INSPECTION TEST RECORD (ITR) - A

JACKET PRE-LOADOUT ST08-A


INSPECTION / TEST OK N/A P/L No.
• Confirm load out arrangement with all parties involved.
• Check for positive pressure in the pile sleeves and identify if there are any leaks
(Bulging Diaphragms). If a gauge is accessible, check the gauge reading.
• Review quantities of all ship loose items for the jacket.
• Placement of ship loose items on the barge and is properly secured.
• Go through all dimensional trial-fit, As-Built and NDT reports (paper exercise)
submitted by the FABRICATOR.
• Check for damages during load out process.
• Check the Quick Connect Panel (QCP) position that it does not interface with
rigging arrangement.
• Checks launch rigging and wiring plan as per drawing.
Inspect all rigging arrangements and check if there is any interface with the launch
7
lug during the launching process.
• Check all stoppers at rocker arms. To be cut off after jacket is loaded out onto the
barge.

• Check the location of the Centre of Gravity (COG)to be marked on the jacket leg.

• Check the ESDV Service Platform sharp edges and protruding members are fully
protected from rigging arrangement.
• Check all installation aids for load out operation are removed.
• OIC to mark self jacket launch distance on the skid beam and jacket launch cradle
after completion of sea fastening.
• OIC to check all the rigging aids are properly installed and clear from any
obstruction.
SKIRT PILES
• Check roundness of pile top, middle and end sections.
• Check piles length and diameter.
• Ensure that the marking on Pile Sleeve are clearly marked:
o B1-4 and C1-4
o B1-1a and C1-1a
• Check stoppers-dimensions, details and location.
8 • Paint mark at internal& external wall at top and bottom of
pile 500mm wide with a white high intensity reflective paint on all skirt piles P1 and P2 skirt
sleeve B1-4, C1-4, B1-1a&C1-1a and numbering shall start on all skirt piles P1 skirt sleeve B1-4,
C1-4, B1-1a&C1-1a as Dwg No. TBA
• Grind flush longitudinal seam welds 10ft from top of skirt pile
• Skirt piles white paint mark at interval:
o 0-10m : 1m interval
o 10m onwards: 250mm interval
9 POST LOAD-OUT PILES
• Confirm position and arrangement of all piles as per approved transportation
drawing.
• Ballast for tow conditions (prior/concurrent/after lashing to hold piles

Potrebbero piacerti anche