Sei sulla pagina 1di 39

NO Task Name Duration Start

SIL GEOTHERMAL POWER PLANT ANNUAL INSPECTION 2019


Main STG
Record data vibration & other on DCS room befor shutdown 1 24 May 23:59
Shutdown STG 3 24 May 23:59
Cooling down 3 24 May 23:59
Turning gear 2 25 May 2:59
Disamantle
Remove heat insulation 2 24 May 23:59
Remove turbine man hole (L & R) 2 25 May 4:59
Perform visual and boroscope inspection of last stage blades 4 26 May 8:00
Remove air duct 1 25 May 4:59
Remove exiter cover 1 25 May 5:59
Remove PMG Cover 1 25 May 6:59
Remove Generator end cover 3 25 May 7:59
Electrical Scope of Works on the STG
Generator
Perform generator cleaning and inspection (no rotor removal). 4 25 May 10:59
Inspect/test diodes and diode bridges for cleanliness and condition 3 25 May 14:59
Visual and boroscope inspection of the insulation, fans, wedges for cracks, deterioration or 3 25 May 17:59
Perform stator winding insulation resistance test 3 26 May 9:29
Perform rotor winding insulation resistance test 3 26 May 13:29
Perform exciter field stator winding insulation test 3 26 May 16:29
STG NGR/Surge Arresters
Visually inspect, clean dust or dirt which might have accumulated on the surge arresters, 2 25 May 10:59
Visually inspect for crack, or leakage on insulators or bushings of the neutral grounding resist 2 25 May 10:59
Check continuity of resistive element of neutral grounding resistors 2 25 May 10:59
Record findings and observation and mention in the servicing report 2 25 May 10:59
Re-assembly Generator
Install PMG & Cover end Cover 6 26 May 19:29
Install Exiter 8 26 May 18:00
Install Air Duct 6 26 May 19:29
Turbine & Generator Re-assembly
Close man hole after inspection 2 26 May 12:00
Install heat insulation 2 26 May 14:00
Witness by SIL Electrical Team 2 25 May 15:59
Pre Start Up
Turbine & Generator Oil Flushing 1 27 May 1:29
Turbine & Generator Turning Gear 2 27 May 1:29
Turbine & Generator Walk Down 2 25 May 15:59
Turbine & Generator Warming Up 4 27 May 1:29
Turbine & generator Start Up 2 27 May 5:29
Main Oil Tank
Inspection and servicing of vapor extractor 4 25 May 4:59
Oil Mist Separator
Replace Cartridge 2 25 May 8:59
Replace gasket 1 25 May 10:59
Lube Oil Conditioner
Check deposit inside the coaleacer and record the quantity 3 25 May 11:59
Check the coaleacer cartridge about clogging 2 25 May 14:59
Check oil leakage from the conditioner 1 25 May 16:59
MCV/CV/CV-LLO
Inspection of the hydraulic actuator of the main and control valves. Solenoid blocks needs to b 4 25 May 17:59
Inspection and cleaning of control oil line. 4 25 May 21:59
Inspection and cleaning of the servo valve mechanism of the control valves. 4 26 May 1:59
Replace of gland packing. 24 26 May 5:59
Main Strainer Cleaning and Inspection (L & R)
Remove heat insulation strainer (L & R) 3 25 May 2:59
Unbolting Strainer (L & R) 4 25 May 5:59
Remove strainer (L & R) 4 25 May 9:59
Cleaning Strainer (L & R) 24 25 May 13:59
Joint Inspection strainer (L & R) 1 26 May 13:59
Install Strainer (L & R) & Replace Gasket 6 26 May 14:59
Bolting Strainer (L & R) 4 26 May 20:59
Install Heat insulation strainer ( L & R) 2 27 May 0:59
STG Drain Pot
Remove cover bolts 0.5 25 May 8:00
Cleaning drain pot 2 25 May 8:30
Reinstall drain pot 0.5 25 May 10:30
Steam Purifier
Install skillet 1 25 May 8:00
Remove man hole 1 25 May 8:00
Blowing & Gas Test 12 25 May 9:00
Install scaffolding inside vessel 4 25 May 21:00
Steam Purifier cleaning 6 26 May 1:00
Uninstall scaffolding 2 26 May 7:00
Joint Inspection 1 26 May 7:00
Install Man Hole & Replace Gasket 1.5 26 May 8:00
Tightening Bolts Man Hole 1.5 26 May 9:30
House Keeping
STG, Auxiliaries, BOP 10 26 May 8:00
OEC MECHANICAL CLEANING & INSPECTION
OEC-06
Shutdown & Cooling down 1 25 May 4:00
Drain Vaporizer & Preheaters 4 25 May 4:00
Remove Heat Insulation 1 25 May 8:00
Unbolting Vaporizer OEC 06 4 25 May 8:00
Unbolting Preheater OEC 06 4 25 May 12:00
Hydro Blast Water Jet Cleaning Vaporizer 06 16 25 May 16:00
Hydro Blast Water Jet Cleaning Preheater 06 16 25 May 16:00
Joint Inspection Vaporizer OEC 06 1 26 May 8:00
Joint Inspection Preheat OEC 06 1 26 May 8:00
Install Gasket (GORTEX) Vaporizer 06 1 26 May 8:00
Install Gasket (GORTEX) Preheat 06 1 26 May 8:00
Install Cover & Bolting Vaporizer OEC 06 4 26 May 12:00
Install Cover & Bolting Preheat OEC 06 4 26 May 12:00
Lube Oil Seal Replacement OEC-06
Drain Lube Oil tank 2 25 May 8:00
Clean Exterior & Interion tank 4 25 May 8:00
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 4 25 May 11:00
Replace all required filters 5 25 May 16:00
Run the lube oil and seal oil system and check for leaks. 1 26 May 9:00
OEC 06 Generator H2S Filter Cleaning. 2 26 May 10:00
Remove bolts stariner feed pump 4 Ea 2 25 May 8:00
Cleaning Strainer Feed Pump 4 Ea 2 25 May 8:00
Reinstall strainer feed pump 2 25 May 10:00
OEC-05
Shutdown & Cooling down 1 25 May 4:00
Drain Vaporizer & Preheaters 4 25 May 4:00
Remove Heat Insulation 1 24 May 20:00
Unbolting Vaporizer OEC 05 4 25 May 16:00
Unbolting Preheater OEC 05 4 25 May 20:00
Hydro Blast Water Jet Cleaning Vaporizer 05 16 26 May 9:00
Hydro Blast Water Jet Cleaning Preheater 05 16 26 May 9:00
Joint Inspection Vaporizer OEC 05 1 27 May 1:00
Joint Inspection Preheat OEC 05 1 26 May 9:00
Install Gasket (GORTEX) Vaporizer 05 1 27 May 2:00
Install Gasket (GORTEX) Vaporizer 05 1 27 May 2:00
Install Cover & Bolting Vaporizer OEC 05 4 27 May 3:00
Install Cover & Bolting Preheat OEC 05 4 27 May 3:00
Lube Oil Seal Replacement OEC-05
Drain Lube Oil tank 2 25 May 8:00
Clean Exterior & Interion tank 4 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 4 25 May 15:00
Replace all required filters 6 25 May 19:00
Run the lube oil and seal oil system and check for leaks. 1 26 May 10:00
OEC 05 Generator H2S Filter Cleaning. 3 26 May 11:00
Remove bolts stariner feed pump 4 Ea 2 25 May 10:00
Cleaning Strainer Feed Pump 4 Ea 2 25 May 13:00
Reinstall Strainer feed pump 2 25 May 15:00
OEC-34
Lube Oil Seal Replacement OEC-34
Drain Lube Oil tank 2 25 May 8:00
Clean Exterior & Interion tank 4 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 4 25 May 14:00
Replace all required filters 4 25 May 18:00
Run the lube oil and seal oil system and check for leaks. 1 26 May 10:30
Generator Air Cooler Filter Cleaning OEC 34 10 25 May 8:00
Remove bolts stariner feed pump 2 Ea 2 26 May 11:30
Cleaning Strainer Feed Pump 2 Ea 2 26 May 14:30
Alignment OEC-34 (CCW)
Final Alignment 12 25 May 8:00
OEC-33
Lube Oil Seal Replacement OEC-33
Drain Lube Oil tank 2 25 May 8:00
Clean Exterior & Interion tank 4 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 4 25 May 14:00
Replace all required filters 5 25 May 18:00
Run the lube oil and seal oil system and check for leaks. 1 26 May 9:00
Generator Air Cooler Filter Cleaning OEC 33 10 25 May 18:00
Remove bolts stariner feed pump 2 Ea 2 26 May 16:30
Cleaning Strainer Feed Pump 2 Ea 3 26 May 18:30
Replace Make Seal Feed Pump OEC-34 - CW
Disconnect Motor Power (Coord to SIL for remove heater power) 0.5 25 May 5:00
Riding Alignment 1 25 May 8:00
Remove Motor Pump 1 25 May 9:00
Disassembly 2 25 May 10:00
Repalce make seal new one 2 25 May 13:00
Reassembly 2 25 May 15:00
Install Motor pump 2 25 May 17:00
Alignment motor to pump 4 25 May 19:00
Reconnect power cable (coordinasi with SIL to remove heater) 1 26 May 11:30
Replace Make Seal Feed Pump OEC-34 - CCW
Disconnect Motor Power (Coord to SIL for remove heater power) 0.5 25 May 5:00
Riding Alignment 1 25 May 8:00
Remove Motor Pump 1 25 May 10:00
Disassembly 2 25 May 11:00
Repalce make seal new one 2 25 May 14:00
Reassembly 2 25 May 16:00
Install Motor pump 2 25 May 19:00
Alignment motor to pump 4 26 May 9:30
Reconnect power cable (coordinasi with SIL to remove heater) 1 26 May 14:30
OEC-31
Lube Oil Seal Replacement OEC-31
Drain Lube Oil tank 2 25 May 6:59
Clean Exterior & Interion tank 4 25 May 8:59
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 5 25 May 11:59
Replace all required filters 4 25 May 16:59
Run the lube oil and seal oil system and check for leaks. 1 25 May 20:59
Generator Air Cooler Filter Cleaning OEC 31 10 26 May 4:00
Remove bolts stariner feed pump 2 Ea 2 27 May 9:00
Cleaning Strainer Feed Pump 2 Ea 3 27 May 11:00
OEC-32
Lube Oil Seal Replacement OEC-32
Drain Lube Oil tank 2 25 May 21:59
Clean Exterior & Interion tank 4 25 May 23:59
Refill new oil using portable filtration machine. Filtration machine is in contractor’s scope 8 26 May 2:59
Replace all required filters 4 26 May 12:00
Run the lube oil and seal oil system and check for leaks. 1 26 May 16:00
Generator Air Cooler Filter Cleaning OEC 32 10 26 May 14:00
Remove bolts stariner feed pump 2 Ea 2 27 May 14:00
Cleaning Strainer Feed Pump 2 Ea 2 27 May 16:00
OEC ELECTRICAL TEST & INSPECTION
Test of Generator OEC-06
Taking of insulation resistance of stator, exciter 1 25 May 8:00
Dismantle cover 1 25 May 9:00
Inspection and testing of diodes 1.5 25 May 10:00
Boroscopic Inspection. 1 25 May 11:30
Rotor DC winding resistance and insulation resistance check. 1.5 25 May 13:30
Inspection, servicing and testing of synchronizing breakers 1 25 May 15:00
Test of Generator OEC-05
Taking of insulation resistance of stator, exciter 1 25 May 8:00
Dismantle cover 1 25 May 9:00
Inspection and testing of diodes 1.5 25 May 10:00
Boroscopic Inspection. 1 25 May 11:30
Rotor DC winding resistance and insulation resistance check. 1.5 25 May 13:30
Inspection, servicing and testing of synchronizing breakers 1 25 May 15:00
Test of Generator OEC 34
Taking of insulation resistance of stator, exciter 1 25 May 16:00
Dismantle cover 1 25 May 17:00
Inspection and testing of diodes 1.5 25 May 18:00
Boroscopic Inspection. 1 26 May 8:00
Rotor DC winding resistance and insulation resistance check. 1.5 26 May 9:00
Inspection, servicing and testing of synchronizing breakers 1 26 May 10:30
Test of Generator OEC 33
Taking of insulation resistance of stator, exciter 1 25 May 16:00
Dismantle cover 1 25 May 17:00
Inspection and testing of diodes 1.5 25 May 18:00
Boroscopic Inspection. 1 26 May 8:00
Rotor DC winding resistance and insulation resistance check. 1.5 26 May 9:00
Inspection, servicing and testing of synchronizing breakers 1 26 May 10:30
Test of Generator OEC 32
Taking of insulation resistance of stator, exciter 1 26 May 11:30
Dismantle cover 1 26 May 13:30
Inspection and testing of diodes 1.5 26 May 14:30
Boroscopic Inspection. 1 26 May 16:00
Rotor DC winding resistance and insulation resistance check. 1.5 26 May 17:00
Inspection, servicing and testing of synchronizing breakers 1 26 May 18:30
Test of Generator OEC 31
Taking of insulation resistance of stator, exciter 1 26 May 11:30
Dismantle cover 1 26 May 13:30
Inspection and testing of diodes 1.5 26 May 14:30
Boroscopic Inspection. 1 26 May 16:00
Rotor DC winding resistance and insulation resistance check. 1.5 26 May 17:00
Inspection, servicing and testing of synchronizing breakers 1 26 May 18:30
OEC GENERATOR ELECTRICAL TEST & INSPECTION
Inspection, cleaning and testing of incoming breakers at OEC power shelter MCC (only 1 for OEC 31, 32, 33 & 34 and 2 for OEC 5 & 6 ea
OEC-06 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 25 May 8:00
OEC -05 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 25 May 14:00
OEC - 33 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 25 May 14:00
OEC - 34 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 25 May 19:00
OEC - 32 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 25 May 19:00
OEC - 31 - Inspection, cleaning and testing of incoming breakers at OEC power shelter ACB & GCB 5 26 May 13:30
Inspection and testing of all Auxiliary Transformer (08 EA).
AT-05 Inspection and testing of all auxiliary transformer 2 MVA - OEC 06 (1 Unit) 10 25 May 8:00
AT-06 Inspection and testing of all auxiliary transformer 2 MVA - OEC 06 (1 Unit) 10 25 May 18:00
AT-07 Inspection and testing of all auxiliary transformer 2 MVA - OEC 05 (1 Unit) 10 26 May 4:00
AT-08 Inspection and testing of all auxiliary transformer 2 MVA - OEC 05 (1 Unit) 10 26 May 14:00
AT-01 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 33 (1 Unit) 10 25 May 8:00
AT-02 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 34 (1 Unit) 10 25 May 18:00
AT-03 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 31 (1 Unit) 10 26 May 4:00
AT-04 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 32 (1 Unit) 10 26 May 14:00
BOP ELECTRICAL
Main Step-Up Transformers (03 EA)
STG Step Up TX-01 - Inspection and testing of Main Step-Up Transformer - 90 MVA (1 Unit) 20 25 May 8:00
ST-02 - Inspection and testing of Main Step-Up Transformer - 35 MVA (1 Unit) 20 25 May 8:00
ST-03 - Inspection and testing of Main Step-Up Transformer - 35 MVA (1 Unit) 20 25 May 8:00
Auxiliary Transformers (02 EA)
AT-11 - Inspection and testing of all auxiliary transformer 2,5 MVA - Wellpad 20 25 May 8:00
AT-09 - Inspection and testing of all auxiliary transformer 2,5 MVA - BOP 20 25 May 8:00
AT-10 - Inspection and testing of all auxiliary transformer 2,5 MVA - BOP 20 25 May 8:00
Inspection, cleaning, servicing and testing of 11KV vacuum breakers (24 Panels)
Panel - MV-01 20 25 May 8:00
Panel - MV-02 20 25 May 8:00
Inspection, testing and calibration of protective relays for Step-up Transformers, STG, HV, MV and LV Switchgears. (23 Units; HV=6ea, MV=4ea, LV=4ea, Transf
Panel - HV 36 25 May 8:00
Panel - MV 36 25 May 8:00
Panel - LV 36 25 May 8:00
Panel - Transformer 36 25 May 8:00
Panel - STG 36 25 May 8:00
150KV Switchyard Inspection (06 EA SF6, 04 EA ES & 12 EA DS)
150kV Switchyard - SF6 Breaker inspection & Maintenance 20 25 May 8:00
150kV Switchyard - Disconnect Switch inspection & maintenance 20 25 May 8:00
150kV Switchyard - Disconnect Switch with Earthing inspection & maintenance 20 25 May 8:00
Steam Field
Electrical Scope of Works :
Inspection, servicing and testing of the grounding systems for Wellpad Area. 32 25 May 8:00
INSTRUMENTATION
HP STM MUFFLER (MU-3902B) INL PV (PIC SIL - AR) 11 25 May 8:00
RE-INJECTION SYSTEM PIC SIL - (PIC SIL - AR) 11 26 May 8:30
STEAM & COOLING WATER (PIC SIL - AR) 11 25 May 19:00
STG LUBE OIL & OIL CONTROL (PIC SIL - AR) 11 26 May 8:30
BRINE OEC (PIC SIL - AR) 20 25 May 8:00
MUFFLERS SYSTEM (PIC SIL - KA) 20 25 May 8:00
BOTTOMING OEC (PIC SIL - KA) 20 25 May 8:00
RE-INJECTION SYSTEM (PIC SIL - KA) 20 25 May 8:00
GATHERING SYSTEM (PIC SIL - KA) 10 25 May 8:00
PLC Calibration (PIC SIL - KA) 20 25 May 8:00
STEAM PURIFIER 20 25 May 8:00
BOTTOMING OEC 20 25 May 8:00
STEAM SCRUBBING SYSTEM 20 25 May 8:00
BOP
Acid Mixing System
Removal of static mixer 4 26 May 8:00
Inspection, sampling and cleaning. Repair damaged portion if found. 4 26 May 12:00
Inspection and cleaning of acid dosing line. 4 26 May 16:00
Reinstall Acid Mixing 4 26 May 20:00
Steam Scrubbing System Orifice & Pipeline Inspection
Removal of pipe spools, 8 25 May 8:00
Inspection and cleaning of orifices 10 25 May 16:00
Removal of scales from spools 10 25 May 16:00
Replacement of gaskets 2 26 May 2:00
Reinstallation of orifices and pipe spools. 12 26 May 4:00
Reinjection line PV-5706C Sizes 12 inch ( Valve stuck
Open the valve and inspection if any minor damage can be repair 3 25 May 8:00
Cleaning the valve seat and disc 5 25 May 11:00
Dye penetrant test on both disc and valve seat 2 25 May 17:00
Contact check between valve seat and disc with prussian blue 2 25 May 19:00
Replace Gaskets 2 26 May 9:30
Re-assemble and install 3 26 May 11:30
STEAM FIELD / WELL PAD
Brine Accumulator - B
Remove heat insulation man hole 0.5 24 May 19:00
Remove man hole 2 25 May 8:00
Blowing & Gas Test 6 25 May 10:00
Inspection and Cleaning of Brine Accumulator Vessels - B 12 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the weld joints. 1 25 May 17:00
Joint Inspection 2 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 26 May 17:30
Separator Vessel B
Remove heat insulation man hole 1 24 May 19:00
Remove man hole 2 25 May 8:00
Blowing & Gas Test 6 25 May 10:00
Inspection and Cleaning of Brine Accumulator Vessels - B 12 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the weld joints. 1 25 May 17:00
Joint Inspection 2 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 26 May 17:30
Brine Accumulator - A
Remove heat insulation man hole 1 25 May 8:00
Remove man hole 2 25 May 10:00
Blowing & Gas Test 4 25 May 13:00
Inspection and Cleaning of Brine Accumulator Vessels - A 12 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the weld joints. 1 25 May 17:00
Joint Inspection 2 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 26 May 18:30
Separator Vessel A
Remove heat insulation man hole 1 25 May 8:00
Remove man hole 2 25 May 13:00
Blowing & Gas Test 4 25 May 15:00
Inspection and Cleaning of Brine Accumulator Vessels - A 18 25 May 19:00
Measurement of wall thickness at 12 points and conduct NDT of the weld joints. 6 25 May 19:00
Joint Inspection 1 27 May 16:00
Replacement of manhole gaskets & Close Man Hole 2 27 May 16:00
Inspection and Cleaning of Brine Strainers - B (2 EA)
Unbolting brine strainer A (2 EA) 3 25 May 8:00
Remove Cover Braine Strainer 2 25 May 11:00
Lift Up Strainer A (2 EA) 1 25 May 11:00
Cleanine Strainer 5 25 May 13:00
Cleaning Internal Strainer 5 25 May 13:00
Install Strainer 2 25 May 18:00
Replace Gasket & Install Strainer Cover 5 26 May 8:30
Inspection and Cleaning of Brine Strainers - A (2 EA)
Unbolting brine strainer A (2 EA) 3 25 May 8:00
Remove Cover Braine Strainer 2 25 May 13:00
Lift Up Strainer A (2 EA) 1 25 May 13:00
Cleanine Strainer 5 25 May 14:00
Cleaning Internal Strainer 5 25 May 19:00
Install Strainer 2 26 May 15:30
Replace Gasket & Install Strainer Cover 5 26 May 17:30
Inspection and Cleaning of Brine Strainers - C (2 EA) @ POWER PLANT
Unbolting brine strainer C (2 EA) 3 25 May 8:00
Remove Cover Braine Strainer 2 25 May 13:00
Lift Up Strainer C (2 EA) 1 25 May 15:00
Cleanine Strainer 5 25 May 16:00
Cleaning Internal Strainer 5 25 May 16:00
Install Strainer 2 26 May 17:30
Replace Gasket & Install Strainer Cover 5 27 May 8:00
Separation System B, Gate Valve T-3157 Sizes 4 inch
Open the valve and inspection if any minor damage can be repair 2 25 May 8:00
Cleaning the valve seat and disc 3 25 May 10:00
Dye penetrant test on both disc and valve seat 1 25 May 14:00
Contact check between valve seat and disc with prussian blue 1 25 May 15:00
Replace Gaskets 2 25 May 16:00
Re-assemble and install 2 25 May 16:00
DUMP VALVE (2 EA) 24" & 12"
Disconnect Power by instrument team 1 25 May 9:00
Remove Valve LV 3111 -24" 4 25 May 11:00
Remove Valve LV3101 - 12" 4 25 May 11:00
Lift Up Valve & Move to laydown area 1 25 May 16:00
Lift Up Valve & Move to laydown area 1 25 May 17:00
Cleaning & Inspection valve 3111 -24" 8 25 May 17:00
Cleaning & Inspection valve LV3101 - 12" 8 25 May 17:00
Reinstall Valve LV 3111 - 24" 4 26 May 14:30
Reinstall Valve LV 3101 - 12" 4 26 May 18:30
Reconnect power cable 2 27 May 11:00

1659.5

S-CURVE
Planning Actual

100

90

80

70

60

50
PROGRESS

40

30

20

10

0
9 9 9 9
-1 -1 -1 -1
ay ay ay ay
-M M -M -M
2 4 2 5- 2 6 2 7

DATE
24-May-19

25-May-19

26-May-19

27-May-19

28-May-19

29-May-19

24-May-19

25-May-19

26-May-19

27-May-19

28-May-19
Finish Weight Progress

25 May 0:59 0.06 100.00 0.06 0.06


25 May 2:59 0.18 100.00 0.18 0.18
25 May 2:59 0.18 100.00 0.18 0.18
25 May 4:59 0.12 100.00 0.12 0.12

25 May 1:59 0.12 100.00 0.12 0.12


25 May 6:59 0.12 0.00 0.12
26 May 12:00 0.24 0.00 0.24
25 May 5:59 0.06 100.00 0.06 0.06
25 May 6:59 0.06 100.00 0.06 0.06
25 May 7:59 0.06 100.00 0.06 0.06
25 May 10:59 0.18 100.00 0.18 0.18

25 May 14:59 0.24 40.00 0.24 0.10


25 May 17:59 0.18 40.00 0.18 0.07
26 May 9:29 0.18 40.00 0.09 0.09 0.07
26 May 13:29 0.18 40.00 0.18 0.07
26 May 16:29 0.18 40.00 0.18 0.07
26 May 19:29 0.18 40.00 0.18 0.07

25 May 13:59 0.12 0.00 0.12


25 May 13:59 0.12 0.00 0.12
25 May 13:59 0.12 0.00 0.12
25 May 13:59 0.12 0.00 0.12

27 May 1:29 0.36 0.00 0.18 0.18


27 May 1:29 0.48 0.00 0.24 0.24
27 May 1:29 0.36 0.00 0.18 0.18

26 May 14:00 0.12 0.00 0.12


26 May 16:00 0.12 0.00 0.12
25 May 17:59 0.12 0.00 0.12

27 May 1:29 0.06 0.00 0.06


27 May 3:29 0.12 0.00 0.12
25 May 17:59 0.12 0.00 0.12
27 May 5:29 0.24 0.00 0.24
27 May 7:29 0.12 0.00 0.12

25 May 8:59 0.24 100.00 0.24 0.24

25 May 10:59 0.12 100.00 0.12 0.12


25 May 11:59 0.06 100.00 0.06 0.06

25 May 14:59 0.18 100.00 0.18 0.18


25 May 16:59 0.12 100.00 0.12 0.12
25 May 17:59 0.06 100.00 0.06 0.06

25 May 21:59 0.24 0.00 0.24


26 May 1:59 0.24 0.00 0.12 0.12
26 May 5:59 0.24 0.00 0.24
27 May 5:59 1.45 0.00 0.72 0.72

25 May 5:59 0.18 100.00 0.18 0.18


25 May 9:59 0.24 100.00 0.24 0.24
25 May 13:59 0.24 100.00 0.24 0.24
26 May 13:59 1.45 100.00 0.72 0.72 1.45
26 May 14:59 0.06 0.00 0.06
26 May 20:59 0.36 0.00 0.36
27 May 0:59 0.24 0.00 0.12 0.12
27 May 2:59 0.12 0.00 0.12

25 May 8:30 0.03 0.00 0.03


25 May 10:30 0.12 0.00 0.12
25 May 11:00 0.03 0.00 0.03

25 May 8:00 0.06 100.00 0.06 0.06


25 May 9:00 0.06 100.00 0.06 0.06
25 May 21:00 0.72 100.00 0.72 0.72
26 May 1:00 0.24 100.00 0.12 0.12 0.24
26 May 7:00 0.36 100.00 0.36 0.36
26 May 9:00 0.12 100.00 0.12 0.12
26 May 8:00 0.06 100.00 0.06 0.06
26 May 9:30 0.09 100.00 0.09 0.09
26 May 11:00 0.09 100.00 0.09 0.09

26 May 18:00 0.60 0.00 0.60

25 May 4:00 0.06 100.00 0.06 0.06


25 May 8:00 0.24 100.00 0.24 0.24
25 May 8:00 0.06 100.00 0.06 0.06
25 May 12:00 0.24 100.00 0.24 0.24
25 May 16:00 0.24 100.00 0.24 0.24
26 May 8:00 0.96 50.00 0.48 0.48 0.48
26 May 8:00 0.96 50.00 0.48 0.48 0.48
26 May 9:00 0.06 0.00 0.06
26 May 9:00 0.06 0.00 0.06
26 May 9:00 0.06 0.00 0.06
26 May 9:00 0.06 0.00 0.06
26 May 16:00 0.24 0.00 0.24
26 May 16:00 0.24 0.00 0.24

25 May 10:00 0.12 100.00 0.12 0.12


25 May 12:00 0.24 100.00 0.24 0.24
25 May 16:00 0.24 100.00 0.24 0.24
26 May 9:00 0.30 50.00 0.15 0.15 0.15
26 May 10:00 0.06 100.00 0.06 0.06
26 May 12:00 0.12 100.00 0.12 0.12
25 May 10:00 0.12 0.00 0.12
25 May 10:00 0.12 0.00 0.12
25 May 12:00 0.12 0.00 0.12

25 May 4:00 0.06 100.00 0.06 0.06


25 May 8:00 0.24 100.00 0.24 0.24
24 May 20:00 0.06 100.00 0.06 0.06
25 May 20:00 0.24 50.00 0.24 0.12
26 May 0:00 0.24 100.00 0.12 0.12 0.24
27 May 1:00 0.96 0.00 0.48 0.48
27 May 1:00 0.96 0.00 0.48 0.48
27 May 2:00 0.06 0.00 0.06
26 May 10:00 0.06 0.00 0.06
27 May 3:00 0.06 0.00 0.06
27 May 3:00 0.06 0.00 0.06
27 May 7:00 0.24 0.00 0.24
27 May 7:00 0.24 0.00 0.24

25 May 10:00 0.12 100.00 0.12 0.12


25 May 15:00 0.24 100.00 0.24 0.24
25 May 19:00 0.24 100.00 0.24 0.24
26 May 10:00 0.36 100.00 0.18 0.18 0.36
26 May 11:00 0.06 100.00 0.06 0.06
26 May 14:00 0.18 100.00 0.18 0.18
25 May 12:00 0.12 0.00 0.12
25 May 15:00 0.12 0.00 0.12
25 May 17:00 0.12 0.00 0.12

25 May 10:00 0.12 100.00 0.12 0.12


25 May 15:00 0.24 100.00 0.24 0.24
25 May 18:00 0.24 100.00 0.24 0.24
26 May 10:30 0.24 100.00 0.12 0.12 0.24
26 May 11:30 0.06 100.00 0.06 0.06
25 May 18:00 0.60 75.00 0.60 0.45
26 May 14:30 0.12 0.00 0.12
26 May 16:30 0.12 0.00 0.12

25 May 20:00 0.72 20.00 0.72 0.14

25 May 10:00 0.12 0.00 0.12


25 May 15:00 0.24 0.00 0.24
25 May 18:00 0.24 0.00 0.24
26 May 9:00 0.30 0.00 0.15 0.15
26 May 10:00 0.06 0.00 0.06
26 May 4:00 0.60 0.00 0.30 0.30
26 May 18:30 0.12 0.00 0.12
27 May 9:00 0.18 0.00 0.09 0.09

25 May 5:30 0.03 100.00 0.03 0.03


25 May 9:00 0.06 100.00 0.06 0.06
25 May 10:00 0.06 100.00 0.06 0.06
25 May 12:00 0.12 100.00 0.12 0.12
25 May 15:00 0.12 100.00 0.12 0.12
25 May 17:00 0.12 0.00 0.12
25 May 19:00 0.12 0.00 0.12
26 May 11:30 0.24 0.00 0.12 0.12
26 May 13:30 0.06 0.00 0.06

25 May 5:30 0.03 100.00 0.03 0.03


25 May 9:00 0.06 100.00 0.06 0.06
25 May 11:00 0.06 100.00 0.06 0.06
25 May 14:00 0.12 100.00 0.12 0.12
25 May 16:00 0.12 100.00 0.12 0.12
25 May 18:00 0.12 0.00 0.12
26 May 9:30 0.12 0.00 0.06 0.06
26 May 14:30 0.24 0.00 0.24
26 May 15:30 0.06 0.00 0.06

25 May 8:59 0.12 0.00 0.12


25 May 12:59 0.24 0.00 0.24
25 May 16:59 0.30 0.00 0.30
25 May 20:59 0.24 0.00 0.24
25 May 21:59 0.06 0.00 0.06
26 May 14:00 0.60 0.00 0.30
27 May 11:00 0.12 0.00 0.12
27 May 14:00 0.18 0.00 0.18

25 May 23:59 0.12 0.00 0.12


26 May 3:59 0.24 0.00 0.24
26 May 12:00 0.48 0.00 0.48
26 May 16:00 0.24 0.00 0.24
26 May 17:00 0.06 0.00 0.06
27 May 0:00 0.60 0.00 0.30 0.30
27 May 16:00 0.12 0.00 0.12
27 May 18:00 0.12 0.00 0.12

25 May 9:00 0.06 100.00 0.06 0.06


25 May 10:00 0.06 100.00 0.06 0.06
25 May 11:30 0.09 100.00 0.09 0.09
25 May 13:30 0.06 100.00 0.06 0.06
25 May 15:00 0.09 100.00 0.09 0.09
25 May 16:00 0.06 100.00 0.06 0.06

25 May 9:00 0.06 100.00 0.06 0.06


25 May 10:00 0.06 100.00 0.06 0.06
25 May 11:30 0.09 100.00 0.09 0.09
25 May 13:30 0.06 100.00 0.06 0.06
25 May 15:00 0.09 100.00 0.09 0.09
25 May 16:00 0.06 100.00 0.06 0.06

25 May 17:00 0.06 20.00 0.06 0.01


25 May 18:00 0.06 20.00 0.06 0.01
25 May 19:30 0.09 20.00 0.09 0.02
26 May 9:00 0.06 20.00 0.06 0.01
26 May 10:30 0.09 20.00 0.09 0.02
26 May 11:30 0.06 20.00 0.06 0.01

25 May 17:00 0.06 0.00 0.06


25 May 18:00 0.06 0.00 0.06
25 May 19:30 0.09 0.00 0.09
26 May 9:00 0.06 0.00 0.06
26 May 10:30 0.09 0.00 0.09
26 May 11:30 0.06 0.00 0.06

26 May 13:30 0.06 0.00 0.06


26 May 14:30 0.06 0.00 0.06
26 May 16:00 0.09 0.00 0.09
26 May 17:00 0.06 0.00 0.06
26 May 18:30 0.09 0.00 0.09
26 May 19:30 0.06 0.00 0.06

26 May 13:30 0.06 0.00 0.06


26 May 14:30 0.06 0.00 0.06
26 May 16:00 0.09 0.00 0.09
26 May 17:00 0.06 0.00 0.06
26 May 18:30 0.09 0.00 0.09
26 May 19:30 0.06 0.00 0.06
0.00
32, 33 & 34 and 2 for OEC 5 & 6 each)
25 May 14:00 0.30 0.00 0.30
25 May 19:00 0.30 0.00 0.30
25 May 19:00 0.30 0.00 0.30
26 May 13:30 0.30 0.00 0.15 0.15
26 May 13:30 0.30 0.00 0.30
26 May 18:30 0.30 0.00 0.30

25 May 18:00 0.60 49.79 0.60 0.30


26 May 4:00 0.60 49.79 0.30 0.30 0.30
26 May 14:00 0.60 49.79 0.60 0.30
27 May 0:00 0.60 49.79 0.30 0.30 0.30
25 May 18:00 0.60 49.79 0.60 0.30
26 May 4:00 0.60 49.79 0.30 0.30 0.30
26 May 14:00 0.60 49.79 0.60 0.30
27 May 0:00 0.60 49.79 0.30 0.30 0.30
26 May 18:30 1.21 100.00 0.60 0.60 1.21
26 May 18:30 1.21 100.00 0.60 0.60 1.21
26 May 18:30 1.21 100.00 0.60 0.60 1.21

26 May 18:30 1.21 0.00 0.60 0.60


26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60

26 May 18:30 1.21 100.00 0.60 0.60 1.21


26 May 18:30 1.21 100.00 0.60 0.60 1.21
Units; HV=6ea, MV=4ea, LV=4ea, Transformer=6ea, STG=3ea)
26 May 20:00 2.17 100.00 1.08 1.08 2.17
26 May 20:00 2.17 0.00 1.08 1.08
26 May 20:00 2.17 0.00 1.08 1.08
26 May 20:00 2.17 100.00 1.08 1.08 2.17
26 May 20:00 2.17 0.00 1.08 1.08

26 May 18:30 1.21 100.00 0.60 0.60 1.21


26 May 18:30 1.21 100.00 0.60 0.60 1.21
26 May 18:30 1.21 100.00 0.60 0.60 1.21

26 May 16:00 1.93 0.00 0.96 0.96

26 May 8:30 0.66 0.00 0.33 0.33


26 May 19:30 0.66 0.00 0.33 0.33
26 May 19:30 0.66 0.00 0.33 0.33
26 May 19:30 0.66 0.00 0.33 0.33
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60
25 May 19:00 0.60 0.00 0.60
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60
26 May 18:30 1.21 0.00 0.60 0.60

26 May 12:00 0.24 0.00 0.24


26 May 16:00 0.24 0.00 0.24
26 May 20:00 0.24 0.00 0.24
27 May 0:00 0.24 0.00 0.12 0.12

25 May 16:00 0.48 0.00 0.48


26 May 2:00 0.60 0.00 0.30 0.30
26 May 2:00 0.60 0.00 0.30 0.30
26 May 4:00 0.12 0.00 0.12
26 May 16:00 0.72 0.00 0.72

25 May 11:00 0.18 0.00 0.18


25 May 17:00 0.30 0.00 0.30
25 May 19:00 0.12 0.00 0.12
26 May 9:30 0.12 0.00 0.06 0.06
26 May 11:30 0.12 0.00 0.12
26 May 15:30 0.18 0.00 0.18

24 May 19:30 0.03 0.00 0.03


25 May 10:00 0.12 0.00 0.12
25 May 17:00 0.36 0.00 0.36
26 May 18:30 0.72 0.00 0.36 0.36
25 May 17:00 0.06 0.00 0.06
26 May 20:30 0.12 0.00 0.12
26 May 20:30 0.12 0.00 0.12
24 May 19:00 0.06 0.00 0.30
25 May 10:00 0.12 0.00 0.12
25 May 17:00 0.36 0.00 0.36
26 May 18:30 0.72 0.00 0.36 0.36
25 May 17:00 0.06 0.00 0.06
26 May 20:30 0.12 0.00 0.12
26 May 20:30 0.12 0.00 0.12

25 May 9:00 0.06 0.00 0.06


25 May 12:00 0.12 0.00 0.12
25 May 17:00 0.24 0.00 0.24
26 May 18:30 0.72 0.00 0.36 0.36
25 May 17:00 0.06 0.00 0.06
27 May 9:00 0.12 0.00 0.06 0.06
27 May 9:00 0.12 0.00 0.06 0.06

25 May 8:00 0.06 0.00 0.06


25 May 15:00 0.12 0.00 0.12
25 May 19:00 0.24 0.00 0.24
27 May 16:00 1.08 0.00 0.36 0.36 0.36
26 May 14:30 0.36 0.00 0.18 0.18
27 May 17:00 0.06 0.00 0.06
27 May 18:00 0.12 0.00 0.12

25 May 11:00 0.18 0.00 0.18


25 May 14:00 0.12 0.00 0.12
25 May 12:00 0.06 0.00 0.06
25 May 18:00 0.30 0.00 0.30
25 May 18:00 0.30 0.00 0.30
26 May 8:30 0.12 0.00 0.06 0.06
26 May 14:30 0.30 0.00 0.30

25 May 11:00 0.18 0.00 0.18


25 May 15:00 0.12 0.00 0.12
25 May 14:00 0.06 0.00 0.06
25 May 19:00 0.30 0.00 0.30
26 May 13:30 0.30 0.00 0.15 0.15
26 May 17:30 0.12 0.00 0.12
27 May 11:00 0.30 0.00 0.15 0.15

25 May 11:00 0.18 0.00 0.18


25 May 15:00 0.12 0.00 0.12
25 May 16:00 0.06 0.00 0.06
26 May 9:30 0.30 0.00 0.15 0.15
26 May 9:30 0.30 0.00 0.15 0.15
26 May 19:30 0.12 0.00 0.12
27 May 14:00 0.30 0.00 0.30

25 May 10:00 0.12 0.00 0.12


25 May 14:00 0.18 0.00 0.18
25 May 15:00 0.06 0.00 0.06
25 May 16:00 0.06 0.00 0.06
25 May 18:00 0.12 0.00 0.12
25 May 18:00 0.12 0.00 0.12

25 May 10:00 0.06 0.00 0.06


25 May 16:00 0.24 0.00 0.24
25 May 16:00 0.24 0.00 0.24
25 May 17:00 0.06 0.00 0.06
25 May 18:00 0.06 0.00 0.06
26 May 14:30 0.48 0.00 0.24 0.24
26 May 14:30 0.48 0.00 0.24 0.24
26 May 18:30 0.24 0.00 0.24
27 May 11:00 0.24 0.00 0.12 0.12
27 May 14:00 0.12 0.00 0.12

100.00 30.44 1.05 49.44 42.99 6.45 0.72 29.72 0.00 0.00

1 50 93 100 0.72 30.44

9
-1
ay
-M
2 7
29-May-19
Task Name Duration Start
SIL GEOTHERMAL POWER PLANT ANNUAL INSPECTION 2019 71 hrs 24 May 19:00
Main STG 55,5 hrs 24 May 23:59
Record data vibration & other on DCS room befor shutdown 1 hr 24 May 23:59
Shutdown STG 3 hrs 24 May 23:59
Cooling down 3 hrs 24 May 23:59
Turning gear 2 hrs 25 May 2:59
Disamantle 36,02 hrs 24 May 23:59
Remove heat insulation 2 hrs 24 May 23:59
Remove turbine man hole (L & R) 2 hrs 25 May 4:59
Perform visual and boroscope inspection of last stage blades 4 hrs 26 May 8:00
Remove air duct 1 hr 25 May 4:59
Remove exiter cover 1 hr 25 May 5:59
Remove PMG Cover 1 hr 25 May 6:59
Remove Generator end cover 3 hrs 25 May 7:59
Electrical Scope of Works on the STG 38,5 hrs 25 May 10:59
Generator 32,5 hrs 25 May 10:59
Perform generator cleaning and inspection (no rotor removal). 4 hrs 25 May 10:59
Inspect/test diodes and diode bridges for cleanliness and condition 3 hrs 25 May 14:59
Visual and boroscope inspection of the insulation, fans, wedges fo 3 hrs 25 May 17:59
Perform stator winding insulation resistance test 3 hrs 26 May 9:29
Perform rotor winding insulation resistance test 3 hrs 26 May 13:29
Perform exciter field stator winding insulation test 3 hrs 26 May 16:29
STG NGR/Surge Arresters 3 hrs 25 May 10:59
Visually inspect, clean dust or dirt which might have accumulate 2 hrs 25 May 10:59
Visually inspect for crack, or leakage on insulators or bushings of t 2 hrs 25 May 10:59
Check continuity of resistive element of neutral grounding resistors 2 hrs 25 May 10:59
Record findings and observation and mention in the servicing report 2 hrs 25 May 10:59
Re-assembly Generator 7,48 hrs 26 May 18:00
Install PMG & Cover end Cover 6 hrs 26 May 19:29
Install Exiter 7,48 hrs 26 May 18:00
Install Air Duct 6 hrs 26 May 19:29
Turbine & Generator Re-assembly 24,02 hrs 25 May 15:59
Close man hole after inspection 2 hrs 26 May 12:00
Install heat insulation 2 hrs 26 May 14:00
Witness by SIL Electrical Team 2 hrs 25 May 15:59
Pre Start Up 39,5 hrs 25 May 15:59
Turbine & Generator Oil Flushing 0 hrs 27 May 1:29
Turbine & Generator Turning Gear 2 hrs 27 May 1:29
Turbine & Generator Walk Down 2 hrs 25 May 15:59
Turbine & Generator Warming Up 4 hrs 27 May 1:29
Turbine & generator Start Up 2 hrs 27 May 5:29
Main Oil Tank 4 hrs 25 May 4:59
Inspection and servicing of vapor extractor 4 hrs 25 May 4:59
Oil Mist Separator 3 hrs 25 May 8:59
Replace Cartridge 2 hrs 25 May 8:59
Replace gasket 1 hr 25 May 10:59
Lube Oil Conditioner 6 hrs 25 May 11:59
Check deposit inside the coaleacer and record the quantity 3 hrs 25 May 11:59
Check the coaleacer cartridge about clogging 2 hrs 25 May 14:59
Check oil leakage from the conditioner 1 hr 25 May 16:59
MCV/CV/CV-LLO 36 hrs 25 May 17:59
Inspection of the hydraulic actuator of the main and control valves. 4 hrs 25 May 17:59
Inspection and cleaning of control oil line. 4 hrs 25 May 21:59
Inspection and cleaning of the servo valve mechanism of the control v 4 hrs 26 May 1:59
Replace of gland packing. 24 hrs 26 May 5:59
Main Strainer Cleaning and Inspection (L & R) 48 hrs 25 May 2:59
Remove heat insulation strainer (L & R) 3 hrs 25 May 2:59
Unbolting Strainer (L & R) 4 hrs 25 May 5:59
Remove strainer (L & R) 4 hrs 25 May 9:59
Cleaning Strainer (L & R) 24 hrs 25 May 13:59
Joint Inspection strainer (L & R) 1 hr 26 May 13:59
Install Strainer (L & R) & Replace Gasket 6 hrs 26 May 14:59
Bolting Strainer (L & R) 4 hrs 26 May 20:59
Install Heat insulation strainer ( L & R) 2 hrs 27 May 0:59
STG Drain Pot 3 hrs 25 May 8:00
Remove cover bolts 0,5 hrs 25 May 8:00
Cleaning drain pot 2 hrs 25 May 8:30
Reinstall drain pot 0,5 hrs 25 May 10:30
Steam Purifier 27 hrs 25 May 8:00
Install skillet 0 hrs 25 May 8:00
Remove man hole 1 hr 25 May 8:00
Blowing & Gas Test 12 hrs 25 May 9:00
Install scaffolding inside vessel 4 hrs 25 May 21:00
Steam Purifier cleaning 6 hrs 26 May 1:00
Uninstall scaffolding 2 hrs 26 May 7:00
Joint Inspection 1 hr 26 May 7:00
Install Man Hole & Replace Gasket 1,5 hrs 26 May 8:00
Tightening Bolts Man Hole 1,5 hrs 26 May 9:30
House Keeping 10 hrs 26 May 8:00
STG, Auxiliaries, BOP 10 hrs 26 May 8:00
OEC MECHANICAL CLEANING & INSPECTION 70 hrs 24 May 20:00
OEC-06 36 hrs 25 May 4:00
Shutdown & Cooling down 0 hrs 25 May 4:00
Drain Vaporizer & Preheaters 4 hrs 25 May 4:00
Remove Heat Insulation 0 hrs 25 May 8:00
Unbolting Vaporizer OEC 06 4 hrs 25 May 8:00
Unbolting Preheater OEC 06 4 hrs 25 May 12:00
Hydro Blast Water Jet Cleaning Vaporizer 06 16 hrs 25 May 16:00
Hydro Blast Water Jet Cleaning Preheater 06 16 hrs 25 May 16:00
Joint Inspection Vaporizer OEC 06 1 hr 26 May 8:00
Joint Inspection Preheat OEC 06 1 hr 26 May 8:00
Install Gasket (GORTEX) Vaporizer 06 1 hr 26 May 8:00
Install Gasket (GORTEX) Preheat 06 1 hr 26 May 8:00
Install Cover & Bolting Vaporizer OEC 06 4 hrs 26 May 12:00
Install Cover & Bolting Preheat OEC 06 4 hrs 26 May 12:00
Lube Oil Seal Replacement OEC-06 28 hrs 25 May 8:00
Drain Lube Oil tank 2 hrs 25 May 8:00
Clean Exterior & Interion tank 4 hrs 25 May 8:00
Refill new oil using portable filtration machine. Filtration machine is 4 hrs 25 May 11:00
Replace all required filters 5 hrs 25 May 16:00
Run the lube oil and seal oil system and check for leaks. 1 hr 26 May 9:00
OEC 06 Generator H2S Filter Cleaning. 2 hrs 26 May 10:00
Remove bolts stariner feed pump 4 Ea 2 hrs 25 May 8:00
Cleaning Strainer Feed Pump 4 Ea 2 hrs 25 May 8:00
Reinstall strainer feed pump 2 hrs 25 May 10:00
OEC-05 59 hrs 24 May 20:00
Shutdown & Cooling down 0 hrs 25 May 4:00
Drain Vaporizer & Preheaters 4 hrs 25 May 4:00
Remove Heat Insulation 0 hrs 24 May 20:00
Unbolting Vaporizer OEC 05 4 hrs 25 May 16:00
Unbolting Preheater OEC 05 4 hrs 25 May 20:00
Hydro Blast Water Jet Cleaning Vaporizer 05 16 hrs 26 May 9:00
Hydro Blast Water Jet Cleaning Preheater 05 16 hrs 26 May 9:00
Joint Inspection Vaporizer OEC 05 1 hr 27 May 1:00
Joint Inspection Preheat OEC 05 1 hr 26 May 9:00
Install Gasket (GORTEX) Vaporizer 05 1 hr 27 May 2:00
Install Gasket (GORTEX) Vaporizer 05 1 hr 27 May 2:00
Install Cover & Bolting Vaporizer OEC 05 4 hrs 27 May 3:00
Install Cover & Bolting Preheat OEC 05 4 hrs 27 May 3:00
Lube Oil Seal Replacement OEC-05 30 hrs 25 May 8:00
Drain Lube Oil tank 2 hrs 25 May 8:00
Clean Exterior & Interion tank 4 hrs 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is 4 hrs 25 May 15:00
Replace all required filters 6 hrs 25 May 19:00
Run the lube oil and seal oil system and check for leaks. 1 hr 26 May 10:00
OEC 05 Generator H2S Filter Cleaning. 3 hrs 26 May 11:00
Remove bolts stariner feed pump 4 Ea 2 hrs 25 May 10:00
Cleaning Strainer Feed Pump 4 Ea 2 hrs 25 May 13:00
Reinstall Strainer feed pump 2 hrs 25 May 15:00
OEC-34 32,5 hrs 25 May 8:00
Lube Oil Seal Replacement OEC-34 27,5 hrs 25 May 8:00
Drain Lube Oil tank 2 hrs 25 May 8:00
Clean Exterior & Interion tank 4 hrs 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is 4 hrs 25 May 14:00
Replace all required filters 4 hrs 25 May 18:00
Run the lube oil and seal oil system and check for leaks. 1 hr 26 May 10:30
Generator Air Cooler Filter Cleaning OEC 34 10 hrs 25 May 8:00
Remove bolts stariner feed pump 2 Ea 2 hrs 26 May 11:30
Cleaning Strainer Feed Pump 2 Ea 2 hrs 26 May 14:30
Alignment OEC-34 (CCW) 12 hrs 25 May 8:00
Final Alignment 12 hrs 25 May 8:00
OEC-33 52 hrs 25 May 5:00
Lube Oil Seal Replacement OEC-33 26 hrs 25 May 8:00
Drain Lube Oil tank 2 hrs 25 May 8:00
Clean Exterior & Interion tank 4 hrs 25 May 10:00
Refill new oil using portable filtration machine. Filtration machine is 4 hrs 25 May 14:00
Replace all required filters 5 hrs 25 May 18:00
Run the lube oil and seal oil system and check for leaks. 1 hr 26 May 9:00
Generator Air Cooler Filter Cleaning OEC 33 10 hrs 25 May 18:00
Remove bolts stariner feed pump 2 Ea 2 hrs 26 May 16:30
Cleaning Strainer Feed Pump 2 Ea 3 hrs 26 May 18:30
Replace Make Seal Feed Pump OEC-34 - CW 32,5 hrs 25 May 5:00
Disconnect Motor Power (Coord to SIL for remove heater power) 0,5 hrs 25 May 5:00
Riding Alignment 1 hr 25 May 8:00
Remove Motor Pump 1 hr 25 May 9:00
Disassembly 2 hrs 25 May 10:00
Repalce make seal new one 2 hrs 25 May 13:00
Reassembly 2 hrs 25 May 15:00
Install Motor pump 2 hrs 25 May 17:00
Alignment motor to pump 4 hrs 25 May 19:00
Reconnect power cable (coordinasi with SIL to remove heater) 1 hr 26 May 11:30
Replace Make Seal Feed Pump OEC-34 - CCW 34,5 hrs 25 May 5:00
Disconnect Motor Power (Coord to SIL for remove heater power) 0,5 hrs 25 May 5:00
Riding Alignment 1 hr 25 May 8:00
Remove Motor Pump 1 hr 25 May 10:00
Disassembly 2 hrs 25 May 11:00
Repalce make seal new one 2 hrs 25 May 14:00
Reassembly 2 hrs 25 May 16:00
Install Motor pump 2 hrs 25 May 19:00
Alignment motor to pump 4 hrs 26 May 9:30
Reconnect power cable (coordinasi with SIL to remove heater) 1 hr 26 May 14:30
OEC-31 55,02 hrs 25 May 6:59
Lube Oil Seal Replacement OEC-31 31,02 hrs 25 May 6:59
Drain Lube Oil tank 2 hrs 25 May 6:59
Clean Exterior & Interion tank 4 hrs 25 May 8:59
Refill new oil using portable filtration machine. Filtration machine is 5 hrs 25 May 11:59
Replace all required filters 4 hrs 25 May 16:59
Run the lube oil and seal oil system and check for leaks. 1 hr 25 May 20:59
Generator Air Cooler Filter Cleaning OEC 31 10 hrs 26 May 4:00
Remove bolts stariner feed pump 2 Ea 2 hrs 27 May 9:00
Cleaning Strainer Feed Pump 2 Ea 3 hrs 27 May 11:00
OEC-32 44,02 hrs 25 May 21:59
Lube Oil Seal Replacement OEC-32 26,02 hrs 25 May 21:59
Drain Lube Oil tank 2 hrs 25 May 21:59
Clean Exterior & Interion tank 4 hrs 25 May 23:59
Refill new oil using portable filtration machine. Filtration machine is 8 hrs 26 May 2:59
Replace all required filters 4 hrs 26 May 12:00
Run the lube oil and seal oil system and check for leaks. 1 hr 26 May 16:00
Generator Air Cooler Filter Cleaning OEC 32 10 hrs 26 May 14:00
Remove bolts stariner feed pump 2 Ea 2 hrs 27 May 14:00
Cleaning Strainer Feed Pump 2 Ea 2 hrs 27 May 16:00
OEC ELECTRICAL TEST & INSPECTION 35,5 hrs 25 May 8:00
Test of Generator OEC-06 8 hrs 25 May 8:00
Taking of insulation resistance of stator, exciter 1 hr 25 May 8:00
Dismantle cover 1 hr 25 May 9:00
Inspection and testing of diodes 1,5 hrs 25 May 10:00
Boroscopic Inspection. 1 hr 25 May 11:30
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 25 May 13:30
Inspection, servicing and testing of synchronizing breakers 1 hr 25 May 15:00
Test of Generator OEC-05 8 hrs 25 May 8:00
Taking of insulation resistance of stator, exciter 1 hr 25 May 8:00
Dismantle cover 1 hr 25 May 9:00
Inspection and testing of diodes 1,5 hrs 25 May 10:00
Boroscopic Inspection. 1 hr 25 May 11:30
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 25 May 13:30
Inspection, servicing and testing of synchronizing breakers 1 hr 25 May 15:00
Test of Generator OEC 34 19,5 hrs 25 May 16:00
Taking of insulation resistance of stator, exciter 1 hr 25 May 16:00
Dismantle cover 1 hr 25 May 17:00
Inspection and testing of diodes 1,5 hrs 25 May 18:00
Boroscopic Inspection. 1 hr 26 May 8:00
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 26 May 9:00
Inspection, servicing and testing of synchronizing breakers 1 hr 26 May 10:30
Test of Generator OEC 33 19,5 hrs 25 May 16:00
Taking of insulation resistance of stator, exciter 1 hr 25 May 16:00
Dismantle cover 1 hr 25 May 17:00
Inspection and testing of diodes 1,5 hrs 25 May 18:00
Boroscopic Inspection. 1 hr 26 May 8:00
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 26 May 9:00
Inspection, servicing and testing of synchronizing breakers 1 hr 26 May 10:30
Test of Generator OEC 32 8 hrs 26 May 11:30
Taking of insulation resistance of stator, exciter 1 hr 26 May 11:30
Dismantle cover 1 hr 26 May 13:30
Inspection and testing of diodes 1,5 hrs 26 May 14:30
Boroscopic Inspection. 1 hr 26 May 16:00
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 26 May 17:00
Inspection, servicing and testing of synchronizing breakers 1 hr 26 May 18:30
Test of Generator OEC 31 8 hrs 26 May 11:30
Taking of insulation resistance of stator, exciter 1 hr 26 May 11:30
Dismantle cover 1 hr 26 May 13:30
Inspection and testing of diodes 1,5 hrs 26 May 14:30
Boroscopic Inspection. 1 hr 26 May 16:00
Rotor DC winding resistance and insulation resistance check. 1,5 hrs 26 May 17:00
Inspection, servicing and testing of synchronizing breakers 1 hr 26 May 18:30
OEC GENERATOR ELECTRICAL TEST & INSPECTION 40 hrs 25 May 8:00
Inspection, cleaning and testing of incoming breakers at OEC pow 34,5 hrs 25 May 8:00
OEC-06 - Inspection, cleaning and testing of incoming breakers at O 5 hrs 25 May 8:00
OEC -05 - Inspection, cleaning and testing of incoming breakers at 5 hrs 25 May 14:00
OEC - 33 - Inspection, cleaning and testing of incoming breakers at 5 hrs 25 May 14:00
OEC - 34 - Inspection, cleaning and testing of incoming breakers at 5 hrs 25 May 19:00
OEC - 32 - Inspection, cleaning and testing of incoming breakers at 5 hrs 25 May 19:00
OEC - 31 - Inspection, cleaning and testing of incoming breakers at 5 hrs 26 May 13:30
Inspection and testing of all Auxiliary Transformer (08 EA). 40 hrs 25 May 8:00
AT-05 Inspection and testing of all auxiliary transformer 2 MVA - OEC 0 10 hrs 25 May 8:00
AT-06 Inspection and testing of all auxiliary transformer 2 MVA - OEC 0 10 hrs 25 May 18:00
AT-07 Inspection and testing of all auxiliary transformer 2 MVA - OEC 0 10 hrs 26 May 4:00
AT-08 Inspection and testing of all auxiliary transformer 2 MVA - OEC 0 10 hrs 26 May 14:00
AT-01 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 10 hrs 25 May 8:00
AT-02 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 10 hrs 25 May 18:00
AT-03 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 10 hrs 26 May 4:00
AT-04 Inspection and testing of all auxiliary transformer 1,5 MVA - OEC 10 hrs 26 May 14:00
BOP ELECTRICAL 36 hrs 25 May 8:00
Main Step-Up Transformers (03 EA) 34,5 hrs 25 May 8:00
STG Step Up TX-01 - Inspection and testing of Main Step-Up Transform 20 hrs 25 May 8:00
ST-02 - Inspection and testing of Main Step-Up Transformer - 35 MVA ( 20 hrs 25 May 8:00
ST-03 - Inspection and testing of Main Step-Up Transformer - 35 MVA ( 20 hrs 25 May 8:00
Auxiliary Transformers (02 EA) 34,5 hrs 25 May 8:00
AT-11 - Inspection and testing of all auxiliary transformer 2,5 MVA - W 20 hrs 25 May 8:00
AT-09 - Inspection and testing of all auxiliary transformer 2,5 MVA - B 20 hrs 25 May 8:00
AT-10 - Inspection and testing of all auxiliary transformer 2,5 MVA - B 20 hrs 25 May 8:00
Inspection, cleaning, servicing and testing of 11KV vacuum breakers (2 34,5 hrs 25 May 8:00
Panel - MV-01 20 hrs 25 May 8:00
Panel - MV-02 20 hrs 25 May 8:00
Inspection, testing and calibration of protective relays for Step-up 36 hrs 25 May 8:00
Panel - HV 36 hrs 25 May 8:00
Panel - MV 36 hrs 25 May 8:00
Panel - LV 36 hrs 25 May 8:00
Panel - Transformer 36 hrs 25 May 8:00
Panel - STG 36 hrs 25 May 8:00
150KV Switchyard Inspection (06 EA SF6, 04 EA ES & 12 EA DS) 34,5 hrs 25 May 8:00
150kV Switchyard - SF6 Breaker inspection & Maintenance 20 hrs 25 May 8:00
150kV Switchyard - Disconnect Switch inspection & maintenance 20 hrs 25 May 8:00
150kV Switchyard - Disconnect Switch with Earthing inspection & ma 20 hrs 25 May 8:00
Steam Field 32 hrs 25 May 8:00
Electrical Scope of Works : 32 hrs 25 May 8:00
Inspection, servicing and testing of the grounding systems for Wellpad 32 hrs 25 May 8:00
INSTRUMENTATION 21 hrs 25 May 8:00
HP STM MUFFLER (MU-3902B) INL PV (PIC SIL - AR) 11 hrs 25 May 8:00
RE-INJECTION SYSTEM PIC SIL - (PIC SIL - AR) 11 hrs 26 May 8:30
STEAM & COOLING WATER (PIC SIL - AR) 11 hrs 25 May 19:00
STG LUBE OIL & OIL CONTROL (PIC SIL - AR) 11 hrs 26 May 8:30
BRINE OEC (PIC SIL - AR) 20 hrs 25 May 8:00
MUFFLERS SYSTEM (PIC SIL - KA) 20 hrs 25 May 8:00
BOTTOMING OEC (PIC SIL - KA) 20 hrs 25 May 8:00
RE-INJECTION SYSTEM (PIC SIL - KA) 20 hrs 25 May 8:00
GATHERING SYSTEM (PIC SIL - KA) 10 hrs 25 May 8:00
PLC Calibration (PIC SIL - KA) 20 hrs 25 May 8:00
STEAM PURIFIER 20 hrs 25 May 8:00
BOTTOMING OEC 20 hrs 25 May 8:00
STEAM SCRUBBING SYSTEM 20 hrs 25 May 8:00
BOP 40 hrs 25 May 8:00
Acid Mixing System 16 hrs 26 May 8:00
Removal of static mixer 4 hrs 26 May 8:00
Inspection, sampling and cleaning. Repair damaged portion if found. 4 hrs 26 May 12:00
Inspection and cleaning of acid dosing line. 4 hrs 26 May 16:00
Reinstall Acid Mixing 4 hrs 26 May 20:00
Steam Scrubbing System Orifice & Pipeline Inspection 32 hrs 25 May 8:00
Removal of pipe spools, 8 hrs 25 May 8:00
Inspection and cleaning of orifices 10 hrs 25 May 16:00
Removal of scales from spools 10 hrs 25 May 16:00
Replacement of gaskets 2 hrs 26 May 2:00
Reinstallation of orifices and pipe spools. 12 hrs 26 May 4:00
Reinjection line PV-5706C Sizes 12 inch ( Valve stuck 31,5 hrs 25 May 8:00
Open the valve and inspection if any minor damage can be repair 3 hrs 25 May 8:00
Cleaning the valve seat and disc 5 hrs 25 May 11:00
Dye penetrant test on both disc and valve seat 2 hrs 25 May 17:00
Contact check between valve seat and disc with prussian blue 2 hrs 25 May 19:00
Replace Gaskets 2 hrs 26 May 9:30
Re-assemble and install 3 hrs 26 May 11:30
STEAM FIELD / WELL PAD 71 hrs 24 May 19:00
Brine Accumulator - B 49,5 hrs 24 May 19:00
Remove heat insulation man hole 0,5 hrs 24 May 19:00
Remove man hole 2 hrs 25 May 8:00
Blowing & Gas Test 6 hrs 25 May 10:00
Inspection and Cleaning of Brine Accumulator Vessels - B 12 hrs 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the we 0 hrs 25 May 17:00
Joint Inspection 2 hrs 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 hrs 26 May 17:30
Separator Vessel B 49,5 hrs 24 May 19:00
Remove heat insulation man hole 0 hrs 24 May 19:00
Remove man hole 2 hrs 25 May 8:00
Blowing & Gas Test 6 hrs 25 May 10:00
Inspection and Cleaning of Brine Accumulator Vessels - B 12 hrs 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the we 0 hrs 25 May 17:00
Joint Inspection 2 hrs 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 hrs 26 May 17:30
Brine Accumulator - A 49 hrs 25 May 8:00
Remove heat insulation man hole 1 hr 25 May 8:00
Remove man hole 2 hrs 25 May 10:00
Blowing & Gas Test 4 hrs 25 May 13:00
Inspection and Cleaning of Brine Accumulator Vessels - A 12 hrs 25 May 17:00
Measurement of wall thickness at 12 points and conduct NDT of the we 0 hrs 25 May 17:00
Joint Inspection 2 hrs 26 May 18:30
Replacement of manhole gaskets & Close Man Hole 2 hrs 26 May 18:30
Separator Vessel A 58 hrs 25 May 8:00
Remove heat insulation man hole 0 hrs 25 May 8:00
Remove man hole 2 hrs 25 May 13:00
Blowing & Gas Test 4 hrs 25 May 15:00
Inspection and Cleaning of Brine Accumulator Vessels - A 18 hrs 25 May 19:00
Measurement of wall thickness at 12 points and conduct NDT of the we 6 hrs 25 May 19:00
Joint Inspection 1 hr 27 May 16:00
Replacement of manhole gaskets & Close Man Hole 2 hrs 27 May 16:00
Inspection and Cleaning of Brine Strainers - B (2 EA) 30,5 hrs 25 May 8:00
Unbolting brine strainer A (2 EA) 3 hrs 25 May 8:00
Remove Cover Braine Strainer 2 hrs 25 May 11:00
Lift Up Strainer A (2 EA) 1 hr 25 May 11:00
Cleanine Strainer 5 hrs 25 May 13:00
Cleaning Internal Strainer 5 hrs 25 May 13:00
Install Strainer 2 hrs 25 May 18:00
Replace Gasket & Install Strainer Cover 5 hrs 26 May 8:30
Inspection and Cleaning of Brine Strainers - A (2 EA) 51 hrs 25 May 8:00
Unbolting brine strainer A (2 EA) 3 hrs 25 May 8:00
Remove Cover Braine Strainer 2 hrs 25 May 13:00
Lift Up Strainer A (2 EA) 1 hr 25 May 13:00
Cleanine Strainer 5 hrs 25 May 14:00
Cleaning Internal Strainer 5 hrs 25 May 19:00
Install Strainer 2 hrs 26 May 15:30
Replace Gasket & Install Strainer Cover 5 hrs 26 May 17:30
Inspection and Cleaning of Brine Strainers - C (2 EA) @ POWER PLANT 54 hrs 25 May 8:00
Unbolting brine strainer C (2 EA) 3 hrs 25 May 8:00
Remove Cover Braine Strainer 2 hrs 25 May 13:00
Lift Up Strainer C (2 EA) 1 hr 25 May 15:00
Cleanine Strainer 5 hrs 25 May 16:00
Cleaning Internal Strainer 5 hrs 25 May 16:00
Install Strainer 2 hrs 26 May 17:30
Replace Gasket & Install Strainer Cover 5 hrs 27 May 8:00
Separation System B, Gate Valve T-3157 Sizes 4 inch 10 hrs 25 May 8:00
Open the valve and inspection if any minor damage can be repair 2 hrs 25 May 8:00
Cleaning the valve seat and disc 3 hrs 25 May 10:00
Dye penetrant test on both disc and valve seat 1 hr 25 May 14:00
Contact check between valve seat and disc with prussian blue 1 hr 25 May 15:00
Replace Gaskets 2 hrs 25 May 16:00
Re-assemble and install 2 hrs 25 May 16:00
DUMP VALVE (2 EA) 24" & 12" 53 hrs 25 May 9:00
Disconnect Power by instrument team 1 hr 25 May 9:00
Remove Valve LV 3111 -24" 4 hrs 25 May 11:00
Remove Valve LV3101 - 12" 4 hrs 25 May 11:00
Lift Up Valve & Move to laydown area 1 hr 25 May 16:00
Lift Up Valve & Move to laydown area 1 hr 25 May 17:00
Cleaning & Inspection valve 3111 -24" 8 hrs 25 May 17:00
Cleaning & Inspection valve LV3101 - 12" 8 hrs 25 May 17:00
Reinstall Valve LV 3111 - 24" 4 hrs 26 May 14:30
Reinstall Valve LV 3101 - 12" 4 hrs 26 May 18:30
Reconnect power cable 2 hrs 27 May 11:00
2 hrs 27 May 11:00
Finish
27 May 18:00
27 May 7:29
25 May 0:59
25 May 2:59
25 May 2:59
25 May 4:59
26 May 12:00
25 May 1:59
25 May 6:59
26 May 12:00
25 May 5:59
25 May 6:59
25 May 7:59
25 May 10:59
27 May 1:29
26 May 19:29
25 May 14:59
25 May 17:59
26 May 9:29
26 May 13:29
26 May 16:29
26 May 19:29
25 May 13:59
25 May 13:59
25 May 13:59
25 May 13:59
25 May 13:59
27 May 1:29
27 May 1:29
27 May 1:29
27 May 1:29
26 May 16:00
26 May 14:00
26 May 16:00
25 May 17:59
27 May 7:29
27 May 1:29
27 May 3:29
25 May 17:59
27 May 5:29
27 May 7:29
25 May 8:59
25 May 8:59
25 May 11:59
25 May 10:59
25 May 11:59
25 May 17:59
25 May 14:59
25 May 16:59
25 May 17:59
27 May 5:59
25 May 21:59
26 May 1:59
26 May 5:59
27 May 5:59
27 May 2:59
25 May 5:59
25 May 9:59
25 May 13:59
26 May 13:59
26 May 14:59
26 May 20:59
27 May 0:59
27 May 2:59
25 May 11:00
25 May 8:30
25 May 10:30
25 May 11:00
26 May 11:00
25 May 8:00
25 May 9:00
25 May 21:00
26 May 1:00
26 May 7:00
26 May 9:00
26 May 8:00
26 May 9:30
26 May 11:00
26 May 18:00
26 May 18:00
27 May 18:00
26 May 16:00
25 May 4:00
25 May 8:00
25 May 8:00
25 May 12:00
25 May 16:00
26 May 8:00
26 May 8:00
26 May 9:00
26 May 9:00
26 May 9:00
26 May 9:00
26 May 16:00
26 May 16:00
26 May 12:00
25 May 10:00
25 May 12:00
25 May 16:00
26 May 9:00
26 May 10:00
26 May 12:00
25 May 10:00
25 May 10:00
25 May 12:00
27 May 7:00
25 May 4:00
25 May 8:00
24 May 20:00
25 May 20:00
26 May 0:00
27 May 1:00
27 May 1:00
27 May 2:00
26 May 10:00
27 May 3:00
27 May 3:00
27 May 7:00
27 May 7:00
26 May 14:00
25 May 10:00
25 May 15:00
25 May 19:00
26 May 10:00
26 May 11:00
26 May 14:00
25 May 12:00
25 May 15:00
25 May 17:00
26 May 16:30
26 May 11:30
25 May 10:00
25 May 15:00
25 May 18:00
26 May 10:30
26 May 11:30
25 May 18:00
26 May 14:30
26 May 16:30
25 May 20:00
25 May 20:00
27 May 9:00
26 May 10:00
25 May 10:00
25 May 15:00
25 May 18:00
26 May 9:00
26 May 10:00
26 May 4:00
26 May 18:30
27 May 9:00
26 May 13:30
25 May 5:30
25 May 9:00
25 May 10:00
25 May 12:00
25 May 15:00
25 May 17:00
25 May 19:00
26 May 11:30
26 May 13:30
26 May 15:30
25 May 5:30
25 May 9:00
25 May 11:00
25 May 14:00
25 May 16:00
25 May 18:00
26 May 9:30
26 May 14:30
26 May 15:30
27 May 14:00
26 May 14:00
25 May 8:59
25 May 12:59
25 May 16:59
25 May 20:59
25 May 21:59
26 May 14:00
27 May 11:00
27 May 14:00
27 May 18:00
27 May 0:00
25 May 23:59
26 May 3:59
26 May 12:00
26 May 16:00
26 May 17:00
27 May 0:00
27 May 16:00
27 May 18:00
26 May 19:30
25 May 16:00
25 May 9:00
25 May 10:00
25 May 11:30
25 May 13:30
25 May 15:00
25 May 16:00
25 May 16:00
25 May 9:00
25 May 10:00
25 May 11:30
25 May 13:30
25 May 15:00
25 May 16:00
26 May 11:30
25 May 17:00
25 May 18:00
25 May 19:30
26 May 9:00
26 May 10:30
26 May 11:30
26 May 11:30
25 May 17:00
25 May 18:00
25 May 19:30
26 May 9:00
26 May 10:30
26 May 11:30
26 May 19:30
26 May 13:30
26 May 14:30
26 May 16:00
26 May 17:00
26 May 18:30
26 May 19:30
26 May 19:30
26 May 13:30
26 May 14:30
26 May 16:00
26 May 17:00
26 May 18:30
26 May 19:30
27 May 0:00
26 May 18:30
25 May 14:00
25 May 19:00
25 May 19:00
26 May 13:30
26 May 13:30
26 May 18:30
27 May 0:00
25 May 18:00
26 May 4:00
26 May 14:00
27 May 0:00
25 May 18:00
26 May 4:00
26 May 14:00
27 May 0:00
26 May 20:00
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 20:00
26 May 20:00
26 May 20:00
26 May 20:00
26 May 20:00
26 May 20:00
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 16:00
26 May 16:00
26 May 16:00
26 May 19:30
26 May 8:30
26 May 19:30
26 May 19:30
26 May 19:30
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
25 May 19:00
26 May 18:30
26 May 18:30
26 May 18:30
26 May 18:30
27 May 0:00
27 May 0:00
26 May 12:00
26 May 16:00
26 May 20:00
27 May 0:00
26 May 16:00
25 May 16:00
26 May 2:00
26 May 2:00
26 May 4:00
26 May 16:00
26 May 15:30
25 May 11:00
25 May 17:00
25 May 19:00
26 May 9:30
26 May 11:30
26 May 15:30
27 May 18:00
26 May 20:30
24 May 19:30
25 May 10:00
25 May 17:00
26 May 18:30
25 May 17:00
26 May 20:30
26 May 20:30
26 May 20:30
24 May 19:00
25 May 10:00
25 May 17:00
26 May 18:30
25 May 17:00
26 May 20:30
26 May 20:30
27 May 9:00
25 May 9:00
25 May 12:00
25 May 17:00
26 May 18:30
25 May 17:00
27 May 9:00
27 May 9:00
27 May 18:00
25 May 8:00
25 May 15:00
25 May 19:00
27 May 16:00
26 May 14:30
27 May 17:00
27 May 18:00
26 May 14:30
25 May 11:00
25 May 14:00
25 May 12:00
25 May 18:00
25 May 18:00
26 May 8:30
26 May 14:30
27 May 11:00
25 May 11:00
25 May 15:00
25 May 14:00
25 May 19:00
26 May 13:30
26 May 17:30
27 May 11:00
27 May 14:00
25 May 11:00
25 May 15:00
25 May 16:00
26 May 9:30
26 May 9:30
26 May 19:30
27 May 14:00
25 May 18:00
25 May 10:00
25 May 14:00
25 May 15:00
25 May 16:00
25 May 18:00
25 May 18:00
27 May 14:00
25 May 10:00
25 May 16:00
25 May 16:00
25 May 17:00
25 May 18:00
26 May 14:30
26 May 14:30
26 May 18:30
27 May 11:00
27 May 14:00
27 May 14:00

Potrebbero piacerti anche