CRONOGRAMA DE AVANCE DE OBRAS PROGRAMADO

PROYECTO: “AMPLIACION DE LA TROCHA CARROZABLE SECTOR DE HUANQUEPAMPA AL SECTOR CRUZPAMPA DEL DISTRITO DE AMASHCA, PROVINCIA DE CARHUAZ - ANCASH”
UBICACIÓN: AMASHCA - CARHUAZ - ANCASH

Precio MES 01 MES 02


Item Descripción Und. Metrado Parcial (S/.)
(S/.) COSTO (S/.) % COSTO (S/.) %
1 OBRAS PROVISIONALES 8,289.26 S/. 8,289.26 100.00% S/. 0.00 0.00%
1.01 CAMPAMENTO Y OFICINA PROVISIONAL DE LA OBRA m2 50.00 55.72 2,786.00 S/. 2,786.00 100.00% S/. 0.00 0.00%
1.02 CARTEL DE IDENTIFICACION DE LA OBRA und 1.00 503.26 503.26 S/. 503.26 100.00% S/. 0.00 0.00%
1.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 5,000.00 5,000.00 S/. 5,000.00 100.00% S/. 0.00 0.00%
2 TRABAJOS PRELIMINARES 8,310.83 6,137.60 73.85% S/. 2,173.22 26.15%
2.01 LIMPIEZA DEL TERRENO MANUAL m2 11,448.36 0.49 5,609.70 S/. 4,487.76 80.00% S/. 1,121.94 20.00%
2.02 TRAZO Y REPLANTEO PRELIMINAR km 2.86 348.81 997.60 S/. 798.08 80.00% S/. 199.52 20.00%
2.03 TRAZO, NIVELACION Y REPLANTEO (DURANTE EL PROCESO) km 2.86 595.64 1,703.53 S/. 851.77 50.00% S/. 851.77 50.00%
3 SEGURIDAD Y SALUD 2,395.00 S/. 2,395.00 100.00% S/. 0.00 0.00%
3.01 EQUIPOS DE PROTECCION INDIVIDUAL und 1.00 2,395.00 2,395.00 S/. 2,395.00 100.00% S/. 0.00 0.00%
4 MOVIMIENTO DE TIERRAS 100,035.23 50,017.61 50.00% 50,017.61 50.00%
4.01 CORTE DE MATERIAL SUELTO CON EQUIPO m3 13,585.52 4.63 62,900.96 S/. 31,450.48 50.00% S/. 31,450.48 50.00%
4.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1,465.20 12.53 18,358.96 S/. 9,179.48 50.00% S/. 9,179.48 50.00%
4.03 PERFILADO DE SUBRASANTE EN ZONA DE CORTE CON EQUIPO m2 11448.36 1.64 18,775.31 S/. 9,387.66 50.00% S/. 9,387.66 50.00%
5 OBRAS DE ARTE 13,738.03 6,869.02 50.00% S/. 6,869.02 50.00%
5.01 CONFORMACION Y PERFILADO DE CUNETAS 13,738.03 S/. 6,869.02 50.00% S/. 6,869.02 50.00%
05.01.01 CONFORMACION DE CUNETAS m 2,862.09 4.80 13,738.03 S/. 6,869.02 50.00% S/. 6,869.02 50.00%
6 MITIGACION DE IMPACTO AMBIENTAL 2,203.96 S/. 0.00 0.00% S/. 2,203.96 100.00%
6.09 RESTAURACION DE AREAS AFECTADAS POR CAMPAM,ENTOS Y PATIO DE glb 1.00 2,203.96 2,203.96 S/. 0.00 0.00% S/. 2,203.96 100.00%
7 FLETE 1,154.26 S/. 1,154.26 100.00% S/. 0.00 0.00%
7.01 FLETE TERRESTRE glb 1.00 1,154.26 1,154.26 S/. 1,154.26 100.00% S/. 0.00 0.00%
COSTO DIRECTO 136,126.57 74,862.75 54.99% 61,263.81 45.01%
AVANCE DE OBRA PROGRAMADO 74,862.75 54.99% 61,263.81 45.01%
AVANCE DE OBRA PROGRAMADO ACUMULADO 74,862.75 54.99% 136,126.55 100.00%