Sei sulla pagina 1di 41

DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :


LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS

DESCRIPTION: Installation of retrofitting materials including welding QUANTITY :


ITEM NO:
works UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 WELDING ROD, 6011 1/8 3.2 4900.09 kgs 160.00
2 WELDING ROD, 6011 1/8 4.0 3417.75 boxes 135.00

Sub Total A

B. LABOR
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Foreman 1 75 900.00
2 Rigger-Welder 20 75 750.00
3 Helper 10 75 500.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Welding Machine 4 75 899.83
2 Torque Wrench 2 75 561.00
3 Nylone Rope 4 75 400.50
4 Pulley 2 75 350.00
5 Mechanical Winch 1 75 675.00
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


TAILED UNIT PRICE ANALYSIS
49.00
Php / kg
UNIT PRICE ANALYSIS
69189.45
kgs

AMOUNT

784,013.86
461,396.25
-
1,245,410.11

AMOUNT
67,500.00
1,125,000.00
375,000.00

1,567,500.00

AMOUNT
269,947.95
84,150.00
120,150.00
52,500.00
50,625.00
577,372.95

3,390,283.06

18.00
31.00
49.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: Tower Electrcal System
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 Tower Light Top Light (Avialite) 1 set 36,000.00
2 Tower Light Side Light (Avialite) 3 set 18,000.00
3 ECB 20A-2P NEMA 3R ENC 1 set 2,750.00
4 Photocell 1 set 2,050.00
5 C.O. "WP" Type 2 set 1,375.00
6 Utility Box 4" x 2" McGil 2 set 1,045.00
7 IMC Pipe 20mmØ x 10' w/ coupling 32 pcs 572.00
8 IMC Elbow 20mmØ 6 pcs 78.00
9 IMC Coupling 20mmØ 12 pcs 28.00
10 Locknut and Bushing 20mmØ 4 pcs 40.00
11 Conduet LB 20mmØ "-WP" 2 pcs 1,650.00
12 Conduet Tee 20mmØ 2 pcs 1,650.00
13 Junction Box 20mmØ k.o. 2 pcs 1,925.00
14 Reducer 1"Ø to 3/4"Ø 4 pcs 385.00
15 IMC Pipe 1"Ø x 10' 1 pcs 750.00
16 U-Bolts for 1"Ø Pipe 3 pcs 20.00
17 U-Bolts for 3/4"Ø Pipe 95 pcs 17.00
18 Wire 5.5mm2 THHN (blk/red) 200 units 42.00
19 wire 3.5mm2 THHN (green) 100 units 39.00
20 Tie Wire Ga #16 2 kg 135.00
21 Electrical Tape 2 pcs 66.00
Sub Total A

B. LABOR
NO. DESCRIPTION QTY DAYS RATE/DAY

1 Supervisor-Electrical 1 11 750.00

2 Elecrtician 2 11 554.75

8 Helper 4 10 475.00

Sub Total B
C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS

DESCRIPTION: Lightning Protection System QUANTITY :


ITEM NO:
(LPS-conventional type) see separate sheet UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 Lightning Rod M25 x 3.0M Solid Copper/Stainl 1 pc 13,390.00
2 S. Connection TOW MCN 3 pc 1,950.00
3 Mounting (Pipe) Bracket 1 set 1,650.00
4 Lightning Strike Recorder 1 set 24,200.00
5 Bus Bar 350 x 75 x 6.0mm 1 pc 10,450.00
6 Bus Bar Insulator 5KV 8 pcs 396.00
7 Flat Bar 85 pcs 24.00
8 Terminal Lug 100mm 2
6 pcs 385.00
9 U-Bolts 1/2"Ø 6 pcs 15.00
10 BNW 3/8"Ø x 1" s/s 110 prs 20.00
11 Down Conduction 100mm (L.A. to T.P.T)
2
95 mts 891.00
12 Down Conduction 100mm2 (B.B. to T.P.T) 85 mts 891.00
Sub Total A
B. LABOR
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Supervisor-Electrical 1 15 750.00
2 Elecrtician 2 15 554.75
3 Helper 4 15 475.00
3

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Meger Tester, etc 1 18 510.60
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS
QUANTITY :
ITEM NO: DESCRIPTION: Grounding System
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 Ground Rod 1"Ø x 10' cc 8 pcs 2,900.00
2 S. Connector 1000 MCW 8 pcs 1,950.00
3 Caldweld Powder #150 12 tubes 902.00
4 T. Lugs for 100mm BCW
2
4 pcs 385.00
5 Ring Ground Wire 100mm BCW2
75 mts 685.00
6 Test Pit w/ Galvanized Cover 1 set 4,450.00
7 BNW 1/2"Ø x 2" s/s 4 prs 25.00
Sub Total A

B. LABOR
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Supervisor-Electrical 1 18 750.00
2 Elecrtician 2 18 554.75
3 Helper 3 15 475.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Meger Tester, etc 1 20 583.35
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


NALYSIS

185,479.50

lot

SIS
1.00

lot

AMOUNT

36,000.00
54,000.00
2,750.00
2,050.00
2,750.00
2,090.00
18,304.00
468.00
336.00
160.00
3,300.00
3,300.00
3,850.00
1,540.00
750.00
60.00
1,615.00
8,400.00
3,900.00
270.00
132.00
146,025.00

AMOUNT

8,250.00

12,204.50

19,000.00

39,454.50
AMOUNT
-
-
-

185,479.50

146,025.00
39,454.50
185,479.50

NALYSIS
291,311.30
lot
SIS
1.00
lot

AMOUNT

13,390.00
5,850.00
1,650.00
24,200.00
10,450.00
3,168.00
2,040.00
2,310.00
90.00
2,200.00
84,645.00
75,735.00
225,728.00
AMOUNT
11,250.00
16,642.50
28,500.00
56,392.50

AMOUNT
9,190.80
9,190.80

291,311.30

225,728.00
65,583.30
291,311.30

NALYSIS
173602.00
lot
SIS
1.00
lot

AMOUNT

23,200.00
15,600.00
10,824.00
1,540.00
51,375.00
4,450.00
100.00
107,089.00 15 -

AMOUNT
13,500.00
19,971.00
21,375.00

54,846.00

AMOUNT
11,667.00
11,667.00

173,602.00

107,089.00
66,513.00
173,602.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: Shipment/Delivery of Materials to site
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1
2
Sub Total A

B. LABOR Loading at San Mateo Plant


NO. DESCRIPTION QTY DAYS RATE/DAY

1 Supervisor 1 5 750.00

2 Checker 4 5 600.00

3 Helper 10 5 550.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Porklift 1 5 2,800.00
2 Crane 2 5 25,000.00
3 Truck 2 lot 569,160.00
4 Airfreight Expenses 1 lot 150,000.00
5 Fuel, Oil, Maintenance (24.5%)
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


DETAILED UNIT PRICE ANALYSIS
PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS

DESCRIPTION: Dimensional Check of existing Tower Foundation QUANTITY :


ITEM NO:
and restortion of effeced area UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
Restoration
1 Cement 162.5 bags 250.00
2 Sand 7 cu.m 1,100.00
3 Grvel 15 cu.m 1,100.00
4 Plywood 5.00 pcs 650.00
5 Form Lumber 175.77 bdft 25.00
6 Hardware Materials 1.00 lot 5,000.00
Sub Total A

B. LABOR
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Foreman 1 10 750.00
2 Helper, excavator 10 10 554.75

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
1 Demolition Hammer 1 7 2,500.00
2 Waterpump/Submersible 1 7 650.00
3 Truck 1 10 2,500.00
4 Backhoe 1 2 2,500.00
5 Fuel, Oil & Maintenance 1 lot 15,333.75

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


ETAILED UNIT PRICE ANALYSIS

1,697,000.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

-
-
-

AMOUNT

3,750.00

12,000.00

27,500.00

43,250.00

AMOUNT
14,000.00
250,000.00
1,138,320.00
150,000.00
101,430.00
1,653,750.00

1,697,000.00

-
1,697,000.00
1,697,000.00
ETAILED UNIT PRICE ANALYSIS
207,828.00
lot
UNIT PRICE ANALYSIS
1.00
lot

AMOUNT

-
40,625.00
7,700.00
16,500.00
3,250.00
4,394.25
5,000.00
77,469.25

AMOUNT
7,500.00
55,475.00

62,975.00

AMOUNT
17,500.00
4,550.00
25,000.00
5,000.00
15,333.75
-
67,383.75

207,828.00

77,469.25
130,358.75
207,828.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: BUILDING PERMIT
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1
2
Sub Total A

B. LABOR
NO. DESCRIPTION QTY UON UNIT COST

1 Social Acceptability Documents 1 lot 10,000.00

2 Barangay Clearance / Permits 1 lot 10,000.00

Government Clearance /Permits

1 Zoning Certificate 1 lot 15,000.00

2 Location Clearance 1 lot 45,000.00

3 Building Permit 1 lot 110,000.00

4 Electrical Permit 1 lot 10,000.00

5 Contractor's Tax 1 lot 30,000.00

Post-Con Permits

1 Certificate of Electrical Inspection 1 lot 10,000.00

2 Fire Safety Inspection Certificate 1 lot 10,000.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


ETAILED UNIT PRICE ANALYSIS

250,000.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

-
-
-

AMOUNT

10,000.00

10,000.00

15,000.00

45,000.00

110,000.00

10,000.00

30,000.00

10,000.00

10,000.00

250,000.00

AMOUNT
250,000.00

-
250,000.00
250,000.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS

DESCRIPTION: Temporary Facilities & utilities (Bunkhouse, site QUANTITY :


ITEM NO:
office, site warehouse) UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
Site Warehouse/Stockyard
1 GI Sheet 10 pcs 450.00
2 Pywood 8 pcs 675.00
3 Form lumber 500 bdft 35.00
4 Hardware 1 lot 2,500.00

Sub Total A

B. LABOR
NO. DESCRIPTION QTY duration rate/month

1 House Rental 2 6 mos 6,000.00

Constructon of Warehouse/stockyard

2 Labor 6 7 550.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna


Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS

DESCRIPTION: Temporary Facilities & utilities QUANTITY :


ITEM NO:
(Consumption of Electricity & water) UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 cable wires 50mm2 229.561333 m 450.00
2 industrial connector 24 sets 2,100.00
3 panel board 3 sets 72,000.00

Sub Total A

B. LABOR
NO. DESCRIPTION QTY duration rate/month
1 Power Consumption 1 6 mos 23,000.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna


Position /Designation: President
ETAILED UNIT PRICE ANALYSIS

125,000.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

-
4,500.00
5,400.00
17,500.00
2,500.00
-
29,900.00

AMOUNT

72,000.00

23,100.00

95,100.00

AMOUNT

125,000.00

-
125,000.00
125,000.00
ETAILED UNIT PRICE ANALYSIS
507,702.60
lot

UNIT PRICE ANALYSIS


1.00
lot

AMOUNT

103,302.60
50,400.00
216,000.00
-
369,702.60

AMOUNT
138,000.00

138,000.00

AMOUNT

507,702.60

369,702.60
138,000.00
507,702.60
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: PROVISION OF SAFETY
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 Pipe 2-1/2"Ø x 6.0m S-40 30 pcs 2,350.00
2 Pipe 2"Ø x 6.0m S-20 159 pcs 1,375.00
3 Ordinary Plywood,1/4" thk 75 pcs 395.00
4 Ordinary Plywood, 3/4" thk 27 pcs 490.00
5 Wire Mesh (2"mesh x 2.8mmØ) 75 pcs 1,750.00
6 Swivel (360º) 65 pcs 60.00
7 Swivel (Fixed) 55 pcs 55.00
8 Safety Net - Black 4 rolls 6,890.00
9 Safety Net - Green 15 rolls 2,275.00
10 Deformed Bar (12mmØ x 6.0m) 25 pcs 175.00
11 G.I. Tie Wire #16 5 rolls 2,250.00
12 Welding Rod (6011 / 7018) 10 box 2,431.00
13 Nylon Rope (3/4"Ø) 3 rolls 5,760.00
14 Nylon Rope (5/8"Ø) 4 rolls 4,688.75
Sub Total A

B. LABOR
NO. DESCRIPTION QTY DUR. (days) RATE /DAY

1 Labor 20 35 500.00

Sub Total B

C. EQUIPMENT
NO. DESCRIPTION QTY DAYS RATE/DAY

Sub Total C
D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


TAILED UNIT PRICE ANALYSIS

957,810.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

70,500.00
218,625.00
29,625.00
13,230.00
131,250.00
3,900.00
3,025.00
27,560.00
34,125.00
4,375.00
11,250.00
24,310.00
17,280.00
18,755.00
607,810.00

AMOUNT

350,000.00

350,000.00

AMOUNT
957,810.00

607,810.00
350,000.00
957,810.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: Survey & Gathering Data
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 A3 size bond paper 1 lot 9,250.00
Sub Total A

B. LABOR
NO. DESCRIPTION QTY DUR. (days) RATE /DAY

1 Technical Supervisor 1 7 700.00

2 Draftsman 1 7 600.00

3 Rigger 2 7 550.00

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY DAYS RATE/DAY
1 BOARD & LODGING 1 7 1,200.00
2 TRANSPORTATION EXPENSES 1 7 650.00
3 AIR FARE 4 2 4,500.00
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS
QUANTITY :
ITEM NO: DESCRIPTION: Design
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
1 A4 size bond paper 1 lot 1,500.00

Sub Total A

B. LABOR
NO. DESCRIPTION QTY UOM UNIT COST
1 Structural Engineer Prof Serice Fee 1 lot 333,600.00
2 Draftsman 1 5 600.00

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY DAYS RATE/DAY

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS
QUANTITY :
ITEM NO: DESCRIPTION: ASBUIT DRAWING
ITEM NO: DESCRIPTION: ASBUIT DRAWING
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION

Sub Total A

B. LABOR
NO. DESCRIPTION QTY UOM UNIT COST
1 Technical Supervisor 1 15 750.00
2 Detailer 1 15 650.00

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY UOM UNIT COST
1 Airfare to Dvao vice versa 2 2 5000
2 Blue printing 80 Shts 50.00

Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS
QUANTITY :
ITEM NO: DESCRIPTION: Material Testing
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
QTY UOM UNIT PRICE
NO. DESCRIPTION

Sub Total A

B. LABOR
NO. DESCRIPTION QTY UOM UNIT COST
1 WELDING TEST (NDT)-3rd party 3 sets 41,000.00
2 TENSILE TEST 3 sample 401.00
3 COMPRESSION TEST 3 sample 333.00

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY dur RATE/DAY
1 Airfare to Dvao vice versa 2 2 5,000.00
2 Board and Lodging 2 2 1,200.00
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President

DETAILED UNIT PRICE ANALYSIS


PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :
LOCATION: Matina Shrine, Matina , Davao City UNIT :
UNIT PRICE ANALYSIS
QUANTITY :
ITEM NO: DESCRIPTION: Soil Testing
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION
Sub Total A

B. LABOR
NO. DESCRIPTION QTY UOM UNIT COST
1 SOIL TEST-3rd party 1 set 153,600.00

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY dur RATE/DAY
1 Airfare to Davao vice versa 1 2 4,500.00
2 Board and Lodging 1 2 1,200.00
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


TAILED UNIT PRICE ANALYSIS

75,000.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

9,250.00
9,250.00

AMOUNT

4,900.00

4,200.00

7,700.00

16,800.00

AMOUNT
8,400.00
4,550.00
36,000.00
48,950.00

75,000.00

9,250.00
65,750.00
75,000.00

TAILED UNIT PRICE ANALYSIS


338,100.00
lot
UNIT PRICE ANALYSIS
1.00
lot

AMOUNT

1,500.00

1,500.00

AMOUNT
333,600.00
3,000.00
-
336,600.00

AMOUNT

338,100.00

1,500.00
336,600.00
338,100.00

TAILED UNIT PRICE ANALYSIS


45,000.00
lot
UNIT PRICE ANALYSIS
1.00
lot

AMOUNT

AMOUNT
11,250.00
9,750.00
-
21,000.00

AMOUNT
20,000.00
4,000.00

24,000.00

45,000.00

-
45,000.00
45,000.00

TAILED UNIT PRICE ANALYSIS


150,002.00
lot
UNIT PRICE ANALYSIS
1.00
lot

AMOUNT
AMOUNT

AMOUNT
123,000.00
1,203.00
999.00

125,202.00

AMOUNT
20,000.00
4,800.00
24,800.00

150,002.00

-
150,002.00
150,002.00

TAILED UNIT PRICE ANALYSIS


165,000.00
lot
UNIT PRICE ANALYSIS
1.00
lot

AMOUNT

-
-

AMOUNT
153,600.00
-

153,600.00

AMOUNT
9,000.00
2,400.00
11,400.00

165,000.00

-
165,000.00
165,000.00
DETAILED UNIT PRICE ANALYSIS

PROJECT: RETROFITTING OF 250FT- DAVAO TOWER Unit Cost :

LOCATION: Matina Shrine, Matina , Davao City UNIT :

UNIT PRICE ANALYSIS


QUANTITY :
ITEM NO: DESCRIPTION: Mobilization/Demobilizzation
UNIT :
A. MATERIALS
QTY UOM UNIT PRICE
NO. DESCRIPTION

Sub Total A

B. LABOR
NO. DESCRIPTION QTY DUR. (days) RATE /DAY

Sub Total B

C. OTHER EXPENSES
NO. DESCRIPTION QTY DAYS RATE/DAY
1 BOARD & LODGING 1 3 1,200.00
2 TRANSPORTATION EXPENSES 1 3 800.00
3 AIR FARE 18 2 6,500.00
Sub Total C

D. TOTAL DIRECT COST (A + B + C)

MATERIAL UNIT COST


LABOR (Labor & Equipment) UNIT COST
TOTAL UNIT COST

Name of Bidder's Authorized Representative: Remegio B. Villaluna

Position /Designation: President


TAILED UNIT PRICE ANALYSIS

240,000.00

lot

UNIT PRICE ANALYSIS


1.00

lot

AMOUNT

-
-

AMOUNT

AMOUNT
3,600.00
2,400.00
234,000.00
240,000.00

240,000.00

-
240,000.00
240,000.00

Potrebbero piacerti anche