% 0.00 0.00 0.00% 0.00 116.00 ###
7.11 JUEGO CONTRAPUNTA DE TUBO DE AºGº DE 2"Ø x1.50m. INCLUYE Abrazadera y pernos sujeción SACO 70.36 29.00 2,040.44 0.00 0.00% 0.00 0.00 0.00% 0.00 29.00 ###
7.12 ALAMBRE GALVANIZADO N° 12 AWG, PARA ENTORCHE M3 0.32 696.00 222.72 696.00 ###
SUB TOTAL 21,806.76 0.00 2,430.00 2,430.00
8.00 PUESTA A TIERRA Err:522 0.00 Err:522
8.01 CONDUCTOR DE COBRE DESNUDO CABLE TEMPLE BLANDO 25mm2, 7 Hilos m 7.19 3300.00 23,727.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 3,300.00 ###
8.02 CONECTOR DE ALEACION DE CU PARA ELECTRODO DE 16 mm Ø, TIPO UND 3.86 386.00 1,489.96 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 386.00 ###
8.03 ELECTRODO DE COPERWELD DE 16mm Ø(5/8")Ø x 2.40 m DE LONGITUD UND 40.25 101.00 4,065.25 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 101.00 ###
8.04 CONECTOR DE COBRE TIPO PERNO PARTIDO 25 mm2 (SPLIT BOLT) UND 4.03 170.00 685.10 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 170.00 ###
8.05 CONECTOR DE COBRE TIPO PERNO PARTIDO 35 mm2 (SPLIT BOLT) UND 4.99 148.00 738.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 148.00 ###
8.06 CAJA DE REGISTRO DE CONCRETO ARMADO DE 400 x 400 x 300mm CON TAPA UND 42.00 101.00 4,242.00 0.00% 0.00 81.00 80.20% 3,402.00 81.00 80.20% 3,402.00 20.00 19.80%
8.07 ARANDELA CUADRADA 152.4 x 152.4 x 6.35 mm - 18 mm DIA. Agujero. + TUERCA DE COBRE PARA MAQUINADO DE 16 UND 37.95 101.00 3,832.95 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 101.00 ###

Página 12 METRADO MT
VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

8.08 PLANCHA DE COBRE TIPO "J" PARA PUESTA A TIERRA UND 6.44 369.00 2,376.36 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 369.00 ###
8.09 TUBO PVC SAP DE 0,50m DE LONGITUD x 1/2" UND 1.01 215.00 217.15 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 215.00 ###
8.10 SAL INDUSTRIAL SACO DE 50 Kg. SACO 16.10 101.00 1,626.10 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 101.00 ###
8.11 BENTONITA SÓDICA (SACO 30 Kg) SACO 13.42 303.00 4,066.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 303.00 ###
8.12 TIERRA VEGETAL CERNIDA COMPACTADA M3 65.41 255.00 16,679.55 255.00 ###
SUB TOTAL 63,746.20 0.00 3,402.00 3,402.00

9.00 TABLEROS DE DISTRIBUCION Y EQUIPOS DE MEDICION Err:522 0.00


9.01 TABLERO DE DISTRIBUCION TIPO TD1 - 25 kVA 220 V 3Ø UND 2753.10 1.00 2,753.10 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
9.02 TABLERO DE DISTRIBUCION TIPO TD2 - 50 kVA 220 V 3Ø UND 2914.10 2.00 5,828.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
9.03 TABLERO DE DISTRIBUCION TIPO TD2 - 75 kVA 220 V 3Ø UND 2930.20 3.00 8,790.60 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 3.00 ###
9.04 TABLERO DE DISTRIBUCION TIPO TD2 - 100 kVA 220 V 3Ø UND 2930.20 2.00 5,860.40 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
9.05 TABLERO DE MEDICION DE PLANCHA LAF. Incluye Medidor Totalizador, Medidor de A.P. y Abrazaderas. UND 1470.09 22.00 32,341.98 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 22.00 ###
9.06 TABLERO DE DISTRIBUCION TIPO TD1 - 25 kVA 380/220 V 3Ø UND 2753.10 1.00 2,753.10 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
9.07 TABLERO DE DISTRIBUCION TIPO TD4 - 25 kVA 440/220 V 1Ø UND 2640.40 2.00 5,280.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
9.08 TABLERO DE DISTRIBUCION TIPO TD4 - 37.5 kVA 440/220 V 1Ø UND 2640.40 2.00 5,280.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
9.09 TABLERO DE DISTRIBUCION TIPO TD4 - 15 kVA 440/220 V 1 Ø UND 2640.40 9.00 23,763.60 0.00% 0.00% 0.00 9.00 ###
SUB TOTAL 92,652.58 0.00 0.00 0.00
10.00 OTROS
10.01 SEÑALIZACION UND 19.75 124.00 2449.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 124.00 ###
10.02 CORREA PLASTICA DE AMARRE 363 mm DE LONGITUD COLOR NEGRO UND 0.59 108.00 63.72 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 108.00 ###
10.03 CINTA AUTOVULCANIZANTE PARA 24 KV m 44.52 15.00 667.80 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 15.00 ###
3,180.52 0.00 0.00 0.00 0.00
TOTAL SUMINISTRO DE MATERIALES Err:522 718,003.27 5,832.00 5,832.00
0.00
MONTAJE ELECTROMECANICO MT

1.00 OBRAS PRELIMINARES Err:522 0.00


1.01 REPLANTEO E INGENIERIA DE DETALLE ( expediente conforme a obra y otros). km 475.87 8.36 3977.42 4.00 47.86% 1,903.48 2.00 23.93% 951.74 6.00 71.79% 2,855.22 2.36 28.21%
1.02 CAMPAMENTOS Y ALMACENES GLOBAL 9773.69 2.00 19547.38 0.00 0.00% 0.00 0.67 33.50% 6,548.37 0.67 33.50% 6,548.37 1.33 66.50%
1.03 SUPERVISION DEL I.N.C. (GASTOS DE C.I.R.A) GLOBAL 15000.00 1.00 15000.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
1.04 SEÑALIZACION DE ESTRUCTURAS; Numeración, señales de seguridad y otros (incluye suministro y pintado, código, fases segú UNID 18.75 124.00 2325.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 124.00 ###
1.05 CARTEL DE OBRA UND 1915.25 2.00 3830.50 0.00% 0.00 2.00 ### 3,830.50 2.00 ### 3,830.50 0.00 0.00%
1.06 ELABORACION DE EXPEDIENTE TECNICO IMPOSICION DE SERVIDUMBRE VALORIZADO km 975.00 8.36 8149.25 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 8.36 ###
1.07 DESPEJE DE ARBOLES (En diversos tramos del Proyecto) km 1533.50 1.29 1973.49 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 1.29 ###
SUB TOTAL 54,803.04 1,903.48 11,330.61 13,234.09
2.00 INSTALACION DE POSTES Err:522 0.00
2.01 TRANSPORTE POSTES 13 m DE CONCRETO DE M. T. DE ALMACEN A PUNTO DE IZAJE UND 99.94 107.00 10693.58 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 107.00 ###
2.02 TRANSPORTE POSTES 15 m DE CONCRETO DE M. T. DE ALMACEN A PUNTO DE IZAJE UND 133.23 22.00 2931.06 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 22.00 ###
2.03 EXCAVACION EN TERRENO NORMAL INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a verdederos, sólopara zonas urbana m3 51.67 65.00 3358.55 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 65.00 ###
2.04 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 13/300/2/180/375 UND 135.76 25.00 3394.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 25.00 ###
2.05 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 13/400/2/180/375 UND 135.76 82.00 11132.32 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 82.00 ###
2.06 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 15/400/2/225/450 UND 179.12 12.00 2149.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 12.00 ###

Página 13 METRADO MT
VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

2.07 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 15/500/2/225/450 UND 179.12 10.00 1791.20 0.00 0.00 0.00 10.00 ###
2.08 EXCAVACION EN TERRENO ROCOSO INC. (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urbanas) m3 153.40 28.00 4295.20 0.00 0.00 0.00 28.00 ###
2.09 CIMENTACION, SOLADO, RELLENO Y COMPACTACIÓN DE POSTES C.A.C. DE M.T. Concreto Fc' = 140 Kg/cm2 m3 133.73 36.00 4814.28 0.00 0.00 0.00 36.00 ###
2.10 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 153.04 4.00 612.16 0.00 0.00 0.00 4.00 ###
2.11 EXCAVACION EN TERRENO CON PAVIMENTO INC. (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urba m3 119.70 19.00 2274.30 0.00 0.00 19.00 ###
SUB TOTAL 47,446.09 0.00 0.00 0.00

3.00 INSTALACION DE RETENIDAS Err:522 0.00


3.01 EXCAVACION EN TERRENO NORMAL INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urban m3 67.77 99.00 6709.23 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 99.00 ###
3.02 EXCAVACION EN TERRENO ROCOSO INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urba m3 153.40 43.00 6596.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 43.00 ###
3.03 INSTALACION DE RETENIDA RI JGO 51.96 87.00 4520.52 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 87.00 ###
3.04 INSTALACION DE RETENIDA RV JGO 51.96 29.00 1506.84 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 29.00 ###
3.05 EXCAVACION EN TERRENO CON PAVIMENTO INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zon m3 119.70 4.67 558.47 0.00 0.00% 0.00 0.00 0.00% 0.00 4.67 ###
3.06 RELLENO Y COMPACTACION PARA EL BLOQUE DE ANCLAJE m3 45.09 99.00 4463.91 0.00 0.00% 0.00 0.00 0.00% 0.00 99.00 ###
3.07 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 153.04 3.00 459.12 0.00 0.00% 0.00 0.00 0.00% 0.00 3.00 ###
SUB TOTAL Err:522 24,814.29
0.00 0.00 0.00 0.00 0.00

4.00 MONTAJE DE ARMADOS Err:522 0.00


4.01 MONTAJE DE ARMADO TIPO PSV-2 (Sist. 2Ø - 22.9 kV) JGO 174.93 16.00 2798.88 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 16.00 ###
4.02 MONTAJE DE ARMADO TIPO PTSV-2B (Sist. 2Ø - 22.9 kV) JGO 153.09 10.00 1530.90 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 10.00 ###
4.03 MONTAJE DE ARMADO TIPO PA1-2 (Sist. 2Ø - 22.9 kV) JGO 102.07 11.00 1122.77 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 11.00 ###
4.04 MONTAJE DE ARMADO TIPO PRVM-2M (Sist. 2Ø - 22.9 kV) JGO 174.93 6.00 1049.58 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 6.00 ###
4.05 MONTAJE DE ARMADO TIPO PTSV-2P1 (Sist. 2Ø - 22.9 kV) JGO 153.09 5.00 765.45 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 5.00 ###
4.06 MONTAJE DE ARMADO TIPO PSEC-2 (Sist. 2Ø - 22.9 kV) JGO 408.23 6.00 2449.38 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 6.00 ###
4.07 MONTAJE DE ARMADO TIPO PR-2B (Sist. 2Ø - 22.9 kV) JGO 102.07 7.00 714.49 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 7.00 ###
4.08 MONTAJE DE ARMADO TIPO PS1-2L (Sist. 2Ø - 22.9 kV) JGO 136.08 2.00 272.16 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.09 MONTAJE DE ARMADO TIPO PA1P-2L (Sist. 2Ø - 22.9 kV) JGO 94.19 1.00 94.19 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.10 MONTAJE DE ARMADO TIPO PRP2-2L (Sist. 2Ø - 22.9 kV) JGO 94.19 13.00 1224.47 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 13.00 ###
4.11 MONTAJE DE ARMADO TIPO PSECP-2L (Sist. 2Ø - 22.9 kV) JGO 408.23 2.00 816.46 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.12 MONTAJE DE ARMADO TIPO SAM -2FP (Sist. 2Ø - 22.9 kV) JGO 979.75 3.00 2939.25 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 3.00 ###
4.13 MONTAJE DE ARMADO TIPO SAM-2FM (Sist. 2Ø - 22.9 kV) JGO 979.75 10.00 9797.50 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 10.00 ###
4.14 MONTAJE DE ARMADO TIPO DT-2 (Sist. 2Ø - 22.9 kV) JGO 204.11 2.00 408.22 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.15 MONTAJE DE ARMADO TIPO PTSV1 - 3 (Sist. 3Ø - 10.0 kV) JGO 244.93 1.00 244.93 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.16 MONTAJE DE ARMADO TIPO PSV1 - 3 (Sist. 3Ø - 10.0 kV) JGO 204.11 2.00 408.22 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.17 MONTAJE DE ARMADO TIPO PDV3 - 3 (Sist. 3Ø - 10.0 kV) JGO 204.11 1.00 204.11 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.18 MONTAJE DE ARMADO TIPO PR3 - 3 (Sist. 3Ø - 10.0 kV) JGO 204.11 2.00 408.22 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.19 MONTAJE DE ARMADO TIPO PSEC6-3 (Sist. 3Ø - 10.0 kV) JGO 1224.66 1.00 1224.66 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.20 MONTAJE DE ARMADO TIPO PA2-3 (Sist. 3Ø - 22.9 kV) JGO 204.11 4.00 816.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 4.00 ###
4.21 MONTAJE DE ARMADO TIPO PTSV1-3 (Sist. 3Ø - 22.9 kV) JGO 244.93 6.00 1469.58 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 6.00 ###
4.22 MONTAJE DE ARMADO TIPO PTV1-3 (Sist. 3Ø - 22.9 kV) JGO 244.93 1.00 244.93 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.23 MONTAJE DE ARMADO TIPO PSV1 - 3 (Sist. 3Ø - 22.9 kV) JGO 204.11 4.00 816.44 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 4.00 ###

Página 14 METRADO MT
VALORIZACION No. 02
METRADO VALORIZADO DE AVANCE MEDIA TENSION

PROYECTO : SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional : Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual : S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion : 180 d.c.
DISTRITO VARIOS Inicio de Obra : Jan-08
FECHA : Feb-08 Fin de obra : Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO
ACUMULADO
PRECIO METRADO
TOTAL
CODIGO DESCRIPCION UND UNITARIO CONTRACTU METRADO % COSTO METRADO % COSTO METRADO % COSTO METRADO % %
AL CONTRACTUAL
S/.

4.24 MONTAJE DE ARMADO TIPO DS-2 (Sist. 3Ø - 22.9 kV) JGO 204.11 8.00 1632.88 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 8.00 ###
4.25 MONTAJE DE ARMADO TIPO PSEC5-3 (Sist. 3Ø - 22.9 kV) JGO 612.34 1.00 612.34 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.26 MONTAJE DE ARMADO TIPO SAB1 - 3F (Sist. 3Ø - 22.9 kV) JGO 1224.66 4.00 4898.64 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 4.00 ###
4.27 MONTAJE DE ARMADO TIPO SAB1 - 3A (Sist. 3Ø - 22.9 kV) JGO 1224.66 1.00 1224.66 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.28 MONTAJE DE ARMADO TIPO SAM-3F (Sist. 3Ø - 22.9 kV) JGO 979.75 1.00 979.75 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.29 MONTAJE DE ARMADO TIPO EMP "+" (FASE) JGO 65.72 1.00 65.72 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
4.30 MONTAJE DE ARMADO TIPO EMP "T" (FASE) JGO 65.72 10.00 657.20 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 10.00 ###
4.31 MONTAJE DE ARMADO TIPO SAB1 - 3F (Sist. 3Ø - 10.0 kV) JGO 1224.66 2.00 2449.32 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 2.00 ###
4.32 MONTAJE DE ARMADO TIPO SAM1 - 3F (Sist. 3Ø - 10.0 kV) JGO 979.75 1.00 979.75 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 1.00 ###
SUB TOTAL 45,321.49 0.00%
0.00% 0.00
0.00 0.00% 0.00
0.00 0.00 0.00% 0.00
0.00 0.00
5.00 MONTAJE DE CONDUCTORES 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00
5.01 TENDIDO Y PUESTA EN FLECHA DE CONDUCTOR AAAC 25mm2 / FASE km 1768.86 11.59 20501.09 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 11.59 ###
5.02 TENDIDO Y PUESTA EN FLECHA DE CONDUCTOR AAAC 35mm2 / FASE km 1768.86 7.42 13124.94 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.00 7.42 ###
SUB TOTAL 33,626.03 0.00 0.00 0.00
6.00 INSTALACION DE PUESTA A TIERRA Err:522 0.00
6.01 EXCAVACION DE TERRENO NORMAL PARA PUESTA A TIERRA (Incluye y/o Eliminacion de desmonte a verdederos) m3 67.77 143.00 9691.11 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 143.00 ###
6.02 EXCAVACION DE TERRENO ROCOSO PARA PUESTA A TIERRA (Incluye y/o Eliminacion de desmonte a verdederos) m3 153.40 61.00 9357.40 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 61.00 ###
6.03 INSTALACION DE PUESTA A TIERRA TIPO PAT- 0 JGO 51.96 90.00 4676.40 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 90.00 ###
6.04 INSTALACION DE PUESTA A TIERRA TIPO PAT - 1 JGO 59.38 9.00 534.42 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 9.00 ###
6.05 INSTALACION DE PUESTA A TIERRA TIPO PAT - 2 JGO 69.29 46.00 3187.34 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 46.00 ###
6.06 EXCAVACION EN TERRENO CON PAVIMENTO PARA PUESTA A TIERRA INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a m3 119.70 10.00 1197.00 0.00 0.00 0.00 10.00 ###
6.07 SISTEMA DE PROTECCION ANTIRROBO DE LAS VARILLAS DE COBRE (Incluye materiales) UND 94.20 55.00 5181.00 0.00 0.00 0.00 55.00 ###
6.08 RELLENO Y COMPACTACION DE PUESTA A TIERRA m3 56.43 204.00 11511.72 0.00 0.00 0.00 204.00 ###
6.09 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 153.04 3.00 459.12 3.00 ###
SUB TOTAL 45,795.51 0.00 0.00 0.00
7.00 PRUEBAS Y PUESTA EN SERVICIO Err:522 0.00
7.01 PRUEBA Y PUESTA EN SERVICIO DE LAS REDES LOC 652.36 13.00 8480.68 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 13.00 ###
SUB TOTAL 8,480.68 0.00 0.00 0.00
TOTAL MONTAJE ELECTROMECANICO Err:522 260,287.13 1,903.48 11,330.61 13,234.09

TOTAL DESMONTAJE ELECTROMECANICO

1.00 DESMONTAJE ELECTROMECANICO

1.01 DESMONTAJE DE LINEA EXISTENTE (Incluye postes, redes, ferreteria, anclajes, subestaciones y otros. Asimismo incluye tra km 8052.26 0.36 2898.81 0.00% 0.36 ###
SUB-TOTAL 2,898.81
TOTAL DESMONTAJE ELECTROMECANICO 0.00 2,898.81

TOTAL 981,189.21 1,903.48 17,162.61 19,066.09

Página 15 METRADO MT
VALORIZACION No. 02
PLANILLA DE AVANCE BAJA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y
PROYECTO :
BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO

METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO %
CONTRACTUAL

SUMINISTRO DE MATERIALES
1.00 POSTES,CRUCETAS Y MENSULAS
1.01 POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 9/300/2/150/285, FABRICADO CON CEMENTO PORTLAND TIPO V,UND 772.00 324.00 324.00 448.00 58.03%
1.02 POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 8/300/2/120/240 INC. PERILLA PARA POSTE UND 6.00 6.00 6.00 0.00 0.00%
1.03 BASTIDOR DE F° G° DE 1.10 m DE LONGITUD KIT COMPLETO UND 24.00 0.00 24.00 100.00%
SUB TOTAL

2.00 CONDUCTORES
2.01 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x25+1x16 + P/25 m 1430.00 0.00 1,430.00 100.00%
2.02 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x16+1x16 + P/25 m 1090.00 0.00 1,090.00 100.00%
2.03 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x35+2x16 + P/25 m 870.00 0.00 870.00 100.00%
2.04 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x25+2x16 + P/25 m 9410.00 0.00 9,410.00 100.00%
2.05 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 3x16+2x16 + P/25 m 370.00 0.00 370.00 100.00%
2.06 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x35+1x16 + P/25 m 3030.00 0.00 3,030.00 100.00%
2.07 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x25+1x16 + P/25 m 6010.00 0.00 6,010.00 100.00%
2.08 CABLE AUTOPORTANTE AL TIPO CAAI C/ PORT. AL-AL AISLAD 2x16+1x16 + P/25 m 5800.00 0.00 5,800.00 100.00%
2.09 CABLE N2XY TETRAPOLAR 4 x 10mm2 m 310.00 0.00 310.00 100.00%
2,10 CORDON PORTATIL DE Cu (NLT) 2 x 2.5 mm2 m 920.00 0.00 920.00 100.00%
SUB TOTAL

3.00 AISLADORES
3.01 AISLADOR DE PORCELANA TRACCION, CLASE ANSI 54-1 (RETENIDA BT) UND 485.00 0.00 485.00 100.00%
SUB TOTAL

4.00 FERRRETERIA
4.01 PERNO MAQ. AºGº 16mmØ x 254mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 260.00 0.00 260.00 100.00%
4.02 PERNO OJO AºGº 16mmØ x 203mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 518.00 0.00 518.00 100.00%
4.03 PERNO OJO AºGº 16mmØ x 305mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 75.00 0.00 75.00 100.00%
4.04 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 152mm DE LONGITUD UND 3.00 0.00 3.00 100.00%
4.05 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 203mm DE LONGITUD UND 367.00 0.00 367.00 100.00%
4.06 PERNO CON GANCHO, 16mmD, PROVISTO DE TUERCA Y CONTRATUERCA DE 305mm DE LONGITUD UND 19.00 0.00 19.00 100.00%
4.07 TUERCA OJO DE A°G° PARA PERNO DE 16mm2 UND 154.00 0.00 154.00 100.00%
4.08 PORTALINEA UNIPOLAR DE A°G°, PARA AISLADOR CLASE ANSI 53-1 UND 520.00 0.00 520.00 100.00%
4.09 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 1552.00 0.00 1,552.00 100.00%
4.10 ARANDELA CUADRADA PLANA DE AºGº 57x57x5mm, HUECO 18mmØ UND 26.00 0.00 26.00 100.00%
4.11 CONECTOR TIPO CUÑA Al-Al 35/35 - 16 mm². UND 224.00 0.00 224.00 100.00%
4.12 CONECTOR TIPO CUÑA Al-Al 25/25 - 16 mm². UND 1454.00 0.00 1,454.00 100.00%
4.13 CONECTOR TIPO CUÑA Al-Al 16/16 - 16 mm². UND 1162.00 0.00 1,162.00 100.00%
4.14 CONECTOR BIMETALICO TIPO CUÑA Al/Cu, 16 mm²/16mm² UND 52.00 0.00 52.00 100.00%
4.15 CONECTOR BIMETALICO TIPO CUÑA Al/Cu, 25 mm²/25 mm² UND 18.00 0.00 18.00 100.00%
4.16 HEBILLA DE ACERO INOXIDABLE P' FLEJE 19 mm UND 260.00 0.00 260.00 100.00%
4.17 FLEJE DE ACERO INOXIDABLE (CINTA BAND IT), DE 19 mm m 208.00 0.00 208.00 100.00%
4.18 CAJA DE DERIVACION POLIMERICA 10 SALIDAS - 03 BARRAS UND 193.00 0.00 193.00 100.00%
4.19 CAJA DE DERIVACION POLIMERICA 10 SALIDAS - 04 BARRAS UND 67.00 0.00 67.00 100.00%
4.20 GRAPA DE SUSPENSION ANGULAR DE ALEACION DE ALUMINIO UND 388.00 0.00 388.00 100.00%
4.21 GRAPA DE ANCLAJE CONICA DE ALEACION DE ALUMINIO UND 748.00 0.00 748.00 100.00%
SUB TOTAL

5.00 RETENIDAS
5,01 CABLE A°G° DE 10 mm Ø GRADO SIEMENS MARTIN, 7 HILOS m 4850.00 0.00 4,850.00 100.00%
5,02 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx203mm, TUERCA Y CONTRATUERCA UND 454.00 0.00 454.00 100.00%
5,03 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx406mm, TUERCA Y CONTRATUERCA UND 31.00 0.00 31.00 100.00%
5,04 GRAPA PARALELA DOBLE VIA AºGº 3 PERNOS, 152mm LONG, PARA CABLE DE ACERO 10 mm2 UND 1940.00 0.00 1,940.00 100.00%
5,05 VARILLA DE ANCLAJE DE A° G° PROVISTO DE OJAL Y GUARDACABO 16mmØx1.80m, Tuerca y Contrat. UND 485.00 0.00 485.00 100.00%
5,06 BLOQUE DE CONCRETO ARMADO DE 0.40 x 0.40 x 0.15m UND 485.00 200.00 200.00 285.00 58.76%
5,07 ARANDELA DE ANCLAJE DE A°G° 102 x 102 x 5 mm, AGUJERO CENTRAL DE 18mmØ UND 485.00 0.00 485.00 100.00%
5,08 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 970.00 0.00 970.00 100.00%
5,09 JUEGO DE CONTRAPUNTA DE TUBO DE AºGº DE 2"Ø x1.00m CON ABRAZADERA PARTIDA Y PERNO DE AJUSTE UND 83.00 0.00 83.00 100.00%
5,10 CANALETA GUARDACBLE DE F° G° DE 2.4 m DE LONG. CON PERNO Y TUERCA EN UN EXTREMO. UND 485.00 0.00 485.00 100.00%
5,11 ALAMBRE DE F°G° N° 12 AWG, PARA ENTORCHADO m 1455.00 0.00 1,455.00 100.00%
SUB TOTAL
6.00 PUESTA A TIERRA
6,01 CONDUCTOR DE COBRE DESNUDO CABLE TEMPLE BLANDO 16mm2, 7 HILOS m 2048.00 0.00 2,048.00 100.00%
6,02 CONECTOR DE ALEACION DE COBRE PARA ELECTRODO DE 16mm∅ UND 256.00 0.00 256.00 100.00%
6,03 ELECTRODO DE COPPERWELD DE 16mm∅ x 2400mm DE LONGITUD (MAQUINADO) UND 128.00 0.00 128.00 100.00%
6,04 CONECTOR BIMETALICO TIPO CUÑA Al-Cu SEGÚN REQUERIMIENTO UND 128.00 0.00 128.00 100.00%
6,05 CAJA DE REGISTRO DE CONCRETO ARMADO DE 400 x 400 x 300mm CON TAPA UND 128.00 0.00 128.00 100.00%
6,06 SAL INDUSTRIAL (SACO 25 KG) SACO 256.00 0.00 256.00 100.00%
6,07 TUBO PVC SAP DE 20mmØ x 1.5m UND 128.00 0.00 128.00 100.00%
6,08 BENTONITA SODICA SACO DE 30 KG. SACO 384.00 0.00 384.00 100.00%
6,09 TIERRA VEGETAL CERNIDA PREPARADA PARA PUESTA A TIERRA M3 285.00 0.00 285.00 100.00%
6,10 ARANDELA DE ANCLAJE CUADRADA PLANA DE COBRE 152 x 152 x 6.35 mm, HUECO 18mmØ UND 128.00 0.00 128.00 100.00%
6,11 TUERCA DE COBRE PARA MAQUINADO DE 16 mmØ UND 128.00 0.00 128.00 100.00%
SUB TOTAL

Página 16 PLANILLA AVANCE BT


VALORIZACION No. 02
PLANILLA DE AVANCE BAJA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y
PROYECTO :
BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO

METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO %
CONTRACTUAL

7.00 EQUIPOS DE ALUMBRADO PUBLICO


7.01 CONECTOR BIMETALICO TIPO CUÑA Al-Cu 16 mm²/2.5 mm² UND 556.00 0.00 556.00 100.00%
7.02 PASTORAL PARABOLICO DE FºGº PP/1.10m/1.5m/38.1mmØ/15º TIPO UNIFIX UND 278.00 0.00 278.00 100.00%
7.03 ABRAZADERA DE AºGº PARA PASTORAL 39mmx125mmØ(POSTE)x25.4mmØ(PASTORAL), 5mm ESP. UND 486.00 0.00 486.00 100.00%
7.04 ABRAZADERA DE AºGº PARA PASTORAL 39mmx220mmØ(POSTE)x25.4mmØ(PASTORAL), 5mm ESP. UND 70.00 0.00 70.00 100.00%
SUB TOTAL

8.00 OTROS
8.01 CORREA PLASTICA DE AMARRE DE 363 mm long. x 54.4 kg resistente a la tracción COLOR NEGRO UND 2287.00 0.00 2,287.00 100.00%
8.02 CINTA AISLANTE m 1.60 0.00 1.60 100.00%
8.03 CINTA DE GOMA AUTOFUNDENTE HASTA 1000V m 1267.00 0.00 1,267.00 100.00%
8.04 SEPARADOR DE VIAS PVC UND 6.00 0.00 6.00 100.00%
SUB TOTAL
TOTAL SUMINISTRO DE MATERIALES
MONTAJE ELECTROMECANICO MT

1.00 OBRAS PRELIMINARES


1.01 REPLANTEO TOPOGRAFICO Y UBICACION DE ESTRUCTURAS km 26.16 21.00 21.00 5.16 19.73%
1.02 INGENIERIA DE DETALLE (Incluye cálculos justificativos, diseño, elaboración de expediente y otros) LOC. 12.00 0.00 3.00 3.00 9.00 75.00%
SUB TOTAL

2.00 INSTALACION DE POSTES


2.01 TRANSPORTE POSTES DE C.A.C. 8 m y 9 m DE ALMACEN A PUNTO DE IZAJE UND 65.19 0.00 65.19 100.00%
2.02 EXCAVACION EN TERRENO NORMAL (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) m3 46.91 0.00 46.91 100.00%
2.03 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 8 m y 9 m. m3 46.02 0.00 46.02 100.00%
2.04 PINTADO, SEÑALIZACION Y NUMERACIÓN DE ESTRUCTURAS (Incluye materiales, mano de obra y otros) UND 16.64 0.00 16.64 100.00%
2.05 CIMENTACION DE POSTES DE CONCRETO ARMADO CENTRIFUGADO DE 8, 9 y 11 m Fc=140 Kg/cm2 (Inc solado,) UND 108.82 0.00 108.82 100.00%
2.06 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 153.04 0.00 153.04 100.00%
2.07 EXCAVACION EN TERRENO ROCOSO (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) m3 153.40 0.00 153.40 100.00%
EXCAVACION EN TERRENO CON PAVIMENTO (Inc. Limpieza y/o Eliminacion de desmonte
2.08 a verdederos en zonas urbanas) m3 119.70 0.00 119.70 100.00%
SUB TOTAL

3.00 INSTALACION DE RETENIDAS


3.01 EXCAVACION EN TERRENO NORMAL (Inc. Limpieza, elimin.desmonte a vertederos en zonas urbanas) m3 61.52 0.00 0.00 0.00 61.52 100.00%
3.02 INSTALACION DE RETENIDA R1 m3 46.20 0.00 0.00 0.00 46.20 100.00%
3.03 INSTALACION DE RETENIDA R2 JGO 46.20 0.00 0.00 0.00 46.20 100.00%
3.04 INSTALACION DE RETENIDA R1P JGO 59.38 0.00 0.00 0.00 59.38 100.00%
3.05 INSTALACION DE RETENIDA R2P JGO 59.38 0.00 0.00 0.00 59.38 100.00%
3.06 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) JGO 153.04 0.00 0.00 0.00 153.04 100.00%
3.07 RELLENO Y COMPACTACION PARA EL BLOQUE DE ANCLAJE JGO 45.09 0.00 0.00 0.00 45.09 100.00%
3.08 EXCAVACION EN TERRENO ROCOSO (Inc. Limpieza y/o Eliminacion de desmonte a verdederos en zonas urbanas) JGO 153.40 0.00 0.00 0.00 153.40 100.00%
EXCAVACION EN TERRENO CON PAVIMENTO (Inc. Limpieza y/o Eliminacion de desmonte a
3.09 verdederos en zonas urbanas) m3 119.70 0.00 0.00 0.00 119.70 100.00%
SUB TOTAL
4.00 MONTAJE DE ARMADOS
4.01 MONTAJE DE ARMADO TIPO E1 JGO 19.88 0.00 19.88 100.00%
4.02 MONTAJE DE ARMADO TIPO E2 JGO 27.82 0.00 27.82 100.00%
4.03 MONTAJE DE ARMADO TIPO E3 JGO 23.20 0.00 23.20 100.00%
4.04 MONTAJE DE ARMADO TIPO E4 JGO 27.82 0.00 27.82 100.00%
4.05 MONTAJE DE ARMADO TIPO E5 JGO 30.91 0.00 30.91 100.00%
4.06 MONTAJE DE ARMADO TIPO E6 JGO 34.78 0.00 34.78 100.00%
4.07 MONTAJE DE ARMADO TIPO E7 JGO 23.20 0.00 23.20 100.00%
4.08 MONTAJE DE ARMADO TIPO E9 JGO 27.82 0.00 27.82 100.00%
4.09 MONTAJE DE ARMADO TIPO A1 JGO 39.72 0.00 39.72 100.00%
4.1 MONTAJE DE ARMADO TIPO A3 JGO 39.72 0.00 39.72 100.00%
4.11 MONTAJE DE ARMADO TIPO A4 JGO 39.72 0.00 39.72 100.00%
4.12 MONTAJE DE ARMADO TIPO E1P JGO 21.41 0.00 21.41 100.00%
4.13 MONTAJE DE ARMADO TIPO E2P JGO 30.91 0.00 30.91 100.00%
4.14 MONTAJE DE ARMADO TIPO E3P JGO 25.27 0.00 25.27 100.00%
4,15 MONTAJE DE ARMADO TIPO E7P JGO 25.27 0.00 25.27 100.00%
4,16 MONTAJE DE ARMADO TIPO E9P JGO 30.91 0.00 30.91 100.00%
4,17 MONTAJE DE ARMADO TIPO EMPALME EN "+" JGO 46.35 0.00 46.35 100.00%
4,18 MONTAJE DE ARMADO TIPO EMPALME EN "T" JGO 46.35 0.00 46.35 100.00%
4,19 MONTAJE DE CAJA DE DERIVACION TIPO TIPO CA10 220 V JGO 46.35 0.00 46.35 100.00%
4,20 MONTAJE DE CAJA DE DERIVACION TIPO TIPO CA10 220 V 3Ø JGO 46.35 46.35 100.00%
4,21 MONTAJE DE ARMADO TIPO E10 JGO 19.88 19.88 100.00%
4,22 MONTAJE DE ARMADO TIPO A4P JGO 46.35 46.35 100.00%
4,23 MONTAJE DE ARMADO TIPO E4P JGO 34.78 0.00 34.78 100.00%
4,24 MONTAJE DE ARMADO TIPO EMPALME EN "ET1" JGO 55.63 0.00 55.63 100.00%
SUB TOTAL

Página 17 PLANILLA AVANCE BT


VALORIZACION No. 02
PLANILLA DE AVANCE BAJA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y
PROYECTO :
BT- UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO

METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO %
CONTRACTUAL

5.00 MONTAJE DE CONDUCTORES


5.01 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x25+1x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5.02 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x16+1x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5.03 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x35+2x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5.04 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x25+2x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5.05 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 3x16+2x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5.06 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x35+1x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5,07 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x25+1x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
5,08 TENDIDO Y PUESTA EN FLECHA CABLE AUTOPORTANTE 2x16+1x16 + P/25 km 1245.42 0.00 1,245.42 100.00%
SUB TOTAL 0.00
0.00
6.00 INSTALACION DE PUESTA A TIERRA 0.00
EXCAVACION DE TERRENO NORMAL PARA PUESTA A TIERRA (Incluye Limpieza y/o
6.01 Eliminacion de desmonte a vertederos en zonas urbanas) m3 61.52 0.00 61.52 100.00%
6.02 INSTALACION DE PUESTA A TIERRA TIPO PATB-1 JGO 83.16 0.00 83.16 100.00%
6.03 SISTEMA DE PROTECCION ANTIRROBO DE LAS VARILLAS DE COBRE (Incluye materiales) UND 94.20 0.00 94.20 100.00%
6.04 RELLENO Y COMPACTACION DE PUESTA A TIERRA (Incluye caja de registro, ) m3 56.43 0.00 56.43 100.00%
6.05 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 153.04 0.00 153.04 100.00%
EXCAVACION DE TERRENO ROCOSO PARA PUESTA A TIERRA (Incluye Limpieza y/o
6,06 Eliminacion de desmonte a vertederos en zonas urbanas) m3 153.40 0.00 153.40 100.00%
6,07 EXCAVACION DE TERRENO CON PAVIMENTO PARA PUESTA A TIERRA (Incluye Limpieza y/o Eliminacion de desmonte m3 119.70 0.00 119.70 100.00%
SUB TOTAL
5.00 INSTALACION DE EQUIPOS DE ALUMBRADO PUBLICO
7.01 MONTAJE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP1 (postes B.T.) JGO 61.79 0.00 61.79 100.00%
7.02 MONTAJE DE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP1P (postes MT) JGO 74.14 0.00 74.14 100.00%
7,02 MONTAJE DE EQUIPO DE ALUMBRADO PUBLICO EN POSTE DE CONCRETO TIPO AP2 JGO 52.95 0.00 52.95 100.00%
SUB TOTAL

6.00 PRUEBAS Y PUESTA EN SERVICIO


6.01 PRUEBA Y PUESTA EN SERVICIO DE LAS REDES LOC 652.36 0.00 652.36 100.00%
SUB TOTAL

7.00 INSTALACION DE ACOMETIDAS


9.01 REINSTALACION DE ACOMETIDAS (Incluye materiales y demas accesorios) LOC 70.69 0.00 70.69 100.00%
SUB TOTAL

TOTAL MONTAJE ELECTROMECANICO

DESMONTAJE ELECTROMECANICO

1.00 DESMONTAJE ELECTROMECANICO

1.01 DESMONTAJE DE LINEA EXISTENTE (Incluye postes, redes, ferreteria, anclajes, y otros, asimismo incluye traslado a km 1.18 0.00 1.18 100.00%

SUB TOTAL

TOTAL DESMONTAJE ELECTROMECANICO


TOTAL

Página 18 PLANILLA AVANCE BT


VALORIZACION No. 02
PLANILLA DE AVANCE MEDIA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT-
PROYECTO :
UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO SALDO
M
E
T
METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO % R
CONTRACTUAL
A
D
O
SUMINISTRO DE MATERIALES
1.00 POSTES, BASTIDORES Y MENSULAS
1.01 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 13/300/2/180/375 INC. PERILLA UND 25.00 0.00 25.00 100.00%
1.02 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 13/400/2/180/375 INC. PERILLA UND 82.00 0.00 82.00 100.00%
1.03 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 15/400/2/225/450 INC. PERILLA UND 12.00 0.00 12.00 100.00%
1.04 POSTE DE CONCRETO ARMADO CENTRIFUGADO REFORZADO DE 15/500/2/225/450 INC. PERILLA UND 10.00 0.00 10.00 100.00%
1.05 PERFIL DE F° G° TIPO "U" DE 60 x 50 x 6 mm DE ESPESOR x 2.40 m DE LONGITUD UND 9.00 0.00 9.00 100.00%
1.06 PERFIL DE F° G° TIPO "U" DE 75 x 60 x 6 mm DE ESPESOR x 2.40 m DE LONGITUD UND 12.00 0.00 12.00 100.00%
1.07 PERFIL DE F° G° TIPO "U" DE 75 x 50 x 9.5 mm DE ESPESOR x 2.80 m DE LONGITUD UND 14.00 0.00 14.00 100.00%
1.08 BRAZO SOPORTE RIOSTRA DE PERFIL ANGULAR DE AoGo DE 38x38x5 mm, SECCION 0.71 LONG UND 20.00 0.00 20.00 100.00%
1.09 PERFIL DE F° G° TIPO "U" DE 64 x 64 x 6 .4mm DE ESPESOR x 1.50 m LONG. C/PERNO UND 2.00 0.00 2.00 100.00%
1.10 MEDIA LOZA DE C.A. 1.30/750. PARA SOPORTE DE TRANSFORMADOR UND 29.00 0.00 29.00 100.00%
1.11 CRUCETA SIMETRICA DE CONCRETO ARMADO VIBRADO DE Z/2.00/500 UND 2.00 0.00 2.00 100.00%
1.12 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 1 . Ver detalles. UND 122.00 0.00 122.00 100.00%
1.13 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 2 . Ver detalles. UND 75.00 0.00 75.00 100.00%
1.14 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 3 . Ver detalles. UND 3.00 0.00 3.00 100.00%
1.15 BASTIDOR PREFABRICADO CON PERFILES DE F° G°, TIPO 5 PARA SECCIONADOR. Ver detalles. UND 2.00 0.00 2.00 100.00%
1.16 PALOMILLA DE CONCRETO ARMADO DE 1.50 / 100 UND 18.00 0.00 18.00 100.00%
1.17 CRUCETA SIMETRICA DE CONCRETO ARMADO VIBRADO DE Z/1.50/300 UND 2.00 0.00 2.00 100.00%
1.18 CRUCETA ASIMETRICA DE C.A.V. DE ZA/1.50/0.90/250 UND 2.00 0.00 2.00 100.00%
1.19 MENSULA DE CONCRETO ARMADO VIBRADO DE M/1.00/250 UND 92.00 0.00 92.00 100.00%
1.20 MENSULA DE CONCRETO ARMADO VIBRADO DE M/0.60/250 UND 10.00 0.00 10.00 100.00%
1.21 MENSULA DE CONCRETO ARMADO VIBRADO DE M/1.50/250 UND 6.00 0.00 6.00 100.00%
SUB TOTAL 0.00
0.00
2.00 CONDUCTORES 0.00
2.01 CONDUCTOR DE ALEACION DE ALUMINIO 6201-T81 AAAC CABLEADO 25mm2, 7HILOS m 11590.00 0.00 11,590.00 100.00%
2.02 CONDUCTOR DE ALEACION DE ALUMINIO 6201-T81 AAAC CABLEADO 35mm2, 7HILOS m 7420.00 0.00 7,420.00 100.00%
2.03 CABLE DE CONTROL DEL TIPO CCT-B DE 12 x 14 AWG m 20.00 0.00 20.00 100.00%
2.04 ALAMBRE DE AMARRE DE ALUMINIO SOLIDO RECOCIDO TEMPLE BLANDO DE 16 mm2 m 520.00 0.00 520.00 100.00%
2.05 CABLE DE CONTROL DEL TIPO CCT-B DE 7 x 2.5 mm2 440 - 220 V m 40.00 0.00 40.00 100.00%
2.06 CABLE DE CONTROL DEL TIPO CCT-B DE 7 x 2.5 mm2 380 - 220 V m 15.00 0.00 15.00 100.00%
2.07 CONDUCTOR TIPO NA2XSA2Y-S 15 kV de 3 X 1X35 mm2 m 30.00 0.00 30.00 100.00%
2.08 CONDUCTOR TIPO NA2XSA2Y-S 30 kV de 3 X 1X35 mm2 m 130.00 0.00 130.00 100.00%
2.09 CABLE NYY EN FORMACION TRIPLE SECCION 3 x 1 x 25 mm2 m 80.00 0.00 80.00 100.00%
2.10 CABLE NYY EN FORMACION TRIPLE SECCION 3 x 1 x 10 mm2 m 110.00 0.00 110.00 100.00%
2.11 CABLE NYY CON FORMACION UNIPOLAR SECCION 1 x 35 mm2 m 75.00 0.00 75.00 100.00%
2.12 CABLE NYY EN FORMACION PARALELA SECCION 3 x1x 50 mm2 m 120.00 0.00 120.00 100.00%
2.13 CABLE NYY EN FORMACION PARALELA SECCION 2 x 1 x 35 mm2 m 70.00 0.00 70.00 100.00%
SUB TOTAL 0.00
0.00
3.00 TRANSFORMADORES DE DISTRIBUCION 0.00
3.01 TRANSFORMADOR 3Ø, MT, 3500 msnm, 10±2x2.5% / 0.23 kV DE 25 kVA UND 1.00 0.00 1.00 100.00%
3.02 TRANSFORMADOR 3Ø, MT, 3500 msnm, 10±2x2.5% / 0.23 kV DE 50 kVA UND 2.00 0.00 2.00 100.00%
3.03 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9.2±2x2.5% /0.40 - 0.23 kV DE 25 kVA UND 1.00 0.00 1.00 100.00%
3,04 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9.2±2x2.5% / 0.400-0.230 kV DE 75 kVA UND 3.00 0.00 3.00 100.00%
3,05 TRANSFORMADOR 3Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.400-0.23 kV DE 100 kVA UND 2.00 0.00 2.00 100.00%
3,06 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9.2±2x2.5% / 0.46-0.23 kV 37.5 kVA UND 2.00 0.00 2.00 100.00%
3,07 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.46-0.23 kV 25 kVA UND 2.00 0.00 2.00 100.00%
3,08 TRANSFORMADOR 1Ø, MT, 3500 msnm, 22.9±2x2.5% / 0.46-0.23 kV 15 kVA UND 9.00 0.00 9.00 100.00%
SUB TOTAL 0.00
0.00
4.00 EQUIPOS DE PROTECCION Y SECCIONAMIENTO 0.00
4.01 SECCIONADOR CUT-OUT 15 KV, 95 kV BIL, INOM 100 A. (Para tensión de servicio 10 kV) UND 12.00 0.00 12.00 100.00%
4.02 SECCIONADOR TIPO CUT OUT DE 27 kV, 125 kV BIL, 100 A (Para tensión de servicio22.9/ 13.2 kV) UND 63.00 0.00 63.00 100.00%
4.03 FUSIBLE DE EXPULSION TIPO K, UND 63.00 0.00 63.00 100.00%
4.04 PARARRAYO POLIMÉRICO DE OXIDO DE METAL, TIPO DISTRIBUCION 15 kV, 10 kA (Para tensión de servicio 10 kV) UND 12.00 0.00 12.00 100.00%
4.05 PARARRAYO POLIMÉRICO DE OXIDO DE METAL, TIPO DISTRIBUCION 21 kV, 10 kA UND 63.00 0.00 63.00 100.00%
SUB TOTAL 0.00
0.00
5.00 AISLADORES 0.00
5.01 AISLADOR POLIMERICO TIPO PIN DE 15 Kv(Vmin) CON ESPIGA A°G° PARA CRUCETA CAV DE POSTE (Tension servicio 10 k UND 30.00 0.00 30.00 100.00%
5.02 AISLADOR POLIMERICO TIPO PIN DE 35 Kv(Vmin) CON ESPIGA A°G° PARA CRUCETA CAV DE POSTE (Tension servicio 22.9 UND 164.00 0.00 164.00 100.00%
5.03 AISLADOR POLIMERICO TIPO SUSPENSION DE 17.5 Kv CON HERRAJE DE FºGº (tensión de servicio 10 kV) UND 24.00 0.00 24.00 100.00%
5.04 AISLADOR POLIMERICO TIPO SUSPENSION DE 36 Kv CON HERRAJE DE FºGº (tensión de servicio 22.9 kV) UND 253.00 0.00 253.00 100.00%
5.05 TERMINAL EXTERIOR TERMORESTRINGER PARA CABLE NA2XSA2Y-S, 15/8.7 KV PARA 35 mm² UND 10.00 0.00 10.00 100.00%
5.06 TERMINAL EXTERIOR TERMORESTRINGER PARA CABLE NA2XSA2Y-S, 30 KV PARA 35 mm² UND 22.00 0.00 22.00 100.00%
5.07 CAPUCHON POLIMERICO DE GOMA 10 KV , RELLENO CON GRASA SILICONADA UND 6.00 0.00 6.00 100.00%
5.08 CAPUCHON POLIMERICO DE GOMA 25 KV , RELLENO CON GRASA SILICONADA UND 18.00 0.00 18.00 100.00%
SUB TOTAL 0.00
0.00

Página 19 PLANILLA MT
VALORIZACION No. 02
PLANILLA DE AVANCE MEDIA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT-
PROYECTO :
UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO SALDO
M
E
T
METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO % R
CONTRACTUAL
A
D
O
6.00 FERRRETERIA 0.00
6.01 PERNO OJO AºGº DE 16mmØ x 152 LONG. 76mm, CON TUERCA Y CONTRATUERCA UND 76.00 0.00 76.00 100.00%
6.02 PERNO OJO AºGº DE 16mmØ x 203mm, CON TUERCA Y CONTRATUERCA UND 56.00 0.00 56.00 100.00%
6.03 PERNO OJO AºGº DE 16mmØ x 305mm, CON TUERCA Y CONTRATUERCA UND 88.00 0.00 88.00 100.00%
6.04 PERNO AºGº DE 9.5 mmØ x 38mm, CON TUERCA Y CONTRATUERCA UND 4.00 0.00 4.00 100.00%
6.05 PERNO MAQ. AºGº 16mmØ x 203mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 92.00 0.00 92.00 100.00%
6.06 PERNO MAQ. AºGº 13mmØ x 406mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 51.00 0.00 51.00 100.00%
6.07 PERNO MAQ. AºGº 16mmØ x 152mm LONG., CON TUERCA Y CONTRATUERCA UND 19.00 0.00 19.00 100.00%
6.08 PERNO MAQ. AºGº 16mmØ x 305mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 304.00 0.00 304.00 100.00%
6.09 PERNO MAQ. AºGº 16mmØ x 356mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 10.00 0.00 10.00 100.00%
6.1 PERNO MAQ. AºGº 16mmØ x 458mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 89.00 0.00 89.00 100.00%
6.11 PERNO MAQ. AºGº 16mmØ x 508mm LONG., 152mm MAQ., CON TUERCA Y CONTRATUERCA UND 47.00 0.00 47.00 100.00%
6.12 PERNO DOBLE ARMADO DE AºGº 16mmØ x 406mm LONGITUD CON ARANDELAS, TUERCA Y CONT. UND 29.00 0.00 29.00 100.00%
6.13 PERNO DOBLE ARMADO DE AºGº 16mmØ x 305mm LONGITUD CON ARANDELAS, TUERCA Y CONT. UND 18.00 0.00 18.00 100.00%
6.14 TUERCA OJO DE AoGo PARA PERNO DE 16mmØ UND 89.00 0.00 89.00 100.00%
6.15 HEBILLA DE ACERO INOXIDABLE PARA FLEJE DE 19 mm UND 43.00 0.00 43.00 100.00%
6.16 GRAPA ANCLAJE TIPO PISTOLA DE A° G° PARA CONDUCTOR DE 25 mm2. de 2 pernos UND 122.00 0.00 122.00 100.00%
6.17 CONECTOR DE ALUMINIO TIPO CUÑA DE 25 - 50 mm² SEGÚN REQUERIMIENTO UND 51.00 0.00 51.00 100.00%
6.18 ARANDELA CUADRADA CURVA DE AºGº 57x57x5mm, HUECO 18mmØ UND 730.00 0.00 730.00 100.00%
6.19 ARANDELA CUADRADA PLANA DE AºGº 57x57x5mm, HUECO 18mmØ UND 628.00 0.00 628.00 100.00%
6.2 ADAPTADOR TIPO LIRA DE ACERO FORJADO GALVANIZADO DE 16 mmØ x 78 mm LONG. UND 42.00 0.00 42.00 100.00%
6.21 GRAPA ANCLAJE TIPO PISTOLA DE A° G° PARA CONDUCTOR DE 35 mm2. de 2 pernos (3 pernos paravano > a 150 m) UND 113.00 0.00 113.00 100.00%
6.22 GRAPA DE SUSPENSION ANGULAR DE ALEACION DE Al. PARA CONDUCTOR DE ACUERDO REQ. UND 36.00 0.00 36.00 100.00%
6.23 GRAPA DE ALUMINIO TIPO DOBLE VIA PARA CONDUCTOR DE 25 mm2. UND 38.00 0.00 38.00 100.00%
6.24 GRAPA DE ALUMINIO TIPO DOBLE VIA PARA CONDUCTOR DE 35 mm2. UND 68.00 0.00 68.00 100.00%
6.25 TERMINAL DE COMPRESION BIMETALICO CON OREJA DE 9,5 mm Ø INC. PERNO Y ARAND. PRESION UND 26.00 0.00 26.00 100.00%
6.26 VARILLA DE ARMAR SIMPLE DE AL-AL, PARA CONDUCTOR DE 25 mm2 UND 26.00 0.00 26.00 100.00%
6.27 VARILLA DE ARMAR SIMPLE DE AL-AL, PARA CONDUCTOR DE 35mm2 UND 74.00 0.00 74.00 100.00%
6.28 PLATINA DE A°G° 652 LONG. x 50 mm ANCHO x 5 mm ESPESOR. CON DOS PERNOS SEGÚN DETALLE. UND 46.00 0.00 46.00 100.00%
6.29 VARILLA DE ARMAR DOBLE DE AL-AL, PARA CONDUCTOR DE 25 mm2 UND 16.00 0.00 16.00 100.00%
6.3 CINTA PLANA DE ARMAR 1.3x7.6 mm x 0.70 m DE LONGITUD. m 242.20 0.00 242.20 100.00%
6.31 FLEJE DE ACERO INOXIDABLE (CINTA BAND IT), DE 3/4" m 73.20 0.00 73.20 100.00%
6.32 PERNO DE A°G° 16 mm Ø x 51 mm LONG. CON ARANDELA, TUERCA Y CONTRATUERCA UND 20.00 0.00 20.00 100.00%
SUB TOTAL 0.00
0.00
7.00 RETENIDAS 0.00
7.01 CABLE A°G° SIEMENS MARTIN 10mm Ø, 7 HILOS m 1880.00 0.00 1,880.00 100.00%
7.02 PERNO ANGULAR OJO CON GUARDACABO AoGo 16mmØx254mm, TUERCA Y CONTRATUERCA UND 116.00 0.00 116.00 100.00%
7.03 GUARDACABO DE F° G° PARA CABLE DE 10 mm Ø UND 152.00 0.00 152.00 100.00%
7.04 GRAPA DOBLE VIA AºGº 3 PERNOS, 152mm LONG, PARA CABLE S.M. DE 10 mm2 UND 500.00 0.00 500.00 100.00%
7.05 VARILLA DE ANCLAJE CON GUARDACABO AoGo 16mmØx2.40m, TUERCA Y CONTRATUERCA UND 116.00 0.00 116.00 100.00%
7.06 BLOQUE DE CONCRETO ARMADO DE 0.50 x 0.50 x 0.20m UND 116.00 81.00 81.00 35.00 30.17%
7.07 ARANDELA DE ANCLAJE CUADRADA PLANA DE A°G° 102 x 102 x 6.35 mm, HUECO 18mmØ UND 116.00 0.00 116.00 100.00%
7.08 ARANDELA CUADRADA CURVADA DE AºGº 57x57x5mm, HUECO 18mmØ UND 232.00 0.00 232.00 100.00%
7.09 AISLADOR DE PORCELANA TRACCION, CLASE ANSI 54-2 (RETENIDA MT) UND 116.00 0.00 116.00 100.00%
7.10 CANALETA GUARDACABLE DE F°G°, DE 2.4m DE LONG. CON PERNO Y TUERCA EN UN EXTREMO SACO 116.00 0.00 116.00 100.00%
7.11 JUEGO CONTRAPUNTA DE TUBO DE AºGº DE 2"Ø x1.50m. INCLUYE Abrazadera y pernos sujeción SACO 29.00 0.00 29.00 100.00%
7.12 ALAMBRE GALVANIZADO N° 12 AWG, PARA ENTORCHE M3 696.00 0.00 696.00 100.00%
SUB TOTAL 0.00 0.00
8.00 PUESTA A TIERRA 0.00
8.01 CONDUCTOR DE COBRE DESNUDO CABLE TEMPLE BLANDO 25mm2, 7 Hilos m 3300.00 0.00 3,300.00 100.00%
8.02 CONECTOR DE ALEACION DE CU PARA ELECTRODO DE 16 mm Ø, TIPO UND 386.00 0.00 386.00 100.00%
8.03 ELECTRODO DE COPERWELD DE 16mm Ø(5/8")Ø x 2.40 m DE LONGITUD UND 101.00 0.00 101.00 100.00%
8.04 CONECTOR DE COBRE TIPO PERNO PARTIDO 25 mm2 (SPLIT BOLT) UND 170.00 0.00 170.00 100.00%
8.05 CONECTOR DE COBRE TIPO PERNO PARTIDO 35 mm2 (SPLIT BOLT) UND 148.00 0.00 148.00 100.00%
8.06 CAJA DE REGISTRO DE CONCRETO ARMADO DE 400 x 400 x 300mm CON TAPA UND 101.00 81.00 81.00 20.00 19.80%
8.07 ARANDELA CUADRADA 152.4 x 152.4 x 6.35 mm - 18 mm DIA. Agujero. + TUERCA DE COBRE PARA MAQUINADO DE 16 UND 101.00 0.00 101.00 100.00%
8.08 PLANCHA DE COBRE TIPO "J" PARA PUESTA A TIERRA UND 369.00 0.00 369.00 100.00%
8.09 TUBO PVC SAP DE 0,50m DE LONGITUD x 1/2" UND 215.00 0.00 215.00 100.00%
8.10 SAL INDUSTRIAL SACO DE 50 Kg. SACO 101.00 0.00 101.00 100.00%
8.11 BENTONITA SÓDICA (SACO 30 Kg) SACO 303.00 0.00 303.00 100.00%
8.12 TIERRA VEGETAL CERNIDA COMPACTADA M3 255.00 0.00 255.00 100.00%
SUB TOTAL 0.00
0.00
9.00 TABLEROS DE DISTRIBUCION Y EQUIPOS DE MEDICION 0.00
9.01 TABLERO DE DISTRIBUCION TIPO TD1 - 25 kVA 220 V 3Ø UND 1.00 0.00 1.00 100.00%
9.02 TABLERO DE DISTRIBUCION TIPO TD2 - 50 kVA 220 V 3Ø UND 2.00 0.00 2.00 100.00%
9.03 TABLERO DE DISTRIBUCION TIPO TD2 - 75 kVA 220 V 3Ø UND 3.00 0.00 3.00 100.00%
9.04 TABLERO DE DISTRIBUCION TIPO TD2 - 100 kVA 220 V 3Ø UND 2.00 0.00 2.00 100.00%
9.05 TABLERO DE MEDICION DE PLANCHA LAF. Incluye Medidor Totalizador, Medidor de A.P. y Abrazaderas. UND 22.00 0.00 22.00 100.00%
9.06 TABLERO DE DISTRIBUCION TIPO TD1 - 25 kVA 380/220 V 3Ø UND 1.00 0.00 1.00 100.00%
9.07 TABLERO DE DISTRIBUCION TIPO TD4 - 25 kVA 440/220 V 1Ø UND 2.00 0.00 2.00 100.00%
9.08 TABLERO DE DISTRIBUCION TIPO TD4 - 37.5 kVA 440/220 V 1Ø UND 2.00 0.00 2.00 100.00%
9.09 TABLERO DE DISTRIBUCION TIPO TD4 - 15 kVA 440/220 V 1 Ø UND 9.00 0.00 9.00 100.00%
SUB TOTAL 0.00

Página 20 PLANILLA MT
VALORIZACION No. 02
PLANILLA DE AVANCE MEDIA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT-
PROYECTO :
UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO SALDO
M
E
T
METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO % R
CONTRACTUAL
A
D
O
10.00 OTROS 0.00
10.01 SEÑALIZACION UND 124.00 0.00 124.00 100.00%
10.02 CORREA PLASTICA DE AMARRE 363 mm DE LONGITUD COLOR NEGRO UND 108.00 0.00 108.00 100.00%
10.03 CINTA AUTOVULCANIZANTE PARA 24 KV m 15.00 0.00 15.00 100.00%
0.00
TOTAL SUMINISTRO DE MATERIALES
MONTAJE ELECTROMECANICO MT 0.00
0.00
1.00 OBRAS PRELIMINARES 0.00
1.01 REPLANTEO E INGENIERIA DE DETALLE ( expediente conforme a obra y otros). km 8.36 4.00 2.00 6.00 2.36 28.21%
1.02 CAMPAMENTOS Y ALMACENES GLOBAL 2.00 0.00 0.67 0.67 1.33 66.50%
1.03 SUPERVISION DEL I.N.C. (GASTOS DE C.I.R.A) GLOBAL 1.00 0.00 1.00 100.00%
1.04 SEÑALIZACION DE ESTRUCTURAS; Numeración, señales de seguridad y otros (incluye suministro y pintado, código, fases segú UNID 124.00 0.00 124.00 100.00%
1.05 CARTEL DE OBRA UND 2.00 2.00 2.00 0.00 0.00%
1.06 ELABORACION DE EXPEDIENTE TECNICO IMPOSICION DE SERVIDUMBRE VALORIZADO km 8.36 0.00 8.36 100.00%
1.07 DESPEJE DE ARBOLES (En diversos tramos del Proyecto) km 1.29 0.00 1.29 100.00%
SUB TOTAL 0.00
0.00
2.00 INSTALACION DE POSTES 0.00
2.01 TRANSPORTE POSTES 13 m DE CONCRETO DE M. T. DE ALMACEN A PUNTO DE IZAJE UND 107.00 0.00 107.00 100.00%
2.02 TRANSPORTE POSTES 15 m DE CONCRETO DE M. T. DE ALMACEN A PUNTO DE IZAJE UND 22.00 0.00 22.00 100.00%
2.03 EXCAVACION EN TERRENO NORMAL INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a verdederos, sólopara zonas urbana m3 65.00 0.00 65.00 100.00%
2.04 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 13/300/2/180/375 UND 25.00 0.00 25.00 100.00%
2.05 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 13/400/2/180/375 UND 82.00 0.00 82.00 100.00%
2.06 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 15/400/2/225/450 UND 12.00 0.00 12.00 100.00%
2.07 IZAJE DE POSTE DE CONCRETO ARMADO CENTRIFUGADO DE 15/500/2/225/450 UND 10.00 0.00 10.00 100.00%
2.08 EXCAVACION EN TERRENO ROCOSO INC. (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urbanas) m3 28.00 0.00 28.00 100.00%
2.09 CIMENTACION, SOLADO, RELLENO Y COMPACTACIÓN DE POSTES C.A.C. DE M.T. Concreto Fc' = 140 Kg/cm2 m3 36.00 0.00 36.00 100.00%
2.10 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 4.00 0.00 4.00 100.00%
2.11 EXCAVACION EN TERRENO CON PAVIMENTO INC. (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urba m3 19.00 0.00 19.00 100.00%
SUB TOTAL 0.00
0.00
3.00 INSTALACION DE RETENIDAS 0.00
3.01 EXCAVACION EN TERRENO NORMAL INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urban m3 99.00 0.00 99.00 100.00%
3.02 EXCAVACION EN TERRENO ROCOSO INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zonas urba m3 43.00 0.00 43.00 100.00%
3.03 INSTALACION DE RETENIDA RI JGO 87.00 0.00 87.00 100.00%
3.04 INSTALACION DE RETENIDA RV JGO 29.00 0.00 29.00 100.00%
3.05 EXCAVACION EN TERRENO CON PAVIMENTO INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a vertederos solo en zon m3 4.67 0.00 4.67 100.00%
3.06 RELLENO Y COMPACTACION PARA EL BLOQUE DE ANCLAJE m3 99.00 0.00 99.00 100.00%
3.07 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 3.00 0.00 3.00 100.00%
SUB TOTAL 0.00
0.00
4.00 MONTAJE DE ARMADOS 0.00
4.01 MONTAJE DE ARMADO TIPO PSV-2 (Sist. 2Ø - 22.9 kV) JGO 16.00 0.00 16.00 100.00%
4.02 MONTAJE DE ARMADO TIPO PTSV-2B (Sist. 2Ø - 22.9 kV) JGO 10.00 0.00 10.00 100.00%
4.03 MONTAJE DE ARMADO TIPO PA1-2 (Sist. 2Ø - 22.9 kV) JGO 11.00 0.00 11.00 100.00%
4.04 MONTAJE DE ARMADO TIPO PRVM-2M (Sist. 2Ø - 22.9 kV) JGO 6.00 0.00 6.00 100.00%
4.05 MONTAJE DE ARMADO TIPO PTSV-2P1 (Sist. 2Ø - 22.9 kV) JGO 5.00 0.00 5.00 100.00%
4.06 MONTAJE DE ARMADO TIPO PSEC-2 (Sist. 2Ø - 22.9 kV) JGO 6.00 0.00 6.00 100.00%
4.07 MONTAJE DE ARMADO TIPO PR-2B (Sist. 2Ø - 22.9 kV) JGO 7.00 0.00 7.00 100.00%
4.08 MONTAJE DE ARMADO TIPO PS1-2L (Sist. 2Ø - 22.9 kV) JGO 2.00 0.00 2.00 100.00%
4.09 MONTAJE DE ARMADO TIPO PA1P-2L (Sist. 2Ø - 22.9 kV) JGO 1.00 0.00 1.00 100.00%
4.10 MONTAJE DE ARMADO TIPO PRP2-2L (Sist. 2Ø - 22.9 kV) JGO 13.00 0.00 13.00 100.00%
4.11 MONTAJE DE ARMADO TIPO PSECP-2L (Sist. 2Ø - 22.9 kV) JGO 2.00 0.00 2.00 100.00%
4.12 MONTAJE DE ARMADO TIPO SAM -2FP (Sist. 2Ø - 22.9 kV) JGO 3.00 0.00 3.00 100.00%
4.13 MONTAJE DE ARMADO TIPO SAM-2FM (Sist. 2Ø - 22.9 kV) JGO 10.00 0.00 10.00 100.00%
4.14 MONTAJE DE ARMADO TIPO DT-2 (Sist. 2Ø - 22.9 kV) JGO 2.00 0.00 2.00 100.00%
4.15 MONTAJE DE ARMADO TIPO PTSV1 - 3 (Sist. 3Ø - 10.0 kV) JGO 1.00 0.00 1.00 100.00%
4.16 MONTAJE DE ARMADO TIPO PSV1 - 3 (Sist. 3Ø - 10.0 kV) JGO 2.00 0.00 2.00 100.00%
4.17 MONTAJE DE ARMADO TIPO PDV3 - 3 (Sist. 3Ø - 10.0 kV) JGO 1.00 0.00 1.00 100.00%
4.18 MONTAJE DE ARMADO TIPO PR3 - 3 (Sist. 3Ø - 10.0 kV) JGO 2.00 0.00 2.00 100.00%
4.19 MONTAJE DE ARMADO TIPO PSEC6-3 (Sist. 3Ø - 10.0 kV) JGO 1.00 0.00 1.00 100.00%
4.20 MONTAJE DE ARMADO TIPO PA2-3 (Sist. 3Ø - 22.9 kV) JGO 4.00 0.00 4.00 100.00%
4.21 MONTAJE DE ARMADO TIPO PTSV1-3 (Sist. 3Ø - 22.9 kV) JGO 6.00 0.00 6.00 100.00%
4.22 MONTAJE DE ARMADO TIPO PTV1-3 (Sist. 3Ø - 22.9 kV) JGO 1.00 0.00 1.00 100.00%
4.23 MONTAJE DE ARMADO TIPO PSV1 - 3 (Sist. 3Ø - 22.9 kV) JGO 4.00 0.00 4.00 100.00%
4.24 MONTAJE DE ARMADO TIPO DS-2 (Sist. 3Ø - 22.9 kV) JGO 8.00 0.00 8.00 100.00%
4.25 MONTAJE DE ARMADO TIPO PSEC5-3 (Sist. 3Ø - 22.9 kV) JGO 1.00 0.00 1.00 100.00%
4.26 MONTAJE DE ARMADO TIPO SAB1 - 3F (Sist. 3Ø - 22.9 kV) JGO 4.00 0.00 4.00 100.00%
4.27 MONTAJE DE ARMADO TIPO SAB1 - 3A (Sist. 3Ø - 22.9 kV) JGO 1.00 0.00 1.00 100.00%
4.28 MONTAJE DE ARMADO TIPO SAM-3F (Sist. 3Ø - 22.9 kV) JGO 1.00 0.00 1.00 100.00%
4.29 MONTAJE DE ARMADO TIPO EMP "+" (FASE) JGO 1.00 0.00 1.00 100.00%
4.30 MONTAJE DE ARMADO TIPO EMP "T" (FASE) JGO 10.00 0.00 10.00 100.00%
4.31 MONTAJE DE ARMADO TIPO SAB1 - 3F (Sist. 3Ø - 10.0 kV) JGO 2.00 0.00 2.00 100.00%
4.32 MONTAJE DE ARMADO TIPO SAM1 - 3F (Sist. 3Ø - 10.0 kV) JGO 1.00 0.00 1.00 100.00%
SUB TOTAL 0.00
0.00 0.00

Página 21 PLANILLA MT
VALORIZACION No. 02
PLANILLA DE AVANCE MEDIA TENSION

SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO PARA LA "AMPLIACION DE REDES MT Y BT-
PROYECTO :
UU.NN. HUANUCO-PARTE II"
UU. NN. HUANUCO Emp Regional Electrocentro S.A.
DPTO HUANUCO Presupuesto Contractual S/. 2,978,568.93
PROVINCIA HUANUCO,YAROWILCA Y DOS DE MAYO Plazo ejecucion 180 d.c.
DISTRITO VARIOS Inicio de Obra Jan-08
FECHA : Feb-08 Fin de obra Jul-08

AVANCE CORRESPONDIENTE AL MES DE FEBRERO 2008


ANTERIOR ACTUAL ACUMULADO SALDO SALDO
M
E
T
METRADO
CODIGO DESCRIPCION UND METRADO METRADO METRADO METRADO % R
CONTRACTUAL
A
D
O
5.00 MONTAJE DE CONDUCTORES 0.00
5.01 TENDIDO Y PUESTA EN FLECHA DE CONDUCTOR AAAC 25mm2 / FASE km 11.59 0.00 11.59 100.00%
5.02 TENDIDO Y PUESTA EN FLECHA DE CONDUCTOR AAAC 35mm2 / FASE km 7.42 0.00 7.42 100.00%
SUB TOTAL 0.00
0.00
6.00 INSTALACION DE PUESTA A TIERRA 0.00
6.01 EXCAVACION DE TERRENO NORMAL PARA PUESTA A TIERRA (Incluye y/o Eliminacion de desmonte a verdederos) m3 143.00 0.00 143.00 100.00%
6.02 EXCAVACION DE TERRENO ROCOSO PARA PUESTA A TIERRA (Incluye y/o Eliminacion de desmonte a verdederos) m3 61.00 0.00 61.00 100.00%
6.03 INSTALACION DE PUESTA A TIERRA TIPO PAT- 0 JGO 90.00 0.00 90.00 100.00%
6.04 INSTALACION DE PUESTA A TIERRA TIPO PAT - 1 JGO 9.00 0.00 9.00 100.00%
6.05 INSTALACION DE PUESTA A TIERRA TIPO PAT - 2 JGO 46.00 0.00 46.00 100.00%
6.06 EXCAVACION EN TERRENO CON PAVIMENTO PARA PUESTA A TIERRA INCLUYE (LIMPIEZA y/o Eliminacion de desmonte a m3 10.00 0.00 10.00 100.00%
6.07 SISTEMA DE PROTECCION ANTIRROBO DE LAS VARILLAS DE COBRE (Incluye materiales) UND 55.00 0.00 55.00 100.00%
6.08 RELLENO Y COMPACTACION DE PUESTA A TIERRA m3 204.00 0.00 204.00 100.00%
6.09 RESANE DE VEREDAS CONCRETO Fc' = 140 Kg/cm2 (donde corresponda) m3 3.00 0.00 3.00 100.00%
SUB TOTAL 0.00
0.00
7.00 PRUEBAS Y PUESTA EN SERVICIO 0.00
7.01 PRUEBA Y PUESTA EN SERVICIO DE LAS REDES LOC 13.00 0.00 13.00 100.00%
SUB TOTAL 0.00
0.00
TOTAL MONTAJE ELECTROMECANICO 0.00
0.00
TOTAL DESMONTAJE ELECTROMECANICO 0.00
0.00
1.00 DESMONTAJE ELECTROMECANICO 0.00
1.01 DESMONTAJE DE LINEA EXISTENTE (Incluye postes, redes, ferreteria, anclajes, subestaciones y otros. Asimismo incluye tra km 0.36 0.00 0.36 100.00%
SUB-TOTAL

TOTAL DESMONTAJE ELECTROMECANICO

TOTAL

Página 22 PLANILLA MT
CODIGO PR01-R03
REVISION 01
FECHA 8/10/2006

ACTA DE CONFORMIDAD DE SERVICIO


DE AREA DE ADMINISTRACION DE PROYECTOS

PARA GERENCIA DE ADMINISTRACION Y FINANZAS

FECHA 29 DE FEBRERO DE 2008

PROVEEDOR TECSUR S.A.

R.U.C. 20206018411

CONTRATO Nro: GR-126-2007/ELCTO DEL: 10/25/2007

DOCUMENTO GPO. TECSUR-RO/HU-23-2008 Nro:

COMPROBANTE DE PAGO FACTURA Nro: 003-0009661

VALOR DEL SERVICIO 168,285.00

I.G.V.-19% 31,974.15

PRECIO TOTAL DEL SERVICIO S/. 200,259.15

SON: Doscientos mil doscientos cincuenta y nueve con 15/100 Nuevos Soles

PENALIDAD NOTA DE CREDITO Nro:


Importe

Marcar con: X Código Detalle


CeCo / / GRAFO / X /OM/ / AMPLIACION REDES MT Y BT
40000488/VARIOS UUNN HUANUCO - PARTE II

Nota: Caso se indique varios CeCos, este debe indicarse en el anexo que formará parte de la presente Acta de Conformidad, asignandose para cada
valor. Si son pocos CeCos y alcanza, indicar en el detalle del servicio. Si asigna solo CeCo o bien GRAFO

DETALLE DEL SERVICIO

VALORIZACION N°02, CORRESPONDIENTE AL MES DE FEBRERO DEL 2008

ANEXA Cuadro a la presente


Conformidad de Servicio? Indicar:
SI / NO SI
Nota:Caso anexa cuadro, este formará parte de la Conformidad de Servicio, este debe indicar: Item,fecha del servicio, concepto, nombres,etc.,
cantidad, precio unitario y total parcial y Total General.

Se dá la conformidad del servicio realizado y por lo tanto, solicito se proceda con el trámite de
pago respectivo, para el cual se sellan y firman.

VoBo ES CONFORME

_________________________
Responsable de área Gerente de área y/o Jefe de
Unidad de Negocio
CUADRO 01: RESUMEN GENERAL

"SUMINISTRO DE MATERIALES, TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y


Proyecto PUESTA EN SERVICIO PARA MEJORA DE LA AMPLIACION DE REDES MT Y BT UU. NN.
HUANUCO - PARTE II"

Mes Valorización FEBRERO

Año Valorización 2008

Contrato GR - 126 - 2007 / ELCTO

METRADO BASE VALORIZACION N° 01 (ENERO 2008) VALORIZACION N° 02 (ENERO 2008)


DESCRIPCION
ITEM % BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL BAJA TENSION MEDIA TENSION TOTAL

I SUMINISTRO DE MATERIALES 717,255.06 718,003.27 1,435,258.33 0.00 0.00 0.00 123,978.00 5,832.00 129,810.00

II MONTAJE ELECTROMECANICO 372,614.18 260,287.13 632,901.31 10,274.46 1,903.48 12,177.94 2,643.90 11,330.61 13,974.51

III DESMONTAJE ELECTROMECANICO 9,187.11 2,898.81 12,085.92 0.00 0.00 0.00

IV TRANSPORTE DE MATERIALES 11.00% 78,898.06 78,980.36 157,878.42 0.00 0.00 0.00 13,637.58 641.52 14,279.10

V TOTAL COSTO DIRECTO (C.D.) 1,177,954.41 1,060,169.57 2,238,123.98 10,274.46 1,903.48 12,177.94 140,259.48 17,804.13 158,063.61

VI GASTOS GENERALES DIRECTOS 23.08% 271,910.58 244,721.97 516,632.55 2,371.68 439.39 2,811.07 32,376.50 4,109.78 36,486.28

VII UTILIDADES 10.00% 117,795.44 106,016.96 223,812.40 1,027.45 190.35 1,217.79 14,025.95 1,780.41 15,806.36

VIII TOTAL REDES MT Y BT (SIN I.G.V.) 1,567,660.43 1,410,908.50 2,978,568.93 13,673.59 2,533.21 16,206.80 186,661.92 23,694.32 210,356.25

IX AMORTIZACION TOTAL DEL ADELANTO 5,469.44 1,013.29 6,482.72 37,332.38 4,738.86 42,071.25

X COSTO NETO A CANCELAR 8,204.15 1,519.93 9,724.08 149,329.54 18,955.46 168,285.00

IX IGV (19%) 297,855.48 268,072.61 565,928.10 1,558.79 288.79 1,847.58 28,372.61 3,601.54 31,974.15

XII MONTO TOTAL CANCELADO 1,865,515.91 1,678,981.11 3,544,497.02 9,762.94 1,808.72 11,571.66 177,702.15 22,557.00 200,259.15

AMORTIZACION AMORTIZACION
XIII ADELANTO (20%) SIN IGV 708,899.41 6,482.72 42,071.25
FALTA POR AMORTIZAR 702,416.69 660,345.44

XIV AVANCE FISICO MENSUAL 0.54 7.06


AVANCE FISICO ACUMULADO 0.54 7.61

XV AVANCE ECONOMICO MENSUAL 24.13 29.45


AVANCE ECONOMICO ACUMULADO 24.13 29.78
CALENDARIO VALORIZADO MENSUAL DE AVANCE DE OBRA
OBRA: FECHA : 7-ene-08
“SUMINISTRO TRANSPORTE, MONTAJE ELECTROMECANICO, PRUEBAS Y PUESTA EN SERVICIO
PARA LA AMPLIACION DE REDES MT Y BT HUANUCO - PARTE II"
MONTO MENSUAL DE AVANCE DE OBRA $. (SIN IGV) AVANCE MENSUAL

Acumulado
AVANCE ACUMULADO AVANCE ACUMULADO

Avance
Nro REDES DE DISTRIBUCION REDES DE DISTRIBUCION TOTAL
MES PRIMARIAS SECUNDARIAS Total Total
Val Sección 1 Sección 2 Programado Ejecutado Programado Real Programado Real/Prog.
(Prog.) Ejecutado (Prog.) Ejecutado

Jan-08 1 1,751 2,533 2,541 13,674 4,292 16,207 4,292 16,207 0.54% 0.14% 377.62%
Feb-08 2 8,806 23,694 10,379 186,662 19,185 210,356 23,477 226,563 7.61% 0.79% 965.06%
Mar-08 3 65,045 82,381 147,426 - 170,902 226,563 7.61% 5.74% 132.57%
Apr-08 4 682,638 753,127 1,435,765 - 1,606,667 226,563 7.61% 53.94% 14.10%
May-08 5 520,581 563,550 1,084,131 - 2,690,798 226,563 7.61% 90.34% 8.42%
Jun-08 6 132,087 155,683 287,770 - 2,978,569 226,563 7.61% 100.00% 7.61%
0 0.00% 0.00% 0.00%
0 0.00% 0.00% 0.00%
0 0.00% 0.00% 0.00%
TOTAL 7 1,410,908 26,227.53 1,567,660 200,335.51 2,978,569 226,563 2,978,569 226,563 7.61% 100.00% 7.61%

AVANCE FISICO MENSUAL


3000000 3000000
2800000 2800000
2600000 2600000
2400000 2400000
2200000 2200000
2000000 2000000
1800000 1800000
1600000 1600000
1400000 1400000
1200000 1200000
1000000 1000000
800000 800000
600000 600000
400000 400000
200000 200000
0 0
39448 39479 39508 39539 39569 39600
MESES Programado Ejecutado Programado
Ejecutado
1000000 1000000
800000 800000
600000 600000
400000 400000
200000 200000
0 0
39448 39479 39508 39539 39569 39600
MESES Programado Ejecutado Programado
Ejecutado

Potrebbero piacerti anche